
The National Company Law Appellate Tribunal has clarified that an operational creditor’s Section 9 application remains maintainable when the corporate debtor, despite raising quality and delay claims, subsequently acknowledges an undisputed debt amount through a formal consequence sheet. This judgment reinforces that conditional admissions tied to reconciliation do not negate liability where the core amount is explicitly accepted.
Background & Facts
The Dispute
M/s Gemini Engi. Fab. Private Limited (Corporate Debtor) entered into multiple purchase orders with M/s Kisaan Steels Pvt. Ltd. (Operational Creditor) between December 2021 and June 2022 for the supply of steel forgings, tube sheets, and related components. The Corporate Debtor alleged repeated delays in delivery and defective goods, resulting in project disruptions and financial losses, particularly in its dealings with IOCL and other clients. The Corporate Debtor imposed penalties and initiated internal reconciliation processes, while the Operational Creditor maintained that all goods were delivered as per approved specifications and accepted by the Corporate Debtor’s own inspection agencies.
Key Facts
- Purchase orders issued by Corporate Debtor totaled Rs. 8,40,01,413/-
- Operational Creditor issued invoices for all deliveries, with GST charged and input tax credit claimed by Corporate Debtor
- Corporate Debtor deducted TDS on payments due to Operational Creditor under Income Tax Act, 1961
- Operational Creditor issued a demand notice under Section 8 of IBC on 01.07.2023 claiming Rs. 6,13,53,270/-
- Corporate Debtor replied on 14.07.2023, asserting pre-existing disputes and submitting a "consequence sheet" calculating net payable amount as Rs. 3,84,63,113/-
- The consequence sheet, signed by the Corporate Debtor, itemized delays, defects, liquidated damages, and net balance due
- Operational Creditor reduced its claim in the Section 9 petition to Rs. 3,97,44,173.70/-, aligning with the undisputed portion identified in the consequence sheet
- Email dated 01.11.2023 from Corporate Debtor stated: "payment would be made" and referenced arbitration as remedy for default, without mentioning dispute
- Corporate Debtor filed a settlement offer on 30.08.2024, which Operational Creditor rejected
- Corporate Debtor offered Rs. 4.25 crores on 23.02.2026 as full and final settlement, but Operational Creditor refused, insisting on Rs. 3.97 crores
Procedural History
- 08.12.2021: First major purchase order (GEF/PO/326/21-22) issued by Corporate Debtor
- 14.12.2021: Operational Creditor acknowledged PO
- 23.12.2021: Corporate Debtor shared Quality Assurance Plan
- 06.01.2022 & 19.01.2022: Corporate Debtor issued revised forging sketches, causing delays
- 23.11.2022: Corporate Debtor notified defects via email after joint UT test
- 01.07.2023: Operational Creditor issued demand notice under Section 8 for Rs. 6,13,53,270/-
- 14.07.2023: Corporate Debtor replied disputing liability and submitted consequence sheet
- 15.03.2023: Operational Creditor filed Company Petition under Section 9 for Rs. 3,97,44,173.70/-
- 24.03.2025: NCLT Mumbai admitted petition, initiating CIRP
- 24.03.2025: Corporate Debtor filed appeal before NCLAT (Company Appeal (AT) (Insolvency) No. 526 of 2025)
- 19.02.2026: Arguments concluded; tribunal reserved order
- 23.02.2026: Corporate Debtor deposited Rs. 4.25 crores as settlement offer
- 21.04.2026: Operational Creditor declined to file settlement memorandum
- 11.05.2026: NCLAT delivered judgment
The Parties' Positions
Appellant (Corporate Debtor): Argued that pre-existing disputes over quality and delivery timelines rendered the Section 9 petition non-maintainable. Relied on Mobilox Innovations, Sabarmati Gas, and S.S. Engineers to assert that any dispute, even if partially resolved, bars CIRP. Claimed the consequence sheet was a negotiation tool, not an admission.
Respondent (Operational Creditor): Contended that the consequence sheet, signed by the Corporate Debtor, crystallized an undisputed debt of Rs. 3.84 crores. Asserted that the Corporate Debtor’s email dated 01.11.2023 constituted an unequivocal admission of liability. Argued that the appeal was filed to delay proceedings and that new grounds (e.g., unauthorized signatory) were raised belatedly.
Relief Sought
The Appellant sought quashing of the NCLT’s order dated 24.03.2025, setting aside the initiation of CIRP, and a declaration that no undisputed debt existed. The Respondent sought dismissal of the appeal and continuation of CIRP.
The Legal Issue
Whether the corporate debtor’s execution and submission of a consequence sheet, which explicitly calculates and acknowledges an undisputed debt of Rs. 3.84 crores, extinguishes the claim of a pre-existing dispute under Section 9 of the Insolvency and Bankruptcy Code, thereby rendering the operational creditor’s petition maintainable?
Arguments Presented
For the Appellant
The Appellant relied on Mobilox Innovations v. Kirusa Software and S.S. Engineers v. Hindustan Petroleum to argue that any bona fide dispute, even if partially resolved, precludes initiation of CIRP under Section 9. It contended that the consequence sheet was a negotiation document, not a final admission, and that the email dated 01.11.2023 was conditional upon acceptance of the sheet. It further argued that TDS and GST deductions are statutory compliance, not acknowledgments of debt, and that the NCLT erred in ignoring the documented delays and defects.
For the Respondent
The Respondent argued that the consequence sheet, signed by the Corporate Debtor, was a formal, itemized reconciliation that admitted liability for Rs. 3.84 crores. It cited NCLAT in Amit Wadhwani and East India Udyog to assert that failure to reconcile accounts indicates dispute, but here, reconciliation was completed and accepted. The Respondent emphasized that the Corporate Debtor’s email dated 01.11.2023 contained no reservation of dispute and explicitly promised payment. It further contended that the Appellant’s belated challenge to the signatory’s authority was an abuse of process.
The Court's Analysis
The NCLAT conducted a meticulous review of the correspondence, the consequence sheet, and the legal framework under Section 9. It held that the mere existence of prior disputes does not automatically bar CIRP if, at the time of the petition, an undisputed amount has been crystallized.
"The consequence sheet... is signed and conveyed to the Operational Creditor... [and] confirms undisputed amount... which cannot be denied at this stage that there is a dispute with respect to this amount."
The Tribunal rejected the Appellant’s argument that the consequence sheet was a negotiation tactic, noting that it was not merely a proposal but a formal, itemized accounting document prepared and submitted by the Corporate Debtor itself. The Tribunal emphasized that the Corporate Debtor had not merely asserted a dispute - it had quantified and accepted liability for a specific sum.
The Court distinguished Mobilox and Praveen Kumar Sharma, noting those cases involved unresolved, genuine disputes without any formal acknowledgment of liability. Here, the Corporate Debtor had moved beyond dispute to admission. The Tribunal held:
"The Corporate Debtor had the opportunity to make payment on receipt of the Demand Notice, but it did not avail that opportunity. Later on, at the stage of both the Adjudicating Authority and the appellate authority, it offered an amount which was not acceptable to the Operational Creditor."
The Court further held that the email dated 01.11.2023, which stated "payment would be made" and referenced arbitration only in case of default, constituted an unequivocal acknowledgment of the debt, absent any reservation of dispute. The Tribunal concluded that the Corporate Debtor was attempting to use the IBC’s dispute mechanism as a shield to delay payment, not to resolve a legitimate disagreement.
The Appellant’s new grounds - including alleged lack of authorization in the board resolution - were dismissed as impermissible at the appellate stage, citing procedural fairness and the principle that fresh allegations cannot be introduced for the first time on appeal.
The Verdict
The appeal was dismissed. The NCLAT upheld the NCLT’s order admitting the Section 9 petition. The Corporate Insolvency Resolution Process shall restart forthwith. The undisputed debt of Rs. 3,84,63,113/-, as crystallized in the consequence sheet, remains enforceable. No costs were awarded. The Tribunal explicitly directed that the insolvency proceedings be resumed without delay.
What This Means For Similar Cases
Consequence Sheets Can Create Uncontested Debt
- Practitioners must treat signed reconciliation documents, even if labeled "consequence sheets," as binding acknowledgments of liability under Section 9
- A corporate debtor cannot simultaneously impose penalties and then claim the entire debt is disputed
- If a debtor calculates and submits a net payable amount, that amount becomes undisputed for CIRP purposes
Conditional Promises Do Not Invalidate Admission
- Statements like "payment will be made" without reservation of dispute constitute admission under IBC
- Linking payment to acceptance of a document does not negate liability if the amount is clearly stated and accepted
- Operational creditors may proceed on the undisputed portion even if other claims remain contested
Abuse of Process Will Be Penalized
-
Raising new grounds on appeal, such as unauthorized signatories, without prior pleading, will be rejected
-
Delay tactics through settlement offers followed by refusal will not stay CIRP
-
Courts will not permit corporate debtors to use IBC as leverage for commercial negotiation
-
Practitioners should advise operational creditors to preserve all reconciliation documents and ensure emails contain clear, unqualified acknowledgments
-
Corporate debtors must be cautious: any formalized accounting submission may limit future dispute defenses
-
Section 9 petitions remain viable where a clear, quantified, and unqualified debt is admitted, even if other claims are pending






