NH Act Acquisition | Solatium & Interest Computed Under 1894 Act for Awards Pre-Dating 01.01.2015 (2013 Act Applicability) : SC
Case Law Analysis
|Supreme Court of India

NH Act Acquisition | Solatium & Interest Computed Under 1894 Act for Awards Pre-Dating 01.01.2015 (2013 Act Applicability) : SC

The Supreme Court ruled that for National Highways Act acquisitions, solatium and interest are payable but must be calculated under the 1894 Land Acquisition Act when the Competent Authority's award pre-dates 1 January 2015 - the date the 2013 RFCTLARR Act was extended to highway projects. The 2013 Act's enhanced compensation regime does not apply retrospectively to finalised awards, directly impacting landowners with pre-2015 awards.

Delay bars re-determination of land acquisition compensation under RFCTLARR Act, 2013 | Madras HC (Madurai Bench)
Case Law Analysis
|Madras High Court

Delay bars re-determination of land acquisition compensation under RFCTLARR Act, 2013 | Madras HC (Madurai Bench)

Applicants seeking fresh compensation for land acquired under the National Highways project were denied because the court held that the statutory limitation period under the RFCTLARR Act, 2013, had expired, invoking the fence-sitter doctrine. The ruling confirms that delayed claims for re-determination are barred, affecting all land-acquisition claimants.

RFCTLARR Act Mandates Compensation Methodology for Pipeline Acquisitions Under P&MP Act : Gauhati HC
|Gauhati High Court

RFCTLARR Act Mandates Compensation Methodology for Pipeline Acquisitions Under P&MP Act : Gauhati HC

Gauhati High Court rules that land acquisitions for pipeline projects under the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act must follow the compensation framework of the RFCTLARR Act, 2013. The judgment ensures landowners receive fair compensation as per the 2015 Removal of Difficulties Order, impacting all right-of-user acquisitions by government entities.

RFCTLARR Act 2013 | Mandatory Land Acquisition Procedure Must Precede Demolition or Marking of Property : AP HC
Case Law Analysis
|Andhra Pradesh High Court

RFCTLARR Act 2013 | Mandatory Land Acquisition Procedure Must Precede Demolition or Marking of Property : AP HC

Andhra Pradesh High Court rules that authorities cannot demolish or mark properties under land acquisition without strict compliance with the RFCTLARR Act, 2013. The judgment reinforces that bypassing statutory due process violates constitutional rights under Articles 14, 21, and 300A, setting a precedent for property owners facing arbitrary state action.

RFCTLARR Act, Section 30 | Market Value at Preliminary Notification Date Mandatory for Compensation; Fraudulent Consent Voids Acquisition : Andhra Pradesh HC
Case Law Analysis
|Andhra Pradesh High Court

RFCTLARR Act, Section 30 | Market Value at Preliminary Notification Date Mandatory for Compensation; Fraudulent Consent Voids Acquisition : Andhra Pradesh HC

Andhra Pradesh HC rules that compensation under the RFCTLARR Act must be calculated based on market value as of the preliminary notification date, not suppressed rates. The court also invalidated consent obtained through misrepresentation of compensation structure, holding it void due to fraud. Landowners facing acquisition disputes can now challenge compensation awards based on post-notification market fluctuations or fraudulent consent.