Consent Award Indemnity Clause Triggers Immediate Payment Obligation Upon Liability Crystallisation : SC
Case Law Analysis
|Supreme Court of India

Consent Award Indemnity Clause Triggers Immediate Payment Obligation Upon Liability Crystallisation : SC

The Supreme Court ruled that an indemnity clause in a consent award becomes enforceable immediately upon crystallisation of liability, without awaiting final judicial confirmation. This decision clarifies that parties cannot delay indemnity payments under arbitration awards, impacting commercial dispute resolutions involving indemnity contracts.

Section 70 Contract Act | Quantum Meruit Recovery Allowed for Unregistered Firm Despite Partnership Act Bar : Madras HC
Case Law Analysis
|Madras High Court

Section 70 Contract Act | Quantum Meruit Recovery Allowed for Unregistered Firm Despite Partnership Act Bar : Madras HC

Madras HC rules that an unregistered partnership firm can recover payment for goods supplied under Section 70 of the Contract Act, overriding the bar under Section 69(2) of the Partnership Act. The court dismissed the MSMED Act interest claim due to the absence of a formal contract, reinforcing the principle of quantum meruit for non-contractual supplies.

Section 64 Contract Act | Developer’s FSI Purchase Price Must Be Restored Upon Termination of Redevelopment Agreement : Bombay HC
Case Law Analysis
|Bombay High Court

Section 64 Contract Act | Developer’s FSI Purchase Price Must Be Restored Upon Termination of Redevelopment Agreement : Bombay HC

Bombay High Court rules that termination of a redevelopment agreement does not entitle the developer to retain the FSI purchase price, as Section 64 of the Contract Act mandates restitution to prevent unjust enrichment. The society is directed to refund Rs. 7.08 crore to the developer, reinforcing contractual fairness in property disputes.