Section 34 Arbitration Act | Wrongful Termination Justifies Loss of Profit & Performance Bank Guarantee Refund : Bombay HC
Case Law Analysis
|Bombay High Court

Section 34 Arbitration Act | Wrongful Termination Justifies Loss of Profit & Performance Bank Guarantee Refund : Bombay HC

Bombay High Court upholds a ₹27.43 crore arbitral award, ruling that ONGC’s wrongful termination of an ETP contract entitles Newton Engineering to both loss of profit and refund of the performance bank guarantee. The judgment reaffirms the limited scope of judicial review under Section 34 of the Arbitration Act, reinforcing contractual sanctity in commercial disputes.

Remand Proceedings | Tribunal Cannot Overturn Binding Finding of State-Caused Delay in Construction Contracts : MP HC
Case Law Analysis
|Madhya Pradesh High Court

Remand Proceedings | Tribunal Cannot Overturn Binding Finding of State-Caused Delay in Construction Contracts : MP HC

The Madhya Pradesh High Court has ruled that when an arbitration award is remanded for fresh adjudication, the tribunal is bound by prior judicial findings on state-caused delay and cannot revisit or negate them. This reinforces the doctrine of judicial finality in construction arbitration, protecting contractors from arbitrary recalculations of delay liability even after remand.