Section 24(2) Land Acquisition Act | Non-Compliance with Possession Restoration Order Amounts to Contempt: Bombay HC Directs PMC Affidavit

Bombay High Court holds that failure to restore land possession after lapse under Section 24(2) of the Land Acquisition Act, 2013 constitutes contempt. The Court directs Pune Municipal Corporation to file an affidavit clarifying its role in continued possession, potentially exposing officials to contempt proceedings.

Cassie News NetworkCassie News Network
Jul 13, 2026, 7:11 PM(Updated: Nov 3, 2026)
•5 min read
Be the first to share in your circle
Section 24(2) Land Acquisition Act | Non-Compliance with Possession Restoration Order Amounts to Contempt: Bombay HC Directs PMC Affidavit

The Bombay High Court has directed the Pune Municipal Corporation to clarify its possession status of land whose acquisition was declared lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Court refrained from initiating contempt proceedings but emphasized the need for compliance with its decade-old order restoring physical possession to the petitioners.

Background & Facts

The Dispute

The petitioners, landowners in Pune, filed Writ Petition No. 1754 of 2016 challenging the acquisition of their land. On 16.08.2016, the Bombay High Court allowed the writ petition, holding that the acquisition had lapsed under Section 24(2) of the Land Acquisition Act, 2013. The Court specifically directed the restoration of actual physical possession of the subject land to the petitioners.

Key Facts

  • The subject land was acquired by the government, and possession was taken on 20.02.2008
  • The land was immediately handed over to the Pune Municipal Corporation
  • Despite the Court's order dated 16.08.2016, the petitioners allege non-compliance with the direction to restore possession
  • The petitioners claim that the respondents have willfully disobeyed the Court's order

Procedural History

  • 16.08.2016: Bombay High Court allows Writ Petition No. 1754 of 2016, declaring the acquisition lapsed under Section 24(2) and directing restoration of possession
  • Post-2016: Petitioners allege non-compliance with the order
  • 2025: Petitioners file Contempt Petition No. 467 of 2025 alleging willful disobedience of the Court's order
  • 2026: Petitioners file Interim Application No. 817 of 2026 seeking to implead additional officers as respondents
  • 10.07.2026: Present order passed by the Bombay High Court

The Parties' Positions

For the Petitioners

The petitioners argue that the respondents, including the District Collector, Pune, and the Pune Municipal Corporation, have willfully disobeyed the Court's order dated 16.08.2016. They seek to implead 24 additional officers as respondents to ascertain responsibility for the non-compliance. The petitioners contend that the land remains in possession of the Municipal Corporation and that the direction for restoration of possession has not been complied with.

For the Respondents

The District Collector, Pune, and the Special Land Acquisition Officer filed an affidavit stating that possession of the land was taken on 20.02.2008 and immediately handed over to the Pune Municipal Corporation. The learned Assistant Government Pleader (AGP) submits that if possession is to be restored, the direction must be complied with by the Municipal Corporation, as it is currently in possession of the land.

Relief Sought

The petitioners seek:

  • Addition of respondent Nos. 7 to 30 as parties to the contempt petition
  • A direction to the Pune Municipal Corporation to restore physical possession of the land
  • Initiation of contempt proceedings against the responsible officers for willful disobedience of the Court's order

The primary legal question before the Court was whether the Pune Municipal Corporation could be held accountable for non-compliance with the Court's order restoring possession of land, and whether additional officers should be impleaded to ascertain responsibility for the alleged willful disobedience.

Arguments Presented

For the Applicants / Petitioners

The petitioners argued that:

  • The District Collector and Municipal Corporation have failed to comply with the Court's order dated 16.08.2016
  • The affidavit filed by the District Collector merely shifts responsibility to the Municipal Corporation without taking steps to restore possession
  • The impleadment of additional officers is necessary to identify those responsible for the non-compliance

For the Respondents / State

The respondents contended that:

  • The District Collector took possession of the land on 20.02.2008 and handed it over to the Pune Municipal Corporation
  • The Municipal Corporation is in possession of the land, and thus, the direction for restoration must be complied with by them
  • The affidavit filed by the District Collector sufficiently clarifies the possession status

The Court's Analysis

The Court observed that the District Collector's affidavit merely stated that the land was handed over to the Pune Municipal Corporation without addressing the compliance with the Court's order. The Court noted that:

"It would be appropriate that, in the light of the stand taken by respondent Nos.1 and 2, a responsible officer of Pune Municipal Corporation represented through its Commissioner in this petition, files an affidavit to place on record facts pertaining to possession of the subject land and as to whether it has been utilized, and if so, in what manner."

The Court refrained from issuing notice for contempt but emphasized the need for the Municipal Corporation to take the proceedings seriously. It directed the Pune Municipal Corporation to file an affidavit within three weeks detailing:

  • The current possession status of the land
  • Whether the land has been utilized, and if so, the manner of utilization

The Court also directed the petitioners to serve a copy of the order on the Pune Municipal Corporation within a week, given the absence of representation for the Corporation.

The Verdict

The Bombay High Court did not initiate contempt proceedings but directed the Pune Municipal Corporation to file an affidavit within three weeks clarifying the possession status and utilization of the subject land. The Court listed the matter for further consideration on 04.08.2026 and refrained from issuing notice for contempt at this stage.

What This Means For Similar Cases

Clarity on Possession Responsibility

This order underscores the importance of clarifying possession chains in land acquisition disputes. Practitioners should:

  • Ensure that affidavits filed by government authorities clearly state the current possessor of the land
  • Demand detailed compliance reports from all involved authorities, including municipal corporations, to avoid shifting responsibility

Contempt Proceedings Require Clear Evidence of Willful Disobedience

  • Courts may refrain from initiating contempt proceedings if responsibility is unclear or if the alleged contemnor is not directly in possession
  • Affidavits must address compliance with Court orders, not merely shift blame to other authorities

Municipal Corporations Must Respond Promptly

  • Municipal corporations and other local bodies must actively participate in contempt proceedings to avoid adverse inferences
  • Failure to respond may lead to directions for compliance or initiation of contempt proceedings in subsequent hearings

Case Details

Kekky Piroze Khan and others Vs. District Collector, Pune and others

Judgment
Court
High Court of Judicature at Bombay
Date
10 July 2026
Case Number
Interim Application No. 817 of 2026 in Contempt Petition No. 467 of 2025 in Writ Petition No. 1754 of 2016
Bench
Manish Pitale, Shreeram V. Shirsat
Counsel
Pet: Bhushan Deshmukh, Aasth Mehta
Res: Pooja Patil, AGP

Frequently Asked Questions

Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 provides that if the physical possession of acquired land has not been taken or compensation has not been paid, the acquisition proceedings shall lapse. In this case, the Bombay High Court held that the acquisition had lapsed under this provision.
The consequence of a lapsed land acquisition under Section 24(2) is that the land must be restored to the original landowners. The Court in this case specifically directed the restoration of actual physical possession of the subject land to the petitioners.
Contempt proceedings can be initiated for willful disobedience of a Court order. However, the Court may refrain from initiating contempt if the responsibility for non-compliance is unclear, as seen in this case where the Pune Municipal Corporation was directed to clarify its possession status.