
The Bombay High Court has clarified that cooperative societies cannot impose additional membership conditions beyond those tied to the actual source of land allotment. This ruling reinforces statutory compliance over self-imposed procedural barriers, offering critical guidance to housing societies and regulatory authorities across Maharashtra.
Background & Facts
The Dispute
The petitioner, Pawan Heights Cooperative Housing Society Ltd., resisted the enrollment of Respondent No. 4 as a member, invoking Bye Law No. 17(c) of its registered bye-laws. The society contended that admission to membership required prior approval from the District Collector, as the land on which the society was built was originally allotted by the Government. The respondents, including the Deputy Registrar of Cooperative Societies and other authorities, directed the society to admit the member, relying on MHADA’s formal approval of the flat transfer.
Procedural History
- 2022: MHADA issued a communication regularizing the transfer of the flat to Respondent No. 4.
- 2023: Respondent No. 4 applied for membership; the society refused citing Bye Law 17(c).
- 2025: The Deputy Registrar, under Section 23(2) of the Maharashtra Cooperative Societies Act, 1960, directed the society to admit the applicant.
- 2026: The society filed two writ petitions challenging the direction, which were consolidated by the Court.
Relief Sought
The petitioner sought quashing of the Deputy Registrar’s order, arguing that admission without Collector’s approval violated the society’s bye-laws and the land grant conditions.
The Legal Issue
The central question was whether Bye Law No. 17(c) of a cooperative society requires approval from the District Collector when the land was allotted by MHADA, or whether approval from the actual allotting authority - MHADA - suffices under the statutory framework.
Arguments Presented
For the Petitioner
The petitioner argued that Bye Law No. 17(c) mandates cumulative approval from both the Government and the Collector, irrespective of the land’s chain of allotment. It relied on the literal wording of the bye-law, which mentions "Collector" and "land grant terms as applicable," asserting that any deviation undermines the society’s autonomy and the integrity of land use conditions. It cited Society for Urban Development v. Registrar to argue that bye-laws are binding unless ultra vires.
For the Respondent
The respondents contended that the bye-law’s requirement of approval is conditional upon the source of the land grant. Since MHADA, not the Government, was the direct allotting authority, its approval was sufficient. They emphasized that the society’s rights derive from MHADA’s allotment, not direct government grant, and that insisting on Collector’s approval would be legally and factually untenable. They relied on State of Maharashtra v. Kalyani Cooperative Society to argue that statutory interpretation must reflect factual reality.
The Court's Analysis
The Court undertook a contextual reading of Bye Law No. 17(c), rejecting a rigid textual interpretation. It emphasized that the proviso - "provided the land has been allotted to the Society by the Government, CIDCO, MHADA, SRA or any other authority" - is not decorative but operative. The phrase "given" in the bye-law was interpreted purposively to include allotment, transfer, or lease by any competent authority, not merely direct grant.
"The insistence on permission of the Collector would arise in a situation where the land has been granted directly by the Government to the society and the terms of such grant reserve supervisory control in favour of the Collector. That is not the factual position here."
The Court noted that the society’s entitlement to the land flows exclusively through MHADA, with no privity between the Government and the society. Therefore, requiring Collector’s approval would impose an extraneous condition not contemplated by the bye-law’s structure or the factual matrix. MHADA’s 2022 communication, which regularized the transfer, constituted a valid, conscious exercise of its statutory authority. The Court held that to demand additional approvals from non-relevant authorities would render the statutory scheme under the Maharashtra Cooperative Societies Act, 1960 ineffective and defeat the purpose of member inclusion.
The Verdict
The petitioner’s writ petitions were dismissed. The Court held that approval from the actual land-allotting authority - MHADA - is sufficient to satisfy Bye Law No. 17(c), and that requiring approval from the District Collector in the absence of a direct government grant is legally unsustainable.
What This Means For Similar Cases
Approval Must Match the Source of Land Allotment
- Cooperative societies cannot impose approval requirements from authorities that had no role in the land’s original allotment.
- Practitioners must verify the chain of land title before challenging membership admissions under bye-laws.
- MHADA, CIDCO, SRA, or other statutory bodies’ approvals are binding where they are the direct allotting authorities.
Bye-Laws Are Not Self-Executing; They Must Be Interpreted Contextually
- Courts will not uphold bye-law provisions that contradict the factual origin of land rights.
- Literal interpretations of bye-laws will be rejected if they lead to absurd or impractical outcomes inconsistent with statutory intent.
- Societies must align their internal rules with the actual legal source of their land rights.
Regularization by Allotting Authority Is Equivalent to Prior Approval
- Formal communications from MHADA or similar bodies regularizing transfers constitute valid approval under Bye Law No. 17(c).
- Practitioners should treat such communications as conclusive evidence of compliance, not as mere formalities.
- Challenges based on "lack of Collector’s approval" will fail where the land was not directly granted by the Government.






