Section 34 Arbitration Act | Arbitral Award Set Aside for Ignoring GST Evidence in Non-Tendered Works: Karnataka HC
Case Law Analysis
|Karnataka High Court

Section 34 Arbitration Act | Arbitral Award Set Aside for Ignoring GST Evidence in Non-Tendered Works: Karnataka HC

Karnataka High Court holds that an arbitral tribunal's failure to consider RA Bills showing 18% GST inclusion in non-tendered works (valued at ₹9.65 crores) constitutes patent illegality under Section 34 of the Arbitration Act. The ruling reinforces that tribunals must account for tax implications in contract disputes, impacting construction and commercial arbitration.

Contractor Entitled to Payment for Partial Performance | Unreturned Materials Must Be Deducted Based on Written Admission : Kerala HC
Case Law Analysis
|Kerala High Court

Contractor Entitled to Payment for Partial Performance | Unreturned Materials Must Be Deducted Based on Written Admission : Kerala HC

The Kerala High Court affirmed that a contractor is entitled to payment for work substantially completed, even when the contract is terminated, but must have the value of unreturned materials deducted if the contractor has formally admitted their non-return. This clarifies the legal standard for set-off in construction disputes where written admissions override speculative cost claims.

Remand Proceedings | Tribunal Cannot Overturn Binding Finding of State-Caused Delay in Construction Contracts : MP HC
Case Law Analysis
|Madhya Pradesh High Court

Remand Proceedings | Tribunal Cannot Overturn Binding Finding of State-Caused Delay in Construction Contracts : MP HC

The Madhya Pradesh High Court has ruled that when an arbitration award is remanded for fresh adjudication, the tribunal is bound by prior judicial findings on state-caused delay and cannot revisit or negate them. This reinforces the doctrine of judicial finality in construction arbitration, protecting contractors from arbitrary recalculations of delay liability even after remand.

Arbitration and Conciliation Act, Section 34 | Hindrance Register Conclusive Proof of Delay Attribution Overrides Contractual Bar to Compensation : Delhi HC
Case Law Analysis
|Delhi High Court

Arbitration and Conciliation Act, Section 34 | Hindrance Register Conclusive Proof of Delay Attribution Overrides Contractual Bar to Compensation : Delhi HC

The Delhi High Court has ruled that a contractor's delay claim is valid when supported by a government-maintained hindrance register, even if the contract purports to bar compensation. This sets a critical precedent for public infrastructure projects, affirming that administrative records of delay take precedence over boilerplate contractual exclusions, empowering contractors to seek fair redress against delayed public works.

Contractual Dispute Resolution Clause Mandates Exhaustion Before Bank Guarantee Encashment : MP HC Indore
Case Law Analysis
|Madhya Pradesh High Court

Contractual Dispute Resolution Clause Mandates Exhaustion Before Bank Guarantee Encashment : MP HC Indore

MP High Court rules that invoking a performance bank guarantee without first exhausting contractual dispute resolution mechanisms violates agreement terms and natural justice. The ruling reinforces that parties must adhere to prescribed contractual remedies before resorting to bank guarantee encashment, impacting construction contracts and commercial agreements.