
The Karnataka High Court recently delivered a nuanced judgment in a commercial dispute involving the refurbishment of a Sewage Treatment Plant (STP) and subsequent Operation & Maintenance (O&M) works. The Court upheld the plaintiff’s claim for payment while modifying the decree amount, emphasizing that minor deficiencies in performance do not absolve the defendant of its payment obligations under the contract. This judgment reinforces the principle that contractual liability persists even when works are substantially completed, provided the deficiencies do not fundamentally vitiate the contract’s purpose.
Background & Facts
The Dispute
The dispute arose between M/s. MVJ College of Engineering Venkatesha Education Trust (appellant/defendant) and M/s. Living Waterfine Technologies Pvt. Ltd. (respondent/plaintiff). The plaintiff was engaged to refurbish the defendant’s non-operational STP and provide O&M services. Despite completing the refurbishment and partial O&M works, the defendant failed to pay the outstanding amounts, leading to litigation.
Key Facts
- 14.06.2017: Plaintiff submitted a quotation for refurbishing the STP at ₹29,98,900 + GST, along with O&M charges of ₹57,500 per month (with a 10% annual increase).
- 15.06.2017: Defendant issued a purchase order accepting the plaintiff’s quotation. The scope of work excluded civil works, which were to be carried out by the defendant.
- 01.07.2017 to 25.09.2017: Plaintiff supplied materials for refurbishment, raising two invoices on 16.08.2017:
- ₹24,58,207 (for materials)
- ₹6,94,973 (for design, repair, and erection works).
- 15.06.2017 and 06.09.2017: Defendant made partial payments totaling ₹23,09,778, leaving a balance of ₹8,43,402 for refurbishment.
- 21.09.2017 to 16.08.2018: Plaintiff carried out O&M works and raised six invoices totaling ₹8,82,050, none of which were paid.
- 27.01.2018: Joint inspection conducted in the presence of an independent observer. The minutes (Ex.D2) noted that the STP was functioning smoothly for three weeks prior to the inspection, though minor issues were identified.
- 02.08.2018: Plaintiff submitted test reports (Ex.P10) demonstrating the STP’s functionality, as stipulated by the independent observer.
Procedural History
- Com.OS No. 25013/2019: Plaintiff filed a suit before the LXXXVI Additional City Civil and Sessions Judge, Bengaluru (Commercial Court)






