
The Bombay High Court has reaffirmed that the statutory mandate under Section 11 of the Maharashtra Ownership Flats Act, 1963, is designed to protect flat purchasers from promoter inaction. Where a project is fully completed and agreements clearly define the property to be conveyed, technical objections to documentation cannot defeat the right to unilateral deemed conveyance.
Background & Facts
The Dispute
The petitioner, Shabnoor Ayub Pathan Cooperative Housing Society, sought unilateral deemed conveyance of an entire residential plot under Section 11 of the Maharashtra Ownership Flats Act, 1963 (MOFA). The promoter, Respondent No. 2, had developed 76 row bungalows on Survey No. 69, Hissa No. 2/2, Mauje Belavli, Badlapur (East), admeasuring 22,500 sq. mtrs., but failed to execute conveyance in favour of the society despite repeated demands.
Key Facts
- A Development Agreement was executed on 04.11.2004 between landowners and Respondent No. 2, granting development rights
- IOD and Commencement Certificate were granted on 08.12.2004
- Between 2004 and 2009, individual purchasers entered into agreements for sale under Section 4 of MOFA
- Each agreement included Schedule 'A' specifying the 22,500 sq. mtrs. plot as the subject property
- Clauses (38)(a) and (40) of the agreements obligated the promoter to form a cooperative society and convey the entire property
- Occupation Certificates were issued in phases: 07.04.2006, 11.12.2007, and finally 01.04.2009
- The project was fully completed by 01.04.2009
- The Cooperative Housing Society was registered on 03.01.2014
- A legal notice demanding conveyance was issued on 30.06.2014
- The petitioner filed an application for deemed conveyance on 22.09.2014, submitting all requisite documents and hard copies
- The Architect’s Certificate indicated a built-up area of 7,953.84 sq. mtrs. against a permissible FSI of 0.85 (allowing 9,193.68 sq. mtrs.)
- No excess construction was alleged or proven
Procedural History
- 04.11.2004: Development Agreement executed
- 08.12.2004: IOD and Commencement Certificate granted
- 07.04.2006: First Occupation Certificate issued
- 11.12.2007: Second Occupation Certificate issued
- 01.04.2009: Final Occupation Certificate issued - project fully completed
- 03.01.2014: Petitioner Society registered
- 30.06.2014: Legal notice issued to promoter demanding conveyance
- 22.09.2014: Application for deemed conveyance filed under Section 11 MOFA
- 14.07.2015: Competent Authority rejected application on ground of alleged discrepancy in area
- 11.11.2015: Writ Petition No. 11689 of 2015 filed before Bombay High Court
- 30.03.2026: Judgment delivered by the High Court
The Parties' Positions
Petitioner: Argued that the promoter’s statutory and contractual obligations under MOFA were triggered upon completion of the project on 01.04.2009. The agreements clearly defined the property, the society was duly formed, and the promoter’s non-appearance before the Competent Authority rendered the rejection arbitrary. The minor discrepancy in the Architect’s Certificate did not affect the identity or extent of the land.
Respondents: Did not appear before the Competent Authority or the High Court. No rebuttal, evidence, or counter-submission was filed.
Relief Sought
The petitioner sought an order directing the Competent Authority to grant unilateral deemed conveyance of the entire 22,500 sq. mtrs. plot to the Cooperative Housing Society, setting aside the order dated 14.07.2015.
The Legal Issue
Whether a minor discrepancy in the area mentioned in the Architect’s Certificate can justify rejection of an application for deemed conveyance under Section 11 of MOFA, when the project is completed, the agreements clearly define the property, and the promoter has failed to respond or contest the claim?
Arguments Presented
For the Petitioner
The petitioner relied on the clear language of Section 11 of MOFA, which empowers the Competent Authority to grant deemed conveyance upon proof of completion and promoter default. It cited the agreements under Section 4, which explicitly obligated the promoter to convey the entire 22,500 sq. mtrs. plot. The Architect’s Certificate showed construction was within permissible FSI limits, and any discrepancy in area figures was immaterial to the identity of the property. The promoter’s non-appearance rendered the Competent Authority’s rejection legally unsustainable.
For the Respondent
No arguments were presented by the respondents, who failed to appear before the Competent Authority or the High Court.
The Court's Analysis
The Court emphasized that Section 11 of MOFA is a remedial provision intended to protect flat purchasers from promoter inaction. The statutory scheme does not require perfect documentation but rather substantive compliance with the obligation to convey. The agreements executed under Section 4 of MOFA, particularly Schedule 'A', unambiguously identified the 22,500 sq. mtrs. plot as the subject of conveyance. The issuance of Occupation Certificates up to 01.04.2009 confirmed full completion of the project, triggering the promoter’s statutory duty.
"The Competent Authority rejected the application primarily on the ground of discrepancy in the area mentioned in the Architect's Certificate. Such a ground, in the considered view of this Court, is wholly insufficient to deny substantive relief under Section 11 of MOFA, particularly when the discrepancy, if any, is not shown to affect the identity or extent of the property sought to be conveyed."
The Court noted that the total built-up area (7,953.84 sq. mtrs.) was well within the permissible limit (9,193.68 sq. mtrs.), and no allegation of unauthorized construction was raised. The promoter’s failure to appear or contest the application meant the uncontroverted evidence - including the agreements, sanctioned plans, and completion certificates - stood accepted. The Competent Authority’s reliance on a technical discrepancy, without examining its materiality, amounted to a failure to discharge its statutory duty.
The Verdict
The writ petition was allowed. The order dated 14.07.2015 of the Competent Authority was set aside. The Competent Authority was directed to grant unilateral deemed conveyance of the entire property admeasuring 22,500 sq. mtrs. to the Shabnoor Ayub Pathan Cooperative Housing Society within four weeks. There shall be no order as to costs.
What This Means For Similar Cases
Minor Documentation Errors Cannot Defeat Statutory Relief
- Practitioners must argue that under Section 11 MOFA, the focus is on completion of the project and promoter default, not perfection of documents
- Discrepancies in area figures, if not material to property identity, are irrelevant - the sanctioned plan and sale agreements prevail
- Non-appearance by the promoter renders the Competent Authority’s rejection arbitrary and liable to be set aside
Completion Triggers Obligation, Not Registration
- The statutory obligation to convey arises upon issuance of the final Occupation Certificate, not upon society registration
- Delay in society formation does not extinguish the purchaser’s right to conveyance
- Applications under Section 11 can be filed even years after completion, provided promoter remains in default
Evidence Hierarchy in MOFA Cases
- Sale agreements under Section 4 are primary evidence of the property to be conveyed
- Sanctioned plans and Occupation Certificates confirm completion
- Architect’s certificates are secondary; discrepancies must be shown to materially affect the property
- Promoter’s silence constitutes admission of uncontroverted facts






