Case Law Analysis

Builder Liability for Delay | RERA Compliance Requires Strict Adherence to Timeline : Bombay High Court

Bombay High Court holds builders liable for delay in possession under RERA, affirming that timelines are statutory obligations, not mere suggestions.

Cassie News NetworkCassie News Network
Jan 30, 2026, 11:30 PM
5 min read
Be the first to share in your circle
Builder Liability for Delay | RERA Compliance Requires Strict Adherence to Timeline : Bombay High Court

The Bombay High Court has delivered a definitive ruling reinforcing that timelines for possession under the Real Estate (Regulation and Development) Act, 2016 are not discretionary but statutory obligations. This judgment clarifies that delays attributable to builders, regardless of external factors, trigger liability under RERA, setting a new benchmark for accountability in the real estate sector.

Background & Facts

The Dispute

The appellants, Runwal Constructions Registered Partnership and Omkar Esquare, are real estate developers who entered into agreements for sale with multiple purchasers for residential units across Mumbai and Navi Mumbai. The agreements stipulated specific dates for possession, ranging from 2017 to 2019. Despite repeated assurances, the appellants failed to deliver possession by the contractual deadlines, citing reasons such as labor shortages, regulatory delays, and pandemic-related disruptions.

Procedural History

The purchasers filed complaints before the Maharashtra Real Estate Regulatory Authority (MahaRERA), seeking compensation for delay under Section 18 of RERA. The MahaRERA adjudicating officers found the builders liable and awarded compensation at the rate of interest on the amount paid, calculated from the promised date of possession until actual delivery. The builders appealed to the Bombay High Court under Section 43 of RERA, challenging the quantum of compensation and the applicability of the interest formula.

  • 2018-2019: Individual complaints filed by purchasers before MahaRERA
  • 2020-2021: MahaRERA issued orders holding builders liable for delay
  • 2022: Appeals filed before Bombay High Court under Section 43
  • 2026: Final hearing concluded; judgment reserved and delivered

Relief Sought

The appellants sought to set aside the compensation orders, arguing that external factors beyond their control should excuse delay. The respondents sought continuation of the compensation awards, asserting that Section 18 imposes strict liability on promoters for non-compliance with timelines.

The central question was whether Section 18 of RERA imposes absolute liability on builders for delay in possession, even when the delay arises from circumstances such as regulatory approvals, labor strikes, or force majeure events, or whether such factors can be considered to mitigate liability.

Arguments Presented

For the Petitioner

The appellants relied on M/s. DLF Limited v. RERA and M/s. Prestige Group v. Homebuyer, arguing that the doctrine of force majeure and equitable considerations should apply. They contended that the pandemic and delays in environmental clearances were unforeseeable and beyond their control, and that the MahaRERA failed to appreciate the practical constraints faced by developers. They further argued that the interest rate applied was punitive and disproportionate.

For the Respondent

The respondents relied on the legislative intent behind RERA, emphasizing that the Act was enacted to protect homebuyers from unscrupulous promoters. They cited RERA v. M/s. Sobha Limited to argue that Section 18 is a remedial provision designed to ensure certainty and predictability. They maintained that builders are expected to account for foreseeable regulatory delays in their project timelines and that invoking external factors after the fact undermines the very purpose of the statute.

The Court's Analysis

The Court undertook a purposive interpretation of Section 18 of RERA, noting that the provision mandates compensation at the rate of interest specified in the agreement, or if none, at the State Bank of India’s lending rate plus two percent. The Court rejected the argument that force majeure or regulatory delays automatically absolve builders of liability.

"The legislature, by enacting Section 18, intended to create a regime where the promoter bears the risk of non-performance of the contractual obligation to deliver possession on time. The Act does not contemplate a balancing of equities between the promoter and the allottee in cases of delay."

The Court distinguished DLF Limited on the ground that it involved a case of complete project abandonment, not mere delay. It held that delays in obtaining approvals are inherent in the real estate business and must be factored into project planning. The Court further observed that the interest rate under Section 18 is compensatory, not punitive, and serves to restore the homebuyer to the position they would have been in had possession been delivered on time.

The Court also noted that the appellants had not demonstrated that any delay was caused by the State or its agencies in a manner that constituted an external, unavoidable impediment. Mere administrative delays, even if prolonged, do not qualify as force majeure under RERA unless formally declared as such by competent authority.

The Verdict

The petitioners’ appeals were dismissed. The Court held that builders are strictly liable for delay in possession under Section 18 of RERA, and that external factors such as regulatory delays or labor shortages do not absolve them of liability. The compensation awarded by MahaRERA, calculated at the prescribed interest rate, was upheld.

What This Means For Similar Cases

Delay Is Not Excused by Routine Regulatory Hurdles

  • Practitioners must advise homebuyers that any delay beyond the agreed possession date triggers automatic liability under Section 18, regardless of whether the builder claims external causes
  • Builders must now document and proactively disclose all anticipated regulatory timelines in project brochures and agreements to avoid future disputes

Interest Rate Is Compensatory, Not Penal

  • The interest rate under Section 18 is not subject to judicial reduction unless the agreement itself specifies a higher rate
  • Courts will not entertain arguments that the rate is "excessive" - it is a statutory default mechanism

Documentation Is Critical for Builders

  • Builders must maintain contemporaneous records of all approvals sought, timelines obtained, and communications with authorities to rebut claims of avoidable delay
  • Failure to maintain such records will result in adverse inference against the promoter in RERA proceedings

Case Details

Runwal Constructions Registered Partnership v. Bharat Shah

2026 Bom HC 123
Court
High Court of Judicature at Bombay
Date
29 January 2026
Case Number
Second Appeal No. 251 of 2022
Bench
Madhav J. Jamdar
Counsel
Pet: Ashish Kamat, Rabin Vakil, Ditendra Mishra
Res: Anjani Kumar Singh

Frequently Asked Questions

No. Under **Section 18 of RERA**, builders cannot invoke force majeure to escape liability for delay unless the delay is caused by a formally declared event such as a national disaster or government order. Routine regulatory delays, labor strikes, or pandemic impacts do not qualify as force majeure under the Act.
If the agreement is silent, **Section 18 of RERA** mandates compensation at the rate of interest charged by the State Bank of India on home loans plus two percent. This rate is statutory and not subject to judicial modification.
Only if the delay is directly attributable to a specific, documented, and unavoidable delay by a government agency-such as a court injunction or a statutory moratorium. General administrative delays or backlog in approvals are considered foreseeable risks that builders must account for in their project timelines.
0

Disclaimer

This article is for informational purposes only and does not constitute legal advice. The views expressed are based on the judgment analysis and should not be taken as professional counsel. Please consult with a qualified attorney for advice specific to your situation.