1 articleLatest March 2026
Regulation 4.8.2 Haryana Electricity Regulations | Transmission Losses for Independent Feeders Must Be Billed from Sub-Station Yard Meter : Punjab & Haryana HC
Case Law Analysis
|Punjab and Haryana High Court

Regulation 4.8.2 Haryana Electricity Regulations | Transmission Losses for Independent Feeders Must Be Billed from Sub-Station Yard Meter : Punjab & Haryana HC

Punjab & Haryana HC clarifies that under Regulation 4.8.2 of the 2016 Haryana Electricity Regulations, transmission losses for independent feeders must be calculated from the sub-station yard meter, not consumer-end meters. The ruling mandates consumer notification for joint readings unless remote metering is proven effective, ensuring regulatory compliance and preventing arbitrary billing.