
After nearly three decades of delay, the Orissa High Court has affirmed that a final order enhancing compensation under Section 28-A of the Land Acquisition Act, 1894, cannot be indefinitely stalled by bureaucratic inertia. The Court issued a binding directive for immediate sanction and payment of differential compensation to land losers, reinforcing the state’s obligation to deliver justice without undue delay.
Background & Facts
The Dispute
The petitioners, five landowners from Deogarh district, Odisha, lost their land to acquisition under a notification dated 15.02.1979 issued under the Land Acquisition Act, 1894. The acquisition was for a public purpose related to water resource development. The compensation awarded at the time of acquisition was challenged by the petitioners before the Civil Judge (Senior Division), Deogarh, in L.A. Misc. Case No.19 of 1997, which resulted in a reference under Section 18 of the Act. The Civil Judge passed an order on 07.08.1999 enhancing the compensation amount.
Key Facts
- The petitioners did not file fresh applications under Section 18 but instead invoked Section 28-A of the Act to claim enhanced compensation based on the 07.08.1999 judgment.
- On 13.04.2015, the Zone Officer, L.A. & R.R. Zone, Deogarh, passed an order enhancing the compensation payable to the petitioners, in accordance with the 1999 judgment.
- The enhanced compensation amount was calculated and submitted to the Department of Water Resources for financial sanction.
- Despite the 2015 order, no sanction was granted, and no payment was made to the petitioners.
- On 31.01.2023, the Zone Officer, L.A. & R.R. Zone, Baghaubaol, Talcher, submitted all records to the Water Resources Department for sanction, but the matter remained pending.
- The petitioners filed the writ petition on 2026, seeking enforcement of the 2015 order.
Procedural History
- 15.02.1979: Notification issued for acquisition of petitioners’ land
- 1997: L.A. Misc. Case No.19 of 1997 filed before Civil Judge (Sr. Division), Deogarh
- 07.08.1999: Civil Judge enhanced compensation under Section 18
- 13.04.2015: Zone Officer, Deogarh, passed order enhancing compensation under Section 28-A
- 31.01.2023: Zone Officer, Talcher, submitted records to Water Resources Department
- 27.02.2026: Orissa High Court directed State to report status of compensation
- 15.04.2026: State counsel sought adjournment citing lack of instructions
- 29.04.2026: Hearing concluded with production of two official letters seeking three-month extension
Relief Sought
The petitioners sought a direction to the State to release the differential compensation as determined in the order dated 13.04.2015, along with statutory dues and interest, and to ensure payment without further delay.
The Legal Issue
The central question was whether a final order passed under Section 28-A of the Land Acquisition Act, 1894, enhancing compensation, can be withheld indefinitely by the State on grounds of pending financial sanction, despite the lapse of over 27 years since acquisition and 11 years since the enhancement order.
Arguments Presented
For the Petitioners
Mr. Kousik Ananda Guru, Advocate, submitted that the 2015 order under Section 28-A was final and binding. The petitioners had acted in good faith by relying on the judicial enhancement under Section 18, and Section 28-A was specifically designed to ensure equitable compensation without requiring fresh litigation. He cited State of Haryana v. Sardar Singh to emphasize that delay in payment of enhanced compensation violates the right to property under Article 300A and amounts to arbitrary state action. He argued that bureaucratic inertia cannot override a judicially determined entitlement.
For the Respondent
Mr. Swayambhu Mishra, Additional Standing Counsel, acknowledged the delay but contended that the matter was pending due to procedural requirements for fund allocation and inter-departmental coordination. He produced two letters dated 29.04.2026 from the Director, R & R, requesting three months to sanction the amount, arguing that the delay was administrative, not malicious.
The Court's Analysis
The Bench examined the nature and purpose of Section 28-A, which was inserted to provide a streamlined mechanism for land losers to claim enhanced compensation based on subsequent judicial awards, without initiating fresh proceedings. The Court noted that the provision was intended to prevent prolonged injustice to landowners who, having already litigated under Section 18, are left in limbo due to executive inaction.
"The purpose of Section 28-A is to ensure that the benefit of enhanced compensation awarded by a court is not rendered illusory by the State’s failure to act. A final order under this section is not a recommendation; it is a statutory entitlement."
The Court rejected the State’s plea for a three-month extension, observing that the delay since acquisition (27 years) and since the enhancement order (11 years) was inexcusable. It emphasized that the State’s duty to pay compensation is not contingent on budgetary convenience but is a constitutional obligation under Article 300A. The Court further noted that the Zone Officer had fulfilled his duty in 2015 and again in 2023, and the onus now lay squarely on the Department of Water Resources.
The Court held that the State’s failure to act constituted a violation of the petitioners’ right to just and fair compensation, and that the doctrine of laches could not be invoked to defeat a statutory right.
The Verdict
The petitioners succeeded. The Court directed that the necessary sanction for the differential compensation, as determined in the order dated 13.04.2015, shall be granted by 24th June, 2026. The differential amount, along with statutory dues and interest at the rate of 9% per annum from 15.02.1979, shall be disbursed by end of July, 2026, upon verification of entitlement and due acknowledgment. The State is directed to communicate a certified copy of this order to the Zone Officer, L.A. & R.R. Zone, Deogarh, and the Director, R & R, Department of Water Resources, within 48 hours.
What This Means For Similar Cases
Final Orders Under Section 28-A Are Enforceable Rights
- Practitioners must treat Section 28-A orders as judicially enforceable entitlements, not administrative recommendations
- Delay beyond 10 years in implementing such orders constitutes prima facie violation of Article 300A
- No further application or petition is required to enforce a final Section 28-A order
State Bureaucracy Cannot Override Judicial Determination
- Financial sanction cannot be used as a shield to delay payment of court-determined compensation
- Departments must act within reasonable timelines; failure triggers writ jurisdiction under Articles 226 and 227
- Courts will impose strict deadlines for compliance, as seen here with June - July 2026 timelines
Interest Accrues from Date of Acquisition, Not Order Date
- Interest under Section 28-A is not limited to the period after the enhancement order
- The Court affirmed that interest must run from the date of acquisition (15.02.1979), aligning with the principle that compensation must be fair and just at the time of taking






