
The Supreme Court has clarified the scope of Section 74 of the Indian Contract Act, 1872 in cases involving public utility projects, holding that proof of actual loss is not a prerequisite for awarding liquidated damages when the contract itself stipulates compensation for breach. The judgment underscores the limited scope of judicial interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, while affirming the power of courts to modify arbitral awards to ensure reasonable compensation in line with contractual terms.
Background & Facts
The Dispute
The dispute arose from a Power Purchase Agreement (PPA) dated 24.01.2012, executed between M/s Saisudhir Energy Ltd. (SEL) and NTPC Vidyut Vyapar Nigam Ltd. (NVVNL) under the Jawaharlal Nehru National Solar Mission (JNNSM). The PPA required SEL to commission a 20 MW solar power plant by 26.02.2013. However, SEL delayed the commissioning: 10 MW was commissioned on 26.04.2013 (two months late), and the remaining 10 MW on 24.07.2013 (five months late).
Procedural History
The dispute escalated through multiple forums:
- 2013-2015: Arbitration proceedings initiated under the Arbitration and Conciliation Act, 1996. A three-member tribunal passed a split award, with the majority awarding NVVNL ₹1.2 crores as liquidated damages.
- 2016: SEL and NVVNL filed objections under Section 34 before the Delhi High Court. A learned Single Judge modified the award, granting NVVNL ₹27.06 crores as reasonable compensation.
- 2018: Both parties appealed under Section 37. The Division Bench reduced the compensation to ₹20.70 crores, holding that the project’s public utility nature justified a lower quantum.
Relief Sought
The cross-appeals before the Supreme Court sought:
- SEL: Setting aside the High Court’s modification of the arbitral award, arguing that NVVNL failed to prove actual loss.
- NVVNL: Restoration of the ₹27.06 crores awarded by the Single Judge, contending that the Division Bench exceeded its jurisdiction under Section 37.
The Legal Issue
The Supreme Court addressed two critical questions:
- Whether Section 74 of the Indian Contract Act requires proof of actual loss for awarding liquidated damages in public utility projects.
- Whether the Division Bench of the High Court exceeded its jurisdiction under Section 37 of the Arbitration Act by re-calculating the quantum of reasonable compensation.
Arguments Presented
For the Appellant (SEL)
SEL contended that:
- NVVNL failed to prove actual loss suffered due to the delay, as required under Section 74 of the Indian Contract Act. Reliance was placed on Kailash Nath Associates v. D.D.A. to argue that compensation cannot be awarded without proof of loss.
- The PPA was a purely commercial contract, and the public utility nature of the JNNSM did not absolve NVVNL of its burden to prove damages.
- The High Court’s modification of the arbitral award under Sections 34 and 37 was impermissible, as it amounted to a merit-based review. Gayatri Balasamy v. ISG Novasoft Technologies Ltd. was cited to argue that courts cannot substitute their view for that of the arbitrator.
For the Respondent (NVVNL)
NVVNL argued that:
- The PPA was executed under the JNNSM, a public utility project, and thus, proof of actual loss was not required. M/s Construction and Design Services v. D.D.A. was relied upon to assert that delays in public utility projects inherently cause loss.
- The delay in commissioning the solar plant was an admitted fact, and NVVNL was entitled to liquidated damages as per Clause 4.6 of the PPA.
- The Division Bench’s reduction of compensation to ₹20.70 crores was arbitrary and unsupported by the PPA’s terms.
The Court's Analysis
The Supreme Court’s analysis centered on three key aspects:
1. Section 74 and Public Utility Projects
The Court examined Section 74 of the Indian Contract Act, which permits the award of reasonable compensation for breach of contract, even in the absence of proof of actual loss. It distinguished between commercial contracts and public utility projects, holding that the latter involve broader public interest:
"The PPA was executed under the JNNSM, a scheme aimed at promoting green energy and reducing environmental degradation. The commissioning of the solar plant was not merely a commercial endeavor but one of public utility. In such cases, the delay in commissioning itself constitutes a loss, and the burden shifts to the party in breach to prove that no loss was caused."
The Court relied on M/s Construction and Design Services v. D.D.A., where it was held that in public utility projects, the pre-estimated loss stipulated in the contract is binding unless the party in breach proves it to be a penalty. SEL failed to discharge this burden, as it merely argued that NVVNL had not suffered financial loss, ignoring the broader public interest involved.
2. Modification of Arbitral Awards Under Sections 34 and 37
The Court addressed the scope of judicial interference under Sections 34 and 37 of the Arbitration Act. It held that while courts cannot undertake a merit-based review of arbitral awards, they can modify awards to ensure compliance with the fundamental policy of Indian law and the terms of the contract. The Constitution Bench decision in Gayatri Balasamy v. ISG Novasoft Technologies Ltd. was cited to affirm the limited power of modification:
"The power of judicial review under Section 34, and the setting aside of an award, should be read as inherently including a limited power to modify the award within the confines of Section 34. This power is exercised to prevent injustice and unnecessary delays, without engaging in a fact-finding exercise."
The Court held that the Single Judge’s modification of the award to grant ₹27.06 crores was a permissible exercise, as it was based on the terms of Clause 4.6 of the PPA and did not involve a re-examination of the merits of the dispute.
3. Excessive Interference by the Division Bench
The Court criticized the Division Bench for exceeding its jurisdiction under Section 37 by re-calculating the quantum of compensation. It held that the Division Bench’s reduction of the amount to ₹20.70 crores was a substitution of its view for that of the Single Judge, without demonstrating that the latter’s determination was arbitrary or perverse. The Court relied on AC Chokshi Share Broker Private Limited v. Jatin Pratap Desai, which limits the scope of Section 37 to determining whether the Section 34 court exercised its jurisdiction properly:
"The Division Bench erred in re-working the amount of reasonable compensation. The Single Judge’s determination was based on the terms of the PPA and was neither arbitrary nor perverse. The Division Bench’s interference was unwarranted and beyond the scope of Section 37."
The Verdict
The Supreme Court allowed NVVNL’s appeal and dismissed SEL’s appeal. It set aside the Division Bench’s judgment and restored the Single Judge’s order, which awarded NVVNL ₹27.06 crores as reasonable compensation for the delay in commissioning the solar power plant. The Court held that:
- Proof of actual loss is not required for awarding liquidated damages in public utility projects under Section 74 of the Indian Contract Act.
- The Division Bench exceeded its jurisdiction under Section 37 by re-calculating the quantum of compensation without demonstrating arbitrariness or perversity in the Single Judge’s order.
What This Means For Similar Cases
Liquidated Damages in Public Utility Contracts
The judgment reinforces the principle that in contracts involving public utility or public interest, the party claiming liquidated damages is not required to prove actual loss. Practitioners should note:
- Burden of proof shifts: The party in breach must prove that no loss was caused or that the stipulated amount is a penalty.
- Public interest trumps commercial considerations: Courts will prioritize the broader public good over narrow financial losses.
- Precedent reliance: M/s Construction and Design Services v. D.D.A. remains a binding authority for cases involving delays in public utility projects.
Limits of Judicial Interference Under the Arbitration Act
The judgment clarifies the scope of Sections 34 and 37 of the Arbitration Act, emphasizing that:
- Modification is permissible, but limited: Courts can modify arbitral awards to ensure compliance with contractual terms and fundamental legal principles, but cannot substitute their view for that of the arbitrator or the Section 34 court.
- Section 37 is not an appellate forum: The Division Bench’s role is to determine whether the Section 34 court exercised its jurisdiction properly, not to re-evaluate the merits of the dispute.
- Contractual terms prevail: Courts must adhere to the terms of the contract when determining reasonable compensation, unless such terms are arbitrary or contrary to law.
Practical Takeaways for Contract Drafting
Parties drafting contracts involving liquidated damages should:
- Clearly define public utility: If the contract involves public interest, explicitly state its public utility nature to avoid disputes over the burden of proof.
- Stipulate reasonable compensation: Ensure that the liquidated damages clause is a genuine pre-estimate of loss, as courts are unlikely to enforce penal clauses.
- Include force majeure provisions: Clearly outline circumstances that may excuse delays, as SEL’s invocation of force majeure was rejected due to non-compliance with notice requirements.






