Contingent Development Rights Not Valued As Present Rights Under Article 5(g-a)(i) | Maharashtra Stamp Act : Bombay HC
Case Law Analysis
|Bombay High Court

Contingent Development Rights Not Valued As Present Rights Under Article 5(g-a)(i) | Maharashtra Stamp Act : Bombay HC

The Bombay High Court held that stamp duty on a Joint Development Agreement cannot be levied on future contingent development rights as if they were present vested rights, quashing orders that inflated valuation beyond rights existing on the execution date. The ruling clarifies that valuation under Article 5(g-a)(i) must reflect only the development rights actually transferred at the time of agreement execution, protecting developers from excessive duty demands on speculative future entitlements.

Maharashtra Stamp Act Article 25 | No Additional Stamp Duty on Conveyance Deed After Registered Agreement for Sale Is Deemed Conveyance : Bombay HC
Case Law Analysis
|Bombay High Court

Maharashtra Stamp Act Article 25 | No Additional Stamp Duty on Conveyance Deed After Registered Agreement for Sale Is Deemed Conveyance : Bombay HC

The Bombay High Court has ruled that once stamp duty is paid on a registered Agreement for Sale deemed a conveyance under Article 25 of the Maharashtra Stamp Act, no further duty is payable on the subsequent Conveyance Deed. This prevents double taxation in property transactions and provides clarity to housing societies and buyers navigating post-agreement transfers.