Case Law Analysis

Post-Award Interest Cannot Be Contracted Out | Arbitration Act Section 31(7)(b) : Delhi High Court

The Delhi High Court has held that post-award interest under Section 31(7)(b) of the Arbitration Act is statutory and cannot be excluded by contract, and that contractor-initiated extra work under Clause 11 of the GCC is enforceable despite employer inaction.

Cassie News NetworkCassie News Network
Feb 26, 2026, 8:54 AM(Updated: Nov 3, 2026)
•6 min read
Be the first to share in your circle
Post-Award Interest Cannot Be Contracted Out | Arbitration Act Section 31(7)(b) : Delhi High Court

The Delhi High Court has reaffirmed a foundational principle of Indian arbitration law: parties cannot contract out of statutory post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996. This judgment clarifies the boundaries of party autonomy and reinforces the statutory framework governing enforcement of arbitral awards.

Background & Facts

The Dispute

The dispute arose from a construction contract executed on 05.11.2014 between M/s Ircon International Limited and M/s Cannon Engineering Construction for civil works at NTPC’s Solapur Super Thermal Power Project. The Respondent claimed entitlement to additional payments for excavation in hard rock, use of tie bolts in RCC shuttering, reimbursement of enhanced statutory levies, and final bill adjustments. The Appellants denied these claims, asserting contractual prohibitions and lack of prior approval.

Procedural History

  • 2019: Respondent invoked arbitration under Clause 56 of the General Conditions of Contract.
  • 2021: Sole Arbitrator Justice (Retd.) Sunil Ambwani awarded Rs. 1,17,55,347.74 for hard rock excavation, Rs. 54,08,398.79 for tie bolts, Rs. 8,31,936.39 for statutory levies, and Rs. 49,19,400.53 for the final bill.
  • 2021: Appellants filed a Section 34 petition to set aside the award. The Single Judge upheld most findings but set aside pre-award interest awarded under Section 70 of the Indian Contract Act.
  • 2022: Appellants filed the present appeal under Section 37 of the Arbitration Act, challenging the award on hard rock classification, tie bolts, future interest, and costs.

Relief Sought

The Appellants sought to set aside the arbitral award on grounds of patent illegality, arguing that the Tribunal misapplied contractual definitions, ignored mandatory approval procedures, and improperly awarded future interest despite express contractual prohibition.

The central question was whether Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 permits parties to contract out of entitlement to post-award interest, and whether the Arbitral Tribunal’s classification of excavation material as hard rock and its reliance on Clause 11 of the General Conditions of Contract constituted patent illegality.

Arguments Presented

For the Appellant

The Appellants contended that the Tribunal’s classification of excavation as hard rock violated Clause 2.1 of the CPWD Specifications, which required manual excavatability for ordinary rock and blasting for hard rock. They argued that since the material could be loosened by light blasting, it qualified as ordinary rock. They further asserted that Clause 10 required prior written approval for extra work, and the Respondent’s unilateral execution without such approval invalidated the claim. Regarding interest, they relied on Union of India v. Manraj Enterprises to argue that contractual prohibition on interest barred all interest, including post-award.

For the Respondent

The Respondent argued that the Tribunal’s factual findings on hard rock were supported by contemporaneous Field Book entries, expert geological reports, and conduct of the parties. They maintained that Clause 11 governed contractor-initiated extra work, not Clause 10, and that the Appellants’ inaction estopped them from denying payment. On interest, they relied on R.P. Garg v. Telecom Department to assert that Section 31(7)(b) creates a statutory right to post-award interest that cannot be excluded by contract.

The Court's Analysis

The Court emphasized the limited scope of appellate review under Section 37, holding that courts cannot reappreciate evidence or substitute their view for that of the Arbitral Tribunal unless patent illegality or jurisdictional error is established.

"The appellate power under Section 37 of the Act is not akin to the normal appellate jurisdiction vested in the civil courts... The arbitral award is not liable to be interfered unless a case for interference as set out... is made out."

Regarding hard rock classification, the Court found no patent illegality. The Tribunal correctly interpreted Clause 2.1(b) and 2.1(c) of the CPWD Specifications, noting that the material’s inability to be excavated manually rendered it hard rock, irrespective of light blasting being feasible. The reliance on site records and expert reports was not extrinsic evidence but a means to apply contractual definitions to facts.

On tie bolts, the Court upheld the Tribunal’s application of Clause 11, distinguishing it from Clause 10. Clause 10 governs employer-directed variations, while Clause 11 provides a mechanism for contractor-initiated extra work. The Respondent’s timely notice under Clause 11, coupled with the Appellants’ failure to respond within three months, rendered their subsequent objection invalid. The maxim nullus commodum capere potest de injuria sua propria applied.

On future interest, the Court squarely addressed the contractual bar. Citing R.P. Garg v. Telecom Department and Morgan Securities v. Videocon Industries, it held that Section 31(7)(b) creates a statutory entitlement to post-award interest, and the phrase "unless the award otherwise directs" relates only to the rate, not the entitlement. Contractual prohibitions on interest apply only to pre-award interest under Section 31(7)(a).

"Clause (b) of Section 31(7) is therefore in contrast with clause (a) and is not subject to party autonomy. In other words, clause (b) does not give the parties the right to ‘contract out’ interest for the post-award period."

The award of costs was upheld as a discretionary exercise under Section 31A, given that four out of five claims were allowed in favor of the Respondent.

The Verdict

The Appellants’ appeal was dismissed. The Court held that Section 31(7)(b) creates a non-negotiable statutory right to post-award interest, the Arbitral Tribunal’s factual findings on hard rock and tie bolts were reasonable and supported by evidence, and Clause 11, not Clause 10, governed the Respondent’s claims. The arbitral award stood fully upheld.

What This Means For Similar Cases

Post-Award Interest Is Statutory and Non-Waivable

  • Practitioners must advise clients that any contractual clause attempting to exclude post-award interest is unenforceable under Section 31(7)(b).
  • Arbitrators may award interest at any rate they deem fit; if silent, the statutory rate of 18% applies.
  • Challenges to post-award interest on contractual grounds will fail unless the award itself is silent and the statutory rate is challenged.

Clause 11 Overrides Clause 10 for Contractor-Initiated Extra Work

  • Where a contractor notifies the Engineer-in-Charge of extra work within 14 days under Clause 11, and the Engineer fails to respond within three months, the contractor is entitled to payment.
  • Silence or inaction by the employer constitutes acquiescence, barring them from later denying liability.
  • Clause 10 applies only to employer-initiated variations; Clause 11 governs contractor-initiated claims.

Arbitral Findings on Technical Facts Are Final

  • Classification of materials, engineering methods, and site conditions are factual determinations reserved for the Arbitral Tribunal.
  • Courts will not interfere unless findings are perverse, unsupported by evidence, or violate the contract’s express terms.
  • Expert reports and contemporaneous site records are admissible to interpret contractual definitions, not to override them.

Case Details

M/s Ircon International Limited & Anr. v. M/s Cannon Engineering Construction Cannon Cottage

2026:DHC:1626-DB
PDF
Court
High Court of Delhi
Date
24 February 2026
Case Number
FAO(OS) (COMM) 16/2022
Bench
Justice C. Hari Shankar, Justice Om Prakash Shukla
Counsel
Pet: Puneet Taneja, Manmohan Singh Narula, Amit Yadav, Anil Kumar
Res: Simil Purohit, Faran Khan, Sandip Vimadalal, Manish Doshi, Rishit Vimadalal, Bharti Gupta

Frequently Asked Questions

No. Section 31(7)(b) creates a statutory entitlement to post-award interest that cannot be excluded by agreement. The phrase 'unless the award otherwise directs' relates only to the rate of interest, not the entitlement itself.
Clause 10 governs variations directed by the Engineer-in-Charge and requires written instructions. Clause 11 governs extra work initiated by the contractor, requiring notice within 14 days and allowing rate revision if the Engineer fails to respond within three months.
No. If the contractor complies with Clause 11 by timely notification and the employer remains silent for more than three months, the employer is estopped from denying payment, as their inaction constitutes acquiescence.
Yes. Tribunals may use contemporaneous records and expert evidence to apply contractual definitions to factual circumstances, provided the interpretation remains within the bounds of the contract and is not a re-writing of its terms.
0

Disclaimer

This article is for informational purposes only and does not constitute legal advice. The views expressed are based on the judgment analysis and should not be taken as professional counsel. Please consult with a qualified attorney for advice specific to your situation.