Case Law Analysis

State Must Pay Admitted Dues Without Unreasonable Delay | Article 14 and 21 Mandate : Andhra Pradesh High Court

The Andhra Pradesh High Court has ruled that withholding an admitted contractual payment by the state, even without malice, violates Articles 14 and 21. Payment must be made within six weeks.

Cassie News NetworkCassie News Network
Jan 30, 2026, 12:22 AM
4 min read
Be the first to share in your circle
State Must Pay Admitted Dues Without Unreasonable Delay | Article 14 and 21 Mandate : Andhra Pradesh High Court

When a state entity admits liability for contractual payments but delays disbursement without legal justification, it crosses the line from administrative delay into constitutional violation. The Andhra Pradesh High Court has now firmly held that such inaction, even if not malicious, violates the state’s duty under Articles 14 and 21 of the Constitution. This judgment reinforces that public bodies cannot treat contractual obligations as optional or subject to bureaucratic inertia.

Background & Facts

The Dispute

The petitioner, Vyshno Constructions, executed road and building works under Agreement No.66/2023-24 dated 30.12.2023 with the State of Andhra Pradesh. The work was completed and certified through official Measurement Books. The first two progress bills were paid in full. The third and final bill, for a net amount of Rs.28,69,870, was generated on the Nidhi portal on 24.07.2025 and approved by the Pay and Accounts Officer on 30.07.2025. Despite this, the amount remained unpaid due to pending fund clearance.

Procedural History

  • 30.12.2023: Agreement executed between petitioner and state.
  • July 2025: Final bill approved by PAO and transmitted for payment.
  • October 2025: Petitioner filed Writ Petition No.31295/2025 under Article 226 seeking payment and interest.
  • January 2026: Hearing before Justice Tarlada Rajasekhar Rao.

Relief Sought

The petitioner sought a writ of mandamus directing the respondents to pay the admitted amount of Rs.28,69,870 with 12% interest from the date of bill approval, and declared the delay as arbitrary and violative of Articles 14 and 21.

The central question was whether withholding an admitted contractual payment by a state entity, without any legal or factual dispute, constitutes a violation of Articles 14 and 21 of the Constitution, thereby justifying judicial intervention under Article 226.

Arguments Presented

For the Petitioner

Counsel argued that the state had admitted the liability through certified Measurement Books and PAO approval. The continued non-payment, despite no pending audit, dispute, or contractual condition, amounted to arbitrary action. Reliance was placed on D.F.O., South Kheri v. Ram Sanehi Singh to assert that state inaction motivated by administrative apathy or fiscal delay, even if not mala fide, still breaches constitutional obligations.

For the Respondent

The Government Pleader conceded that the amount was due and approved but contended that payment was delayed due to fund allocation processes. They relied on W.A.791/2022 to argue that interest claims must be pursued before a civil forum and that writ jurisdiction should not interfere in routine financial disbursements.

The Court's Analysis

The Court rejected the notion that fiscal constraints or procedural delays justify non-payment of admitted dues. It emphasized that the state, as a contracting party, is bound by the same principles of fairness and non-arbitrariness as any private entity. The fact that the bill was approved and no dispute existed rendered the delay legally indefensible.

"When a State decides not to pay the dues with mala fide, with ulterior motives or arbitrarily... such an act of the State of not paying its dues cannot be said to be wholly beyond the reach of Article 226."

The Court distinguished this case from those involving factual disputes requiring evidence or arbitration. Here, the state had already validated the work and the quantum due. The Court further held that delay in payment of public dues, even without malice, erodes public trust and violates the right to equality and life with dignity under Articles 14 and 21.

The Court declined to entertain the interest claim under writ jurisdiction, noting that interest disputes require factual adjudication best suited for civil courts. However, it underscored that the principal amount, once admitted, must be paid without further delay.

The Verdict

The petitioner succeeded. The Court held that the state’s failure to pay an admitted contractual amount, despite approval and no dispute, violates Articles 14 and 21. The respondents were directed to pay Rs.28,69,870 within six weeks. The interest claim was left open for civil remedy.

What This Means For Similar Cases

Payment of Admitted Dues Is Non-Discretionary

  • Practitioners can now invoke Article 226 to compel payment of undisputed government dues, even without alleging mala fide.
  • The burden shifts to the state to prove a legitimate, documented reason for delay - not mere administrative backlog.
  • Writ petitions are maintainable where the state has already certified work and approved bills.

Interest Claims Must Be Separately Pursued

  • While principal amounts are enforceable via writ, interest claims require civil litigation.
  • Lawyers should file writ petitions for principal dues and parallel civil suits for interest to avoid jurisdictional pitfalls.
  • Courts will not entertain interest claims under Article 226 unless tied to constitutional arbitrariness.

State Entities Cannot Hide Behind Budgetary Constraints

  • Fiscal constraints are not a valid defense against constitutional obligations.
  • Public departments must prioritize contractual payments to private parties as part of their duty under Rule of Law.
  • Delayed payments now carry reputational and legal risk beyond financial liability.

Case Details

Vyshno Constructions v. State of Andhra Pradesh

APHC010603022025
PDF
Court
High Court of Andhra Pradesh at Amaravati
Date
27 January 2026
Case Number
Writ Petition No. 31295 of 2025
Bench
Justice Tarlada Rajasekhar Rao
Counsel
Pet: Ch B R P Sekhar
Res: Government Pleader for Roads and Buildings, Government Pleader for Finance Planning

Frequently Asked Questions

Yes, if the state has certified the work and approved the payment through official channels, and no dispute exists, the refusal to pay constitutes arbitrariness under Article 14 and can be challenged via writ petition under Article 226, as held in this judgment.
No. The Court held that interest claims involve factual disputes requiring evidence and are best adjudicated in civil courts. Writ jurisdiction is limited to enforcing the principal admitted amount.
Yes. The Court held that fiscal constraints cannot override constitutional duties under Articles 14 and 21. The state must ensure timely payment of admitted dues as part of its obligation to uphold the Rule of Law.
0

Disclaimer

This article is for informational purposes only and does not constitute legal advice. The views expressed are based on the judgment analysis and should not be taken as professional counsel. Please consult with a qualified attorney for advice specific to your situation.