Milestone payments classified as operational debt; Section 9 insolvency petition barred by three-year limitation | EPC contract remains subsisting : SC
Case Law Analysis
|Supreme Court of India

Milestone payments classified as operational debt; Section 9 insolvency petition barred by three-year limitation | EPC contract remains subsisting : SC

Milestone payments under the EPC agreement are treated as operational debt under Section 5(21) of the IBC, and the creditor’s Section 9 petition is dismissed as time-barred after three years. The ruling confirms that such contracts continue despite delays, limiting insolvency claims by contractors. This impacts EPC contractors and lenders seeking recovery in insolvency proceedings.

Rule 64 Assam Minor Mineral Rules | Statutory Royalty Demand Enforceable Even Without Extraction Permit: Gauhati HC
Case Law Analysis
|Gauhati High Court

Rule 64 Assam Minor Mineral Rules | Statutory Royalty Demand Enforceable Even Without Extraction Permit: Gauhati HC

Gauhati HC upheld a ₹40 crore royalty demand against Simplex Infrastructures for extracting minor minerals without a permit under NH-52 project, ruling Rule 64 Assam Minor Mineral Rules imposes strict liability regardless of procedural lapses. The judgment reinforces statutory compliance obligations for contractors in infrastructure projects involving mineral extraction.

Assam Minor Mineral Rules | Forest Royalty on Excavated Earth Requires Documentary Proof for Internal Reuse Exemption: Gauhati HC
Case Law Analysis
|Gauhati High Court

Assam Minor Mineral Rules | Forest Royalty on Excavated Earth Requires Documentary Proof for Internal Reuse Exemption: Gauhati HC

Gauhati HC rules that contractors must provide verifiable documentation under Assam Minor Mineral Rules to claim exemption from forest royalty on excavated earth reused internally in infrastructure projects. The court held that writ jurisdiction cannot bypass statutory compliance, setting a precedent for strict adherence to procedural proofs in mining and environmental law disputes.

Promissory Estoppel & Article 14 | State Cannot Withdraw EPC Contract Without Contractor Default: Rajasthan HC
|Rajasthan High Court

Promissory Estoppel & Article 14 | State Cannot Withdraw EPC Contract Without Contractor Default: Rajasthan HC

The Rajasthan High Court struck down the Jaipur Development Authority’s unilateral withdrawal of an EPC contract for the OTS Flyover, holding that invoking Clause 32 without evidence of contractor default violates both Article 14 and the doctrine of promissory estoppel. This ruling reinforces that state agencies cannot arbitrarily revoke contracts merely on policy grounds, setting a critical precedent for infrastructure contractors relying on state assurances.