
The Madhya Pradesh High Court recently clarified the enforceability of risk purchase clauses in commercial contracts, even when payment delays occur. The judgment underscores that contractual terms prevail when parties consciously agree to conditions like time-bound delivery, and mere payment delays do not absolve the defaulting party of liability for additional procurement costs. The Court also refined the interest rate under Section 34 of the Code of Civil Procedure (CPC), aligning it with prevailing commercial lending rates.
Background & Facts
The Dispute
The appellant, M/s Shrikrishna Chemical, Indore, entered into a contract with the Union of India for the supply of 60 Metric Tons (MT) of Caustic Soda Flakes at Rs. 12,195 per MT. The purchase order dated 10.05.1994 mandated delivery of 30 MT within 3-6 weeks and the remaining 30 MT within 6 months. The appellant supplied only 18 MT in two lots but failed to deliver the balance 42 MT, compelling the respondent to procure the material from the open market at an additional cost of Rs. 2,41,397.
Key Facts
- 10.05.1994: Purchase order issued for 60 MT Caustic Soda Flakes
- 07.07.1994: First lot of 9 MT supplied; payment made via Bank Draft on 03.08.1994
- 30.07.1994: Second lot of 9 MT supplied; payment made on 16.09.1994
- 07.11.1994, 07.12.1994, 21.12.1994: Respondent issued reminders for balance supply
- Contract validity: Initially till 10.11.1994, extended to 30.11.1994 at appellant’s request
- Risk Purchase Clause (Term No. 10): Authorized respondent to procure material from the market at appellant’s cost if delivery failed
Procedural History
- Civil Suit No. 8B/97: Filed by respondent before 2nd Additional District Judge, Neemuch for recovery of Rs. 2,41,397 with 18% interest
- 15.03.2000: Trial Court decreed in favor of respondent, directing recovery of Rs. 2,41,397 with 18% interest from the date of suit till realization
- First Appeal No. 612/2000: Filed by appellant before Madhya Pradesh High Court, Indore Bench
The Parties' Positions
Appellant’s Defence
- Payment for supplied material was delayed beyond 10 days, preventing further procurement
- Respondent’s delay in payment absolved appellant of liability under the contract
- 18% interest was exorbitant and not aligned with Section 34 CPC
- Relied on Union Bank of India v. Parasuram (2003(3) CCC 489), arguing interest should reflect nationalized bank lending rates
Respondent’s Contention
- Appellant knowingly accepted the purchase order with Term No. 10 (Risk Purchase Clause)
- Payment delays were not undue: First payment made on 03.08.1994 (within 27 days), second on 16.09.1994 (within 48 days)
- Appellant failed to supply material even after contract extension till 30.11.1994
- 18% interest was justified as the transaction was commercial and prevailing rates were high
Relief Sought
- Appellant: Set aside the trial court’s decree and dismiss the suit
- Respondent: Uphold the decree with 18% interest
The Legal Issue
The appeal raised two critical questions:
- Whether the risk purchase clause in the contract remains enforceable despite alleged payment delays by the respondent?
- Whether the interest rate of 18% awarded under Section 34 CPC was excessive given prevailing commercial lending rates?
Arguments Presented
For the Appellant
- Payment delays by the respondent frustrated the contract, absolving the appellant of liability
- Section 34 CPC mandates interest alignment with nationalized bank rates, which were lower than 18%
- Relied on Union Bank of India v. Parasuram to argue that commercial interest rates should reflect lending practices
For the Respondent
- Term No. 10 explicitly made delivery the essence of the contract
- Payment delays were not material as the contract period was extended and payments were eventually made
- 18% interest was justified as the transaction was commercial and prevailing rates were high
The Court's Analysis
The Court conducted a two-pronged analysis of the dispute:
Enforceability of Risk Purchase Clause
The Court held that contractual terms prevail when parties consciously agree to conditions like time-bound delivery. The appellant’s defence of payment delays was factually unsustainable because:
- Payments for supplied material were made on 03.08.1994 and 16.09.1994, well within the contract validity period
- The contract was extended till 30.11.1994 at the appellant’s request, yet no further supply was made
- Term No. 10 explicitly authorized the respondent to procure material from the market at the appellant’s cost if delivery failed
"The defence of the appellant that the payment of the supplied material was not made within 10 days, therefore, the appellant failed to procure the further material, is imaginary and not based on factual matrix of the case... The appellant failed to supply the material even in the extended period."
The Court emphasized that commercial contracts must be interpreted strictly, and breach of essential terms (like delivery timelines) triggers liability under risk purchase clauses.
Interest Rate Under Section 34 CPC
The Court examined Section 34 CPC, which grants discretion to trial courts to award interest from the date of suit if no agreed rate exists. While upholding the decree for recovery of Rs. 2,41,397, the Court modified the interest rate:
- Prevailing commercial lending rates at the time of the transaction were lower than 18%
- Section 34 CPC requires interest to be just and reasonable, aligning with nationalized bank rates
- Citing Union Bank of India v. Parasuram, the Court reduced the interest to 12%
"Considering the fact that at the time of subject transaction and filing of the suit prevailing rate of interest at which moneys were lent or advanced by the nationalized bank was lesser than 18% per annum, in view of this Court the decree for payment of interest is required to be modified to the extent that interest will be payable @12% per annum instead of 18%."
The Verdict
The appeal was partly allowed with the following directions:
- The decree for recovery of Rs. 2,41,397 was upheld in favor of the respondent
- The interest rate was modified to 12% per annum from the date of filing of the suit till realization
- The appellant was directed to bear the costs of litigation in both the trial and appellate courts
- The decree was drawn up accordingly, and the trial court’s record was directed to be sent back with a copy of the judgment
What This Means For Similar Cases
Risk Purchase Clauses Are Strictly Enforceable
- Commercial contracts with risk purchase clauses will be interpreted literally if terms are clear
- Payment delays do not absolve liability if the contract period is extended and payments are eventually made
- Essential terms (like delivery timelines) cannot be circumvented by technical defences
Interest Rates Under Section 34 CPC Must Align With Commercial Lending Practices
- Section 34 CPC grants discretion but mandates reasonable interest rates
- Courts will modify excessive interest to reflect nationalized bank lending rates at the time of the transaction
- Commercial transactions may justify higher interest, but prevailing rates serve as a benchmark
Burden of Proof Lies on the Defaulting Party
- The defaulting party must prove factual impossibility (e.g., payment delays making supply impossible)
- Imaginary defences (like alleged payment delays) will not succeed if contractual timelines are extended
- Documentary evidence (e.g., purchase orders, payment receipts) is critical to establish breach or compliance






