The Madhya Pradesh High Court directs municipal bodies to decide demolition petitions within 45 days, emphasizing procedural fairness and public safety over indefinite delay.

Cassie News NetworkCassie News Network
Jan 22, 2026, 11:10 PM
5 min read
Be the first to share in your circle
Municipal Authorities Must Decide Demolition Requests Within Reasonable Time | Public Safety and Procedural Fairness : High Court of Madhya Pradesh

The High Court of Madhya Pradesh has directed municipal authorities to conclude pending decisions on the demolition of a dilapidated building within 45 days, affirming that public safety cannot be subordinated to bureaucratic inertia. The order underscores the state’s duty to act decisively when structures pose imminent threats to life, while mandating due process for all affected parties.

The Verdict

The petitioners won. The High Court held that municipal authorities must decide pending demolition requests involving hazardous structures within 45 days of receiving a certified copy of the order. The court directed the authorities to ascertain the legal status of occupants before any action and to conduct demolition strictly in accordance with law, with due regard to safety protocols. No final determination on ownership or encroachment was made by the court.

Background & Facts

The petitioners, residents and concerned citizens, filed a writ petition seeking the demolition of a structurally unsound building in Bhopal that had been identified as a serious public safety hazard. Representations had been submitted to the Municipal Corporation of Bhopal and other concerned authorities since at least December 2025, but no final decision had been rendered despite repeated follow-ups. The petitioners alleged that the building, occupied by private respondents without any lawful tenancy agreement, was in a state of advanced disrepair and posed an imminent risk of collapse.

The petitioners sought a writ of mandamus compelling the authorities to demolish the structure immediately, with police assistance if necessary, and to evict all illegal occupants to facilitate safe execution. They relied on Annexure P/3, a structural assessment report, and Annexure P/7, a prior notice of demolition issued by the authorities, to substantiate the urgency of the matter.

The respondents, represented by the Government Advocate, did not dispute the hazardous condition of the building but contended that the matter was under internal review and that due process required time to verify ownership and tenancy claims before any action.

The petition had been pending for several months without resolution, prompting the petitioners to approach the High Court under Article 226 of the Constitution.

The central question was whether municipal authorities may indefinitely delay action on a verified threat to public safety pending internal review, or whether the state’s duty to protect life under Article 21 imposes a time-bound obligation to decide such matters. Additionally, whether the court may direct a timeline for decision-making in the absence of a statutory mandate.

Arguments Presented

For the Petitioner

The petitioners argued that the right to life under Article 21 includes the right to live in a safe environment, and that prolonged inaction by municipal authorities in the face of a documented structural hazard constitutes a violation of this fundamental right. They cited precedents where courts have issued mandatory directions to local bodies to remove imminent threats to public safety, emphasizing that administrative delay cannot override the urgency of life preservation. They relied on the report annexed to the petition as conclusive evidence of danger and contended that the absence of a rent agreement rendered the occupants’ possession unlawful, thereby removing any legal barrier to demolition.

For the Respondent

The respondents argued that demolition is a complex administrative process requiring verification of title, notice to all parties, and compliance with procedural safeguards under municipal bye-laws. They contended that the court should not interfere in the administrative domain unless there was clear mala fide or gross negligence, and that the matter was already under consideration. They emphasized that premature demolition without verifying occupancy rights could lead to legal challenges and potential compensation claims.

The Court's Analysis

The Court rejected the notion that administrative convenience could justify indefinite delay in addressing a known threat to public safety. It held that the state’s obligation under Article 21 is not contingent upon the existence of a specific statutory timeline but arises from the inherent duty to protect life. The Court observed that the petitioners had provided credible documentation, including a structural assessment report and a prior demolition notice, which together created a prima facie case for urgent action.

"The right to life does not permit the state to remain passive while a building, known to be structurally unsound, continues to endanger the lives of passersby and residents alike."

The Court clarified that while it was not determining whether the occupants were encroachers, it was imperative that the authorities make this determination before proceeding with demolition. This was not an endorsement of the occupants’ claim but a recognition that due process must be followed even in matters of public safety. The Court emphasized that procedural fairness does not equate to procedural delay, particularly when lives are at stake.

The 45-day timeline was not imposed arbitrarily but was calibrated to allow sufficient time for notice, hearing, and verification, while preventing further stagnation. The Court noted that the authorities had already issued a notice in December 2025, indicating that the matter was not entirely dormant, and therefore, a final decision was well within their capacity.

What This Means For Similar Cases

This judgment establishes a clear precedent for petitioners seeking enforcement of public safety obligations against municipal bodies. Practitioners may now cite this order to demand time-bound decisions in cases involving hazardous structures, especially where structural reports and prior notices exist. The 45-day window, while not a statutory mandate, is likely to be adopted as a benchmark in similar writ petitions across states.

The ruling does not create a blanket right to immediate demolition but reinforces that authorities must act with reasonable expedition once a credible threat is documented. It also clarifies that verification of occupancy rights is a necessary procedural step, not a justification for delay. Future litigants should ensure that petitions are supported by expert reports and prior administrative correspondence to strengthen the prima facie case for urgency.

The judgment also implicitly limits the scope of judicial intervention: courts will not adjudicate ownership disputes but will compel authorities to resolve them within a reasonable timeframe. This preserves the separation of powers while enforcing constitutional obligations.

Case Details

Harpreet Singh Saluja and Others v. Municipal Corporation Bhopal and Others

2026:MPHC-JBP:5741
Court
High Court of Madhya Pradesh at Jabalpur
Date
21 January 2026
Case Number
WP-2256-2026
Bench
Vishal Mishra
Counsel
Pet: Kapil Sharma
Res: A.S. Baghel
0