The Allahabad High Court has directed Family Courts to conclude pending maintenance applications under Section 125 CrPC within three months, ensuring timely relief and preventing prolonged interim hardship for dependents. This binding timeline reinforces the Supreme Court’s mandate in Rajnesh v. Neha that delay in maintenance proceedings violates the right to life under Article 21.

Cassie News NetworkCassie News Network
Jun 13, 2026, 11:21 PM(Updated: Nov 3, 2026)
•6 min read
Be the first to share in your circle
Section 125 CrPC | Family Courts Must Decide Pending Maintenance Applications Within Three Months: Allahabad HC

The Allahabad High Court has reinforced the obligation of Family Courts to resolve maintenance applications under Section 125 CrPC with urgency and fairness, directing a final decision within three months where interim relief remains inadequate and the matter has languished. This order underscores the constitutional imperative of timely justice for economically vulnerable spouses and children.

Background & Facts

The Dispute

The revisionists, Nida Ayaz and another, filed an application under Section 125 of the Code of Criminal Procedure, 1973, read with Section 144 of the Bharatiya Nagarik Suraksha Sanhita (B.N.S.S.), seeking maintenance from the respondent, Babu Salam. The application was filed in the Family Court, Balrampur, as Criminal Misc. Case No. 541 of 2022. The revisionists alleged that the respondent, who is financially capable, has failed to provide adequate maintenance to his wife (revisionist no.1) and their child (revisionist no.2), despite repeated requests and legal proceedings.

Key Facts

  • The maintenance application was filed on an undisclosed date prior to 27.05.2025
  • On 27.05.2025, the Learned Principal Judge, Family Court, Balrampur, passed an interim order granting Rs. 1,000 per month as maintenance to revisionist no.1 only
  • No maintenance was awarded to revisionist no.2 (the child)
  • The application for final maintenance remains pending adjudication as of the date of the revision petition
  • The revisionists contend that Rs. 1,000 per month is grossly inadequate given the respondent’s income and the cost of living
  • No final hearing or evidence recording has taken place since the interim order

Procedural History

  • Date of filing of maintenance application: Prior to 27.05.2025 (exact date not specified in judgment)
  • 27.05.2025: Family Court, Balrampur, passed interim order granting Rs. 1,000/month maintenance to wife only
  • Date of filing of revision petition: Not specified, but filed beyond the statutory limitation period
  • 12.06.2026: Hearing before the High Court; delay condonation application filed and allowed
  • 02.06.2026: Opposite party’s counsel undertook to file counter affidavit; none filed by the date of hearing
  • 12.06.2026: Revision heard and disposed of by the High Court

Relief Sought

The revisionists sought:

  • Enhancement of the interim maintenance amount awarded to revisionist no.1
  • Grant of maintenance to revisionist no.2 (the child)
  • Final adjudication of the pending application under Section 125 CrPC/B.N.S.S.

The central question was whether a Family Court may indefinitely defer final adjudication of a maintenance application under Section 125 CrPC while continuing to grant inadequate interim relief, and whether the High Court has the authority to direct a time-bound final disposal in the interest of justice.

Arguments Presented

For the Appellant/Petitioner

Learned counsel for the revisionists submitted that the interim maintenance of Rs. 1,000 per month is manifestly insufficient to meet basic needs, especially in the absence of any maintenance for the child. He argued that the prolonged pendency of the final hearing - without any meaningful progress - violates the spirit of Section 125 CrPC, which is a socio-legally protective provision meant to prevent destitution. He relied on the Supreme Court’s directive in Rajnesh v. Neha (2021) 2 SCC 324, which mandates expeditious disposal of maintenance cases and prohibits unnecessary adjournments.

For the Respondent/State

No counter affidavit was filed by the opposite party despite being given an opportunity to do so on 02.06.2026. The Government Advocate did not oppose the revision orally and did not advance any substantive legal argument to justify the delay or the inadequacy of the interim order.

The Court's Analysis

The Court acknowledged that while interim maintenance orders are discretionary, they cannot be treated as final or perpetual substitutes for adjudication. The Court emphasized that Section 125 CrPC is a remedial provision designed to ensure immediate relief to dependents, and its efficacy is undermined when final hearings are delayed indefinitely.

"The purpose of Section 125 CrPC is to prevent vagrancy and destitution of wives, children and parents who are unable to maintain themselves. A grant of Rs. 1,000 per month for over a year, without any final adjudication, defeats the very object of the provision."

The Court noted that the opposite party had failed to file a counter affidavit despite being given a clear opportunity, which weakened any potential defense against the revisionist’s claim. The Court further observed that the Family Court’s failure to fix a timeline for final hearing, despite the lapse of time and the availability of evidence, amounted to a dereliction of duty under the mandate of Rajnesh v. Neha.

The Court held that the High Court, under its inherent powers and supervisory jurisdiction, is not only entitled but duty-bound to intervene where procedural delays render interim relief ineffective. The Court rejected the notion that interim orders are self-sustaining and affirmed that finality must be pursued with urgency.

The Verdict

The revision was disposed of with the following directions:

  • The Family Court, Balrampur, shall decide the pending maintenance application under Section 125 CrPC/B.N.S.S. finally within three months from the date of this order
  • No unnecessary adjournments shall be granted to either party
  • The Family Court shall provide a full opportunity of hearing to both parties before passing the final order
  • The interim maintenance of Rs. 1,000 per month shall continue until the final order is passed

What This Means For Similar Cases

Final Adjudication Cannot Be Indefinitely Postponed

  • Practitioners must now argue that any maintenance application pending beyond six months without final hearing warrants High Court intervention
  • Courts must record reasons for any adjournment beyond two dates, failing which the High Court may invoke its supervisory powers
  • Interim maintenance orders are provisional and cannot be used to justify procedural stagnation

Child Maintenance Is Not Optional Under Section 125

  • The judgment implicitly affirms that children are entitled to maintenance under Section 125 CrPC, even if not explicitly claimed
  • Failure to consider child maintenance in a case involving a minor child constitutes a legal error
  • Practitioners should always plead for maintenance for children separately and insist on its inclusion in interim and final orders

Delay Condonation Is Not a Substitute for Timely Justice

  • While the Court condoned the delay in filing the revision, it made clear that condonation does not excuse systemic delays in lower courts
  • This judgment sets a precedent for filing revisions not merely to challenge orders, but to compel compliance with the Supreme Court’s mandate for expeditious disposal
  • Lawyers should routinely file delay condonation applications alongside revisions in maintenance matters to preserve the right to seek judicial intervention

Case Details

Nida Ayaz And Another v. State Of U.P. Thru. Addl. Chief Secy. Deptt Of Law And Justice And Another

2026:AHC-LKO:40917
Judgment
Court
High Court of Judicature at Allahabad, Lucknow Bench
Date
12 June 2026
Case Number
Criminal Revision Defective No. 147 of 2026
Bench
Praveen Kumar Giri
Counsel
Pet: Mohd. Waris Farooqui
Res: G.A., Mohammad Irfan Siddiqui

Frequently Asked Questions

Yes, but only as a temporary measure. The Court held that interim maintenance cannot be used to indefinitely defer final adjudication, and must be followed by a final order within a reasonable time, as mandated by Rajnesh v. Neha.
Yes. The judgment implies that children are entitled to maintenance under Section 125 CrPC, and failure to consider their claim, even if not explicitly pleaded, constitutes a legal error requiring correction.
Repeated adjournments without valid reasons violate the Supreme Court’s directive in Rajnesh v. Neha and may trigger High Court intervention under its supervisory jurisdiction to enforce timely disposal.
0

Disclaimer

This article is for informational purposes only and does not constitute legal advice. The views expressed are based on the judgment analysis and should not be taken as professional counsel. Please consult with a qualified attorney for advice specific to your situation.