Section 34 Arbitration Act | Reasoned Approximation of Damages Suffices Without Exact Calculation : Bombay HC

The Bombay High Court upheld an arbitral award where the tribunal awarded Rs. 8.17 crores for risk purchases through reasoned approximation, not precise computation, affirming that Section 34 does not demand mathematical exactitude. This clarifies that parties and tribunals may rely on logical, evidence-based estimates in complex commercial disputes, reducing the risk of awards being set aside on technical grounds.

Cassie News NetworkCassie News Network
Jun 9, 2026, 6:36 PM(Updated: Nov 3, 2026)
•8 min read
Be the first to share in your circle
Section 34 Arbitration Act | Reasoned Approximation of Damages Suffices Without Exact Calculation : Bombay HC

The Bombay High Court has reaffirmed that an arbitral award need not contain exhaustive quantification of damages if it provides a reasoned, commercially sensible basis for its findings. In dismissing a Section 34 challenge, the Court emphasized that arbitral tribunals are entitled to adopt rough and ready estimates where evidence is complex and parties have failed to establish precise causation.

Background & Facts

The Dispute

Paharpur Cooling Towers Limited (Paharpur) and Siemens Limited entered into a General Responsibility Agreement (GRA) and three separate contracts on 24.12.2010 for the construction of three natural draft cooling towers at Torrent Energy Ltd.’s power project in Dahej, Gujarat. Siemens, as the turnkey contractor, engaged Paharpur for cooling tower construction. Disputes arose over delays, risk purchases, and invocation of bank guarantees, leading to arbitration.

Key Facts

  • The total contract value was approximately Rs. 117.95 Crores.
  • Siemens claimed Rs. 29.89 Crores under the head of "risk purchases" - expenses incurred from third-party contractors due to alleged delays by Paharpur.
  • Paharpur admitted liability for Rs. 13.54 Crores of this claim but disputed the remaining Rs. 16.34 Crores.
  • Siemens invoked eight bank guarantees totaling Rs. 34.73 Crores between 2013 and 2014.
  • Paharpur alleged that the invocation was fraudulent and sought refund with 18% interest.
  • Siemens claimed liquidated damages of Rs. 23.59 Crores (20% of contract value) under Clause 2.1 of the GRA, citing 100+ days of delay attributable to Paharpur.
  • Paharpur raised counterclaims for wrongful deductions, retention money withholding, and underpaid invoices totaling Rs. 39.63 Crores.

Procedural History

  • 24.12.2010: Execution of GRA and three contracts between Paharpur and Siemens.
  • 2013 - 2014: Siemens invoked eight bank guarantees totaling Rs. 34.73 Crores.
  • 2015: Paharpur filed criminal complaint alleging fraud in invocation of guarantees; Siemens moved to quash under Section 482 CrPC.
  • 06.11.2015: Supreme Court observed in Siemens v. Paharpur (Crl. P. No. 123/2015) that the legality of guarantee invocation was a civil matter for arbitration.
  • 27.02.2019: Three-member Arbitral Tribunal delivered the Impugned Award.
    • Allowed Siemens’ risk purchase claim by 50%: Rs. 8.17 Crores.
    • Allowed Siemens’ liquidated damages claim: Rs. 23.59 Crores.
    • Allowed Paharpur’s counterclaims: Rs. 22.48 Crores.
    • Net liability: Siemens to pay Paharpur Rs. 20.84 Crores with 6% interest.
  • 28.03.2019: Paharpur filed Commercial Arbitration Petition No. 996 of 2019 under Section 34 of the Arbitration and Conciliation Act, 1996.
  • 05.05.2026: Arguments concluded before Bombay High Court.
  • 08.06.2026: Judgment pronounced.

The Parties' Positions

Paharpur’s Contentions:

  • The 50% award on risk purchases was arbitrary, lacking evidentiary basis.
  • Liquidated damages were improperly awarded despite concurrent delay by Siemens via its sub-contractor Gammon India.
  • The Arbitral Tribunal ignored vital evidence on fraudulent invocation of bank guarantees.
  • The Tribunal wrongly equated Advance Payment Guarantee with Performance Bank Guarantee.
  • The Tribunal failed to comply with the Supreme Court’s 2015 direction to adjudicate the guarantee issue.

Siemens’ Contentions:

  • The Arbitral Tribunal provided reasoned analysis for all findings.
  • The 50% discount was a fair estimate based on absence of price negotiation and inflated wage rates.
  • Delay attributable to Paharpur exceeded 100 days, triggering liquidated damages.
  • The Supreme Court’s 2015 observation was not a direction but a clarification of jurisdiction.
  • The Advance Payment Guarantee was contractually intended to also serve as a Performance Guarantee.
  • No mala fide intent was established in guarantee invocation.

Relief Sought

Paharpur sought to set aside:

  • Paragraphs 301 - 311: Rs. 8.17 Crores awarded for risk purchases.
  • Paragraphs 44 - 79 and 94 - 103: Rs. 23.59 Crores in liquidated damages.
  • Paragraphs 330 - 334: Findings on bank guarantee invocation, seeking refund of Rs. 34.73 Crores with 18% interest.

The central question was whether an arbitral award can be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 for patent illegality when the tribunal provides a reasoned, albeit approximate, basis for its award, rather than exact quantification of damages.

Arguments Presented

For the Petitioner

Paharpur relied on OPG Power Generation v. Enexio Power Cooling Solutions and Kailash Nath Associates v. DDA to argue that an arbitral award must clearly apportion delay and cannot impose maximum liquidated damages without proportionality. It contended that the 50% risk purchase award was a pure guess, unsupported by evidence, and that the Tribunal ignored testimony on fraudulent guarantee invocation. It further argued that equating Advance Payment Guarantee with Performance Guarantee was a legal error, and that the Supreme Court’s 2015 observation constituted a binding direction.

For the Respondent

Siemens cited Gayatri Balasamy v. ISG Novasoft and Ssangyong Engineering v. NHAI to argue that courts must not re-appreciate evidence under Section 34. It submitted that the Tribunal’s reasoning was commercially rational: the 50% discount reflected the absence of price negotiation and inflated costs; the delay attribution was based on contemporaneous Minutes of Meeting; and the dual purpose of the Advance Payment Guarantee was a reasonable contractual interpretation. It emphasized that the Supreme Court’s observation was jurisdictional, not directive.

The Court's Analysis

The Court undertook a meticulous review of the Impugned Award and the evidence. It held that patent illegality under Section 34 requires the absence of reasoning or reasoning so illogical that no reasonable person could have adopted it - not mere disagreement with the outcome.

"It is only when there is no reasoning at all that the standard of patent illegality on the face of the award would be attracted. If reasons are indeed accorded, unless there are illogical reasons that no reasonable person would provide, there is a wider leeway to Arbitral Tribunals to provide reasons for its adjudication."

On the risk purchase claim, the Court noted the Tribunal had considered Siemens’ submission of 29.89 Crores, Paharpur’s admission of 13.54 Crores, and the absence of price negotiation or documentation justifying inflated rates. The 50% reduction was not arbitrary but a reasoned discount based on evidentiary uncertainty - a permissible exercise under commercial arbitration.

Regarding liquidated damages, the Court found the Tribunal had correctly applied Clause 2.1 of the GRA, which required only a finding of delay exceeding 100 days. The Tribunal’s reliance on Minutes of Meeting and the abandonment of challenges to those documents by Paharpur at final hearing rendered the delay attribution valid. The Court rejected Paharpur’s attempt to import a criminal standard of proof into a civil arbitration.

On the bank guarantee issue, the Court held that the Tribunal’s interpretation of the Advance Payment Guarantee as also serving as a Performance Guarantee was commercially logical. The contract did not provide for automatic discharge upon adjustment of advance, indicating the parties intended continued security. The Tribunal’s finding of no mala fide intent was supported by evidence and could not be disturbed.

"The contention that the Learned Arbitral Tribunal has whimsically equated the Performance Bank Guarantee and the Advance Bank Guarantee is not a tenable criticism. The reasoning for which the Learned Arbitral Tribunal has equated the two is indeed logical and does not make out a case for constituting a view that no reasonable person would have taken."

The Court further clarified that the Supreme Court’s 2015 observation was not a direction but a clarification that the dispute was civil in nature and belonged in arbitration - not a mandate to decide the issue in a particular manner.

The Verdict

The Petition was dismissed. The Bombay High Court upheld the Impugned Award dated 27.02.2019 in its entirety. Siemens is entitled to retain the net amount of Rs. 20.84 Crores awarded to Paharpur, with 6% interest from the date of accrual of the cause of action, which has already been paid. No further relief, including refund of bank guarantee amounts or interest thereon, is granted. The Court found no patent illegality, perversity, or failure of reasoning warranting interference under Section 34.

What This Means For Similar Cases

Reasoned Approximation Is Sufficient in Arbitration

  • Practitioners must now accept that arbitral tribunals may use rough estimates where precise quantification is impractical due to complex, multi-party projects.
  • A 50% reduction based on documented inconsistencies (e.g., inflated rates, lack of negotiation) is not per se arbitrary - it is a recognized form of equitable adjustment.
  • Challenges under Section 34 must focus on absence of reasoning, not the adequacy of the number.

Delay Attribution Does Not Require Perfect Apportionment

  • If a party is found responsible for delay exceeding the contractual threshold (e.g., 100 days), liquidated damages may be awarded even if the other party contributed to delay.
  • The burden is not to apportion delay precisely, but to establish that the defaulting party caused delay sufficient to trigger the clause.
  • Contemporaneous documents like Minutes of Meeting are decisive if not challenged at final hearing.

Bank Guarantees: Contractual Interpretation Trumps Technical Distinctions

  • Advance Payment Guarantees and Performance Guarantees may be interpreted as overlapping if the contract language supports it.

  • Courts will not interfere with commercial interpretations unless they are wholly irrational.

  • Allegations of fraud in guarantee invocation must be substantiated with evidence - mere procedural objections are insufficient.

  • Always examine the contract’s express terms before arguing statutory or technical distinctions.

  • Avoid framing Section 34 challenges as "evidence re-appreciation" - focus on absence of reasoning or patent illegality.

  • Use Ssangyong and Kailash Nath to argue for judicial restraint in arbitration matters.

Case Details

Paharpur Cooling Towers Ltd v. Siemens Limited

2026:BHC-OS:12504
PDF
Court
High Court of Judicature at Bombay
Date
08 June 2026
Case Number
Commercial Arbitration Petition No. 996 of 2019
Bench
Somashekhar Sundaresan, J.
Counsel
Pet: Siddharth Datta, Suhani D., Kriti Kalyani, Siddhant Marathe
Res: Rashmin Khandekar, Chakrapani Misra, Jeevan Ballav Panda, Rahul Kaushik, Ananya Mishra

Frequently Asked Questions

Yes, under Section 34 of the Arbitration and Conciliation Act, 1996, an arbitral tribunal may adopt a rough and ready estimate if it provides a reasoned basis for the approximation, especially where evidence is complex or parties have failed to establish precise causation, as held in this judgment.
Yes, if the tribunal finds that the defaulting party caused delay exceeding the contractual threshold (e.g., 100 days), liquidated damages may be awarded even if the other party also contributed to delay, provided the threshold is met and the award is based on reasoned appreciation of evidence.
Yes, if the contract does not provide for automatic discharge upon adjustment of the advance and the parties intended continued security, an arbitral tribunal may reasonably interpret the Advance Payment Guarantee as also functioning as a Performance Guarantee, and courts will not interfere with such a commercially logical interpretation.