
The Andhra Pradesh High Court has reaffirmed that procedural rigidity must yield to substantial justice in commercial disputes, holding that a reasonable explanation for delayed filing of documents - such as misplacement - cannot be summarily rejected merely due to inordinate delay. This judgment clarifies the judicial approach to document production under the Commercial Courts Act, 2015, and the amended CPC.
Background & Facts
The Dispute
The dispute arose from a contract between the Government of Andhra Pradesh (through its Roads and Buildings Department) and M/s R S V Constructions Pvt Ltd for construction work. A commercial suit (C.O.S.No.16 of 2020) was filed by the respondent/plaintiff seeking payment for work allegedly not completed or defective. The petitioners/defendants, being the State, filed a written statement in which they reserved the right to file an additional written statement if new facts emerged.
Key Facts
- The commercial suit was originally filed in 2020 and later transferred to the Special Court for Trial and Disposal of Commercial Disputes, Vijayawada, as C.S.No.2 of 2019.
- The written statement was filed by the defendants in 2019.
- At the time of filing the written statement, the defendants did not produce 25 documents, including the original contract agreement and correspondence between the parties.
- The defendants claimed these documents were misplaced in their office and could not be located during the initial stages of litigation.
- The documents were traced and identified in early 2025.
- On 15.04.2025, the defendants filed I.A.No.114 of 2025 seeking leave to produce the 25 documents under Order XI Rule 7 of the CPC.
- The documents include:
- Sl.No.1: The original contract agreement between the parties
- Sl.Nos.2 - 25: Correspondence exchanged during execution of the work, addressed to the plaintiff
- All documents are admitted to be between the parties and not newly created or fabricated.
- The respondent/plaintiff did not dispute the authenticity or relevance of the documents.
Procedural History
- 2019: Written statement filed by defendants in the commercial suit.
- 15.04.2025: Application (I.A.No.114 of 2025) filed seeking leave to produce 25 documents under Order XI Rule 7 CPC.
- 18.06.2025: Special Judge dismissed the application, holding that:
- The delay of over five years was inordinate.
- The reason of ‘misplacement’ was vague and insufficient.
- Order XI Rule 7 CPC was incorrectly invoked.
- The Commercial Courts Act, 2015, bars belated document production.
- 28.06.2025: Civil Revision Petition No.1860 of 2025 filed before the Andhra Pradesh High Court.
- 22.04.2026: Case reserved for judgment.
- 07.05.2026: Judgment pronounced.
The Parties' Positions
For the Petitioners/Defendants (State of Andhra Pradesh)
- The documents were genuinely misplaced during office relocation and were only traced in early 2025.
- The documents are not new - they are the contract and contemporaneous correspondence, both known to and exchanged with the plaintiff.
- No prejudice will arise to the plaintiff as the documents are not ex parte or fabricated.
- The State, as a public entity, has no motive to manipulate evidence.
- The documents are crucial for adjudication and directly impact public exchequer.
- The application was filed immediately upon discovery.
- The invocation of Order XI Rule 7 was a technical error; the substance of the application sought relief under Order XI Rule 1(7) and (10), which govern document production in commercial disputes.
For the Respondent/Plaintiff
- The Commercial Courts Act, 2015, mandates strict compliance with timelines for document production.
- Order XI Rule 7 CPC is inapplicable - it pertains to striking interrogatories, not document production.
- The defendants failed to show sufficient cause for a delay of over five years.
- The affidavit merely stated documents were ‘misplaced’ without specifying when they were lost or found.
- The defendants had access to the documents at the time of filing the written statement and their non-production was due to negligence.
- Allowing belated production defeats the object of expeditious disposal under the Commercial Courts Act.
- Reliance was placed on Sudhir Kumar v. Vinay Kumar G.B. and Ambalal Sarabhai Enterprises Ltd. v. K.S. Infraspace LLP to argue that procedural compliance is non-negotiable.
Relief Sought
The petitioners sought:
- Setting aside of the order dated 18.06.2025 dismissing I.A.No.114 of 2025.
- Permission to produce the 25 documents in the suit.
- No order as to costs.
The Legal Issue
Can a party in a commercial dispute obtain leave under Order XI Rule 1(7) and (10) of the CPC to produce documents belatedly, where the delay exceeds five years, but the explanation offered is misplacement and the documents are essential, non-fabricated, and known to both parties?
Arguments Presented
For the Appellant/Petitioner
The petitioners relied on Sugandhi (Dead) by Legal Representatives v. P. Rajkumar (2020) 10 SCC 706, which held that procedural rules are handmaids of justice and leave to produce documents should be granted liberally if no prejudice is caused and the documents are essential. They emphasized that misplacement negates actual possession at the relevant time, thus triggering the exception under Order XI Rule 1(3). They further cited C-Star Engineers & Contractors v. IDMC Limited (2025 SCC Online AP 51), a coordinate bench judgment of the same High Court, which applied Sugandhi to permit document production despite delay due to office shifting. They argued that the invocation of Order XI Rule 7 was a technical misstatement, and courts must look at the substance of the application under M.T. Khan v. Government of Andhra Pradesh (2004) 2 SCC 267 and Union of India v. Khazan Singh (1993 Supp 1 SCC 583).
For the Respondent/State
The respondent contended that the Commercial Courts Act, 2015, and the amended CPC impose strict timelines to ensure speed and efficiency. They argued that Order XI Rule 7 is irrelevant and that the correct provisions are Rule 1(7) and (10), which do not permit belated production without cogent reasons. They relied on Estralla Rubber v. Dass Estate (P) Ltd. (2001) 8 SCC 97 and P. Udaya Bhaskara Reddy v. Sreepada Real Estates (2024 SCC Online AP 4102) to argue that the High Court cannot act as an appellate court to correct errors of fact or law unless there is flagrant injustice. They asserted that the ‘misplacement’ explanation was vague, uncorroborated, and an afterthought, and that allowing such documents would undermine the statutory scheme.
The Court's Analysis
The Court began by addressing the procedural misstep: the application was filed under Order XI Rule 7 CPC, which deals with striking interrogatories, not document production. However, citing M.T. Khan, Union of India v. Khazan Singh, and State of Karnataka v. Krishnaji Srinivas Kulkarni (1994) 2 SCC 558, the Court held that a wrong or omitted citation of a legal provision does not invalidate the application if the court has jurisdiction to grant the relief sought. The Court treated the application as one under Order XI Rule 1(7) and (10) CPC, which govern document production in commercial disputes.
The Court then turned to the core issue: whether the delay of over five years and the explanation of ‘misplacement’ were sufficient to warrant leave. The Court rejected the notion that delay alone is fatal. It emphasized that the documents were not new - they were the contract and correspondence between the parties, both of which the plaintiff had received and responded to. The respondent did not dispute their relevance or authenticity.
The Court placed decisive reliance on Sugandhi v. P. Rajkumar (2020) 10 SCC 706, wherein the Supreme Court held:
"Procedure is the handmaid of justice. Procedural and technical hurdles shall not be allowed to come in the way of the court while doing substantial justice. If the procedural violation does not seriously cause prejudice to the adversary party, courts must lean towards doing substantial justice rather than relying upon procedural and technical violation."
The Court noted that the defendants’ affidavit, while brief, stated the documents were misplaced and only traced in 2025. The plaintiff did not challenge this assertion. The Court held that misplacement, even without precise dates, logically implies absence of possession at the time of filing the written statement, thereby satisfying the condition under Order XI Rule 1(3) that the document was not in the party’s possession at the relevant time.
The Court further cited its own coordinate bench’s decision in C-Star Engineers, which held that the phrase ‘reasonable cause’ must be interpreted liberally to advance substantial justice. The Court observed that rejecting the application on technical grounds would cause greater injustice by depriving the Special Court of essential evidence in a case involving public funds.
The Court also rejected the respondent’s reliance on Estralla Rubber and P. Udaya Bhaskara Reddy, noting that those cases dealt with the High Court’s supervisory jurisdiction under Article 227, not the power to grant leave under Order XI Rule 1. The Special Judge’s order was not a flagrant violation of law but a misapplication of procedural flexibility.
"The rejection of such an application on technicalities would further render into unwarranted delay which would defeat the very purpose of the provisions of Commercial Courts Act, 2015 and the amendments made to the Civil Procedure Code under Order XI Rule 1 as applicable to the commercial disputes."
The Verdict
The Civil Revision Petition was allowed. The order dated 18.06.2025 dismissing I.A.No.114 of 2025 was set aside. The application for leave to produce the 25 documents was allowed. The documents shall be taken on file in C.O.S.No.16 of 2020. There shall be no order as to costs. All pending miscellaneous applications shall stand closed.
What This Means For Similar Cases
Reasonable Cause Trumps Mechanical Delay
- Practitioners must now argue that delay alone is not dispositive; the nature of the documents and the reason for non-production are decisive.
- Misplacement, even without exact dates, can constitute reasonable cause if the documents are essential and not fabricated.
- Courts must distinguish between willful non-compliance and genuine oversight.
Substantive Justice Over Procedural Rigidity
- The Commercial Courts Act’s goal of speed does not justify denying access to critical evidence.
- The burden shifts to the opposing party to show actual prejudice from belated production - not mere delay.
- Courts must interpret Order XI Rule 1(7) and (10) liberally, as procedural rules are meant to serve justice, not obstruct it.
Strategic Implications for Document Management
- Parties must maintain meticulous document logs and retention policies to avoid claims of misplacement.
- If documents are lost, immediate action upon discovery is critical - delay beyond filing the written statement must be explained without delay.
- Applications for leave should always cite Order XI Rule 1(7) and (10) explicitly to avoid procedural challenges.






