
The Delhi High Court has affirmed that liquidated damages under a commercial contract are enforceable even without proof of actual loss, provided the stipulated sum is a genuine pre-estimate of anticipated harm agreed upon by both parties. This ruling reinforces the sanctity of contractual risk allocation in commercial arbitration and clarifies the limits of judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996.
Background & Facts
The Dispute
The dispute arose under a Contract Brewing and Packaging Agreement dated 11.12.2015 between Carlsberg India Private Limited (Respondent) and Pali Hills Breweries Private Limited (Petitioner). The Petitioner was obligated to achieve a "Start Date" for contract manufacturing within 135 days of the effective date. Clause 4.3 of the Agreement provided that if the Start Date was delayed for any reason, the Petitioner would pay Rs.25 lakhs as liquidated damages, which both parties acknowledged as a "fair" pre-estimate of lost sales and missed opportunities.
Procedural History
- December 2015: Agreement executed with stipulated Start Date of 24.04.2016.
- June 2016: Parties modified the requirement for Bank Guarantee to post-dated cheques; Respondent expressly reserved rights to claim liquidated damages.
- October 2016: CIPL equipment delivered, but 3G Labeler found defective; production delayed.
- October 2017: Petitioner terminated Agreement citing financial distress and policy changes in Jharkhand liquor licensing.
- September 2020: Arbitral Tribunal awarded Respondent Rs.25 lakhs under Clause 4.3 and rejected all five counterclaims.
- December 2020: Petitioner filed Section 34 petition to set aside the Award.
Relief Sought
The Petitioner sought to set aside the Award to the extent of: (1) the award of Claim No.1 (liquidated damages), and (2) the rejection of Counter Claims Nos. 1, 3, and 4. The Petitioner argued that the liquidated damages were unenforceable due to lack of actual loss and that the Tribunal erred in rejecting its claims for electricity charges, equipment storage rent, and broken glass removal.
The Legal Issue
The central question was whether Section 74 of the Indian Contract Act, 1872 requires proof of actual loss to enforce liquidated damages when the contract explicitly states that the stipulated sum is a genuine pre-estimate of harm, and whether an arbitral tribunal’s finding on contractual interpretation can be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 for merely being erroneous.
Arguments Presented
For the Petitioner
The Petitioner relied on Kailash Nath Associates v. DDA and Indian Oil Corp. v. Fiberfill Engineer to argue that Section 74 mandates proof of actual loss as a sine qua non for any award of compensation, even if a sum is labeled as "fair" or "reasonable" in the contract. It contended that the Tribunal’s finding that the Respondent suffered no actual loss rendered the Rs.25 lakh award invalid. It further argued that the Tribunal ignored documentary evidence proving the Respondent’s failure to remove equipment and provide access, thereby rendering the rejection of Counter Claim No.3 perverse.
For the Respondent
The Respondent relied on Associate Builders v. DDA and Ssangyong Engineering v. NHAI to argue that Section 34 does not permit re-appreciation of evidence or contractual interpretation. It submitted that the Tribunal correctly interpreted Clause 4.3 as a genuine pre-estimate, given the parties’ express acknowledgment of fairness and the commercial context of lost market opportunities. It further contended that the Tribunal’s factual findings on Counter Claim No.3 were plausible and not perverse, and that the Petitioner’s challenge was an impermissible attempt to convert a Section 34 petition into an appeal.
The Court's Analysis
The Court began by reaffirming the limited scope of judicial review under Section 34 of the Arbitration and Conciliation Act, 1996, emphasizing that courts cannot act as appellate forums or substitute their view for that of the arbitrator unless the award suffers from patent illegality, perversity, or contravention of public policy.
"The view taken by the Arbitral Tribunal is ordinarily to be accepted and allowed to prevail. Thus, the scope of interference in arbitral matters is only confined to the extent envisaged under Section 34 of the Act."
The Court then turned to the interpretation of Section 74 of the Indian Contract Act, 1872. It distinguished between penalties and genuine pre-estimates, citing Kailash Nath to hold that while actual loss is a sine qua non for compensation under Section 73, Section 74 permits enforcement of a stipulated sum if it is a genuine pre-estimate - even without proof of actual loss - provided the parties intended it as such.
The Court found that Clause 4.3 was not a penalty but a carefully negotiated pre-estimate. The use of the word "fair" and the explicit linkage of delay to lost sales and alternative tie-up opportunities demonstrated mutual intent to quantify harm in advance. The Tribunal’s conclusion that this was a genuine pre-estimate was therefore plausible and beyond judicial interference.
Regarding Counter Claim No.3, the Court found the Tribunal’s reasoning flawed. The Tribunal had rejected the claim on the ground that the Respondent failed to prove when access to the site was provided. However, the record contained clear emails dated 01.11.2017 and 24.04.2018 from the Petitioner inviting the Respondent to remove equipment. Further, the Respondent’s own witness admitted in cross-examination that equipment remained on site until March 2019. The Tribunal’s failure to consider this evidence rendered its finding perverse.
"The burden of rental obligation, for the acts of the respondent, cannot be put upon the petitioner. No prudent person can arrive at the said findings in view of the documents available on record."
The Court invoked Gayatri Balasamy v. ISG Novasoft to hold that where an award contains separable parts, courts may modify or sever only the illegal portion. Since the award on Claim No.1 was valid and the rejection of Counter Claim No.3 was perverse, the Court severed the latter.
The Verdict
The Petitioner’s challenge was partially allowed. The Court upheld the award of Rs.25 lakhs in liquidated damages under Clause 4.3, holding it to be a valid genuine pre-estimate under Section 74 of the Indian Contract Act. However, the rejection of Counter Claim No.3 was set aside, and the Tribunal was directed to award Rs.10,000 per month from November 2017 to March 2019 for the Respondent’s failure to remove equipment, as stipulated in Clause 20.1.3.
What This Means For Similar Cases
Genuine Pre-Estimate Trumps Proof of Actual Loss
- Practitioners must now argue that liquidated damages are enforceable if the contract clearly links the sum to anticipated harm and uses language like "fair," "reasonable pre-estimate," or "agreed compensation."
- Evidence of actual loss is not required if the clause is structured as a pre-estimate, even if the claimant cannot quantify damages post-breach.
- Drafting tip: Include explicit acknowledgments like "Parties agree this amount reflects a genuine pre-estimate of lost market share, operational disruption, or reputational harm."
Arbitral Findings on Contract Interpretation Are Final Unless Perverse
- Courts will not interfere with arbitral interpretation of contract terms unless the finding is so unreasonable that no reasonable tribunal could have reached it.
- A mere error in reasoning or alternative interpretation does not constitute patent illegality under Section 34.
- Challenge strategies should focus on evidentiary omissions or contradictions, not on re-arguing contractual meaning.
Evidence of Access and Performance Must Be Documented
- In disputes involving equipment removal or site access, contemporaneous written communications are critical.
- Failure to document requests for access or refusal to remove assets may result in liability under penalty clauses.
- Practitioners should advise clients to:
- Send formal notices for removal of equipment with clear deadlines.
- Preserve all correspondence and meeting minutes.
- Obtain signed acknowledgments of access provision.






