
The Delhi High Court dismissed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, upholding a 30 October 2018 arbitral award concerning illumination work at Safdarjung Tomb. The judgment re-affirms the narrow scope of judicial interference, emphasizing that courts cannot re-appraise evidence or alter an arbitrator’s discretion on interest unless a clear breach of public policy or patent illegality is shown.
Background & Facts
The Dispute
The petitioner, India Tourism Development Corporation (ITDC), floated a Notice Inviting Tender (NIT) for supply, installation, testing and commissioning (SITC) of specialised illumination works at Safdarjung Tomb Monument, New Delhi. The respondent, M/s Bajaj Electricals Ltd, submitted its tender on 06 February 2007 and was awarded the contract.
Key Facts
- 04 April 2007 - Letter of Intent (LOI) issued by ITDC to Bajaj; contract value Rs 2,08,90,095.
- 10 April 2007 - Work Order issued, requiring Bajaj to submit detailed drawings.
- 22 May 2007 - Formal contract signed, incorporating the General Conditions of Contract (GCC) with clauses 10, 11, 42-44.
- 03 & 05 October 2007 - Newspaper reports of damage to the monument caused by Bajaj’s execution.
- 31 December 2007 - Memorandum of Understanding (MoU) between ITDC and the Archaeological Survey of India (ASI) to revise fixture layout.
- 20 March 2008 - ITDC letter requesting completion per revised drawings.
- 05 May 2008 - ITDC forwarded approved revised drawings.
- 23 April 2009 - Bajaj submitted documents claiming completion of the lightning system.
- 01 June 2009 - ASI took over illumination work.
- 08 June 2009 - Bajaj submitted final bill of Rs 1,18,95,572 out of a total work value of Rs 2,39,75,000.
- Multiple requests by Bajaj for payment remained unsatisfied, leading to Company Petition CO. PET. 472/2011 before the Delhi High Court.
- 16 April 2013 - The Court noted that ITDC had paid Rs 26,96,258 to Bajaj.
- 13 August 2008 - Measurement Book No. 1613 signed by the contractor, site engineer and architect consultant up to this date.
- 30 October 2018 - Sole Arbitrator passed the award directing Bajaj to receive principal Rs 46,92,298.22, pre-reference interest Rs 33,27,886 (25 July 2009-16 April 2013) and pendente-lite interest Rs 31,17,742.91 (17 April 2013-30 Oct 2018), plus future interest.
- 01 May 2019 - Arbitrator terminated review proceedings for non-deposit of arbitrator’s fee.
- 13 January 2023 - Delhi High Court condoned delay in filing IA 1351/2019 and IA 13519/2019.
- 08 July 2025 - Court directed ITDC to deposit the decretal amount; ITDC failed to comply.
- 17 August 2026 - Judgment under review petition O.M.P. (COMM) 404/2019 delivered.
Procedural History
- 06 May 2026 - Petition filed under Section 34 of the Arbitration Act (O.M.P. (COMM) 404/2019).
- 13 January 2023 - IA 1351/2019 and IA 13519/2019 condoned for delay.
- 08 July 2025 - Court ordered deposit of decretal amount; stay on award.
- 17 August 2026 - Single Judge delivered the judgment dismissing the petition.
The Parties' Positions
- Petitioner (ITDC) argued that the award was perverse, that deductions of Rs 11,07,832 for non-execution of civil/electrical works were ignored, that service tax, ESI/EPF and labour-cess amounts were wrongly awarded, and that the 12% post-award interest was excessive.
- Respondent (Bajaj) contended that the arbitrator correctly applied the contract, that statutory deductions had been complied with via indemnity bonds, and that the award fell within the permissible discretion under Section 31(7) of the Arbitration Act.
Relief Sought
ITDC sought setting aside the award in whole or in part, reversal of interest calculations, and direction to recover the amounts it had already paid.
The Legal Issue
What is the precise scope of judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996 - can a court set aside an arbitral award on the basis of alleged perverse findings, excessive interest, or ignored deductions, or must it be limited to violations of Indian public policy or patent illegality?
Arguments Presented
For the Petitioner
- The award ignored legitimate deductions of Rs 11,07,832 recorded in Measurement Book No. 1613, thereby violating the contract.
- Service tax, ESI/EPF and labour-cess amounts were awarded despite ITDC having already deposited the statutory amounts; this amounts to a breach of the contract and a perverse finding.
- The arbitrator’s post-award interest of 12% per annum is excessive and not justified by the prevailing market rates, constituting a violation of public policy.
- Relied on MMTC Ltd. v. Vedanta Ltd. and Ramesh Kumar Jain v. BALCO for the proposition that a patent illegality or a finding that shocks the conscience warrants interference.
For the Respondent
- The arbitrator exercised the discretion conferred by Section 31(7) to award interest and to assess the quantum of the award; courts cannot substitute their view of the evidence.
- All statutory deductions were either covered by indemnity bonds or had been deposited by ITDC, as evidenced by the service-tax challans and EPF/ESI bonds produced during the arbitration.
- The award was reasoned, intelligible and based on the evidence before the tribunal; no patent illegality or violation of public policy is evident.
- Cited Associate Builders v. DDA, ONGC Ltd. v. Saw Pipes Ltd., and McDermott International Inc. v. Burn Standard Co. Ltd. to underscore that courts do not sit in appeal over arbitral awards.
The Court's Analysis
The Court began by reiterating the settled position that Section 34 does not confer an appellate jurisdiction. It quoted the Supreme Court’s pronouncement in MMTC Ltd. v. Vedanta Ltd.:
"the Court does not sit in appeal over the arbitral award and may interfere on merits on the limited ground provided under Section 34(2)(b)(ii) i.e. if the award is against the public policy of India." The Court then examined the post-2015 amendment, noting that the scope of "public policy" now expressly includes fraud, corruption, violation of Sections 75 or 81, and conflict with basic notions of justice or morality. However, the Court stressed that the proviso to Section 34(2-A) bars setting aside an award merely for erroneous legal application or re-appreciation of evidence.
On the issue of interest, the Court referred to the statutory language of Section 31(7), emphasizing that the arbitrator may award interest at a rate it deems reasonable. It observed that the award’s 12% rate fell within the arbitrator’s discretion and was not “so excessive as to shock the conscience,” distinguishing the present case from Vedanta Ltd. where the interest rate was held unreasonable.
Regarding the alleged ignored deductions, the Court held that the Measurement Book entries after 13 August 2008 were not signed by the contractor, and the arbitrator was entitled to rely on the signed portions. The Court found no evidence of patent illegality; the deductions were a matter of contractual interpretation, a domain reserved for the arbitrator.
The Court also addressed the adequacy of reasoning, concluding that the award was intelligible and based on the material before the tribunal. Consequently, none of the petitioner’s grounds satisfied the narrow criteria for interference under Section 34.
The Verdict
The petition under Section 34 was dismissed. The High Court upheld the arbitral award dated 30 October 2018, including the principal sum of Rs 46,92,298.22, pre-reference interest of Rs 33,27,886, pendente-lite interest of Rs 31,17,742.91, and the post-award interest rate of 12% per annum. No monetary alteration or costs were ordered. The decree to deposit the decretal amount remains unenforced due to the petitioner’s non-compliance.
What This Means For Similar Cases
Section 34 Remains Narrow
- Courts will not re-appraise evidence or substitute their own findings; interference is limited to violations of public policy or patent illegality.
- Practitioners must frame challenges around clear breaches of statutory or fundamental policy, not merely adverse factual conclusions.
Arbitrator’s Discretion on Interest Is Preserved
- Under Section 31(7), arbitrators may set post-award interest rates they consider reasonable; courts will not reduce rates unless they are manifestly excessive.
- Parties should negotiate interest clauses expressly in the arbitration agreement to avoid uncertainty.
Evidence Appreciation Is Not Re-examined
- Signed portions of measurement books or other documents control the arbitrator’s valuation; unsigned entries may be excluded.
- Parties should ensure all critical documents are duly signed by all contractual parties before arbitration.
Practical Takeaways
- Draft arbitration clauses that specify the governing law for interest and include a clear mechanism for post-award interest.
- Preserve signed copies of all measurement books, bills and statutory compliance certificates to pre-empt challenges.
- When invoking Section 34, focus on demonstrable patent illegality or public policy violation; generic dissatisfaction with the award’s amount will not succeed.






