Case Law Analysis

Pre-Award Interest Barred by Contract | Post-Award Interest Mandatory Unless Explicitly Excluded : Supreme Court

Supreme Court holds that contractual bars on pre-award interest are enforceable under Section 31(7)(a) of the Arbitration Act, but post-award interest is statutory and cannot be contracted out.

Cassie News NetworkCassie News Network
Mar 2, 2026, 12:06 AM(Updated: Nov 3, 2026)
•6 min read
Be the first to share in your circle
Pre-Award Interest Barred by Contract | Post-Award Interest Mandatory Unless Explicitly Excluded : Supreme Court

The Supreme Court has clarified a critical distinction in arbitration jurisprudence: while parties may contractually prohibit interest accruing before an award is made, they cannot extinguish the statutory right to interest on the awarded sum after the award is rendered. This judgment reinforces the supremacy of party autonomy in pre-award interest matters while affirming that post-award interest operates as a mandatory legal remedy.

Background & Facts

The Dispute

The dispute arose from a turnkey contract dated 27.01.2011 between the Union of India and Larsen & Toubro Limited (L&T) for the modernization of the Jhansi Workshop of North Central Railways. The contract value was Rs. 93.08 crore, with an original completion deadline of 18.07.2012. The deadline was extended ten times, resulting in a 40-month delay. Disputes emerged over delayed payments, variations in foreign exchange rates, price adjustments, and indirect costs incurred during the extended project period.

Procedural History

  • 04.09.2017: L&T applied for appointment of an Arbitral Tribunal under Clause 64 of the General Conditions of Contract (GCC).
  • 10.01.2018: The three-member Arbitral Tribunal was formally constituted and entered into reference.
  • 25.12.2018: The Arbitral Tribunal issued an award in favor of L&T, granting Rs. 5.53 crore as net award, including pre-award interest on Claims 1, 3, and 6, and post-award interest at 12% per annum.
  • 15.09.2022: The Commercial Court, Jhansi, dismissed the Section 34 application challenging the award.
  • 25.05.2023: The Allahabad High Court upheld the award under Section 37 of the Act.
  • 2023: Union of India filed a Special Leave Petition before the Supreme Court.

Relief Sought

The Union of India sought to set aside the Arbitral Award to the extent it granted pre-award interest on claims arising from delayed payments, arguing that Clause 16(3) and Clause 64(5) of the GCC explicitly barred such interest. It also challenged the 12% post-award interest rate as excessive and unsupported.

The central question was whether Clause 16(3) and Clause 64(5) of the General Conditions of Contract validly prohibit an arbitral tribunal from awarding pre-award or pendente lite interest, and whether Section 31(7)(b) of the Arbitration and Conciliation Act, 1996, permits parties to contract out of post-award interest.

Arguments Presented

For the Appellant

The Union of India contended that Clause 16(3) of the GCC, which bars interest on "amounts payable to the contractor under the contract," is unambiguous and comprehensive. It relied on Union of India v. Bright Power Projects (India) (P) Ltd. and Union of India v. Manraj Enterprises to argue that Section 31(7)(a) subordinates the arbitrator’s discretion to the contract’s terms. The appellants further asserted that the tribunal’s characterization of interest as "compensation" was a subterfuge to circumvent the contractual bar. They also contended that Raveechee and Company and Ambica Construction were decided under the 1940 Act and are inapplicable to the 1996 Act.

For the Respondent

L&T argued that Clause 16(3) should be interpreted through ejusdem generis, limiting its scope to earnest money and security deposits only. It contended that Clause 64(5) only prohibits pendente lite interest on disputed amounts, not on admitted sums like final bills and PVC. L&T relied on RP Garg v. Chief General Manager to assert that Section 31(7)(b) mandates post-award interest as a statutory right, independent of contractual terms. It further argued that denying interest on admitted dues would amount to unjust enrichment of the Union.

The Court's Analysis

The Court undertook a rigorous statutory and contractual interpretation, distinguishing between pre-award and post-award interest under the 1996 Act.

First, the Court rejected the ejusdem generis argument. It held that the use of the disjunctive "or" in Clause 16(3) - "earnest money and security deposit or amounts payable to the contractor under the contract" - renders the phrase "amounts payable to the contractor under the contract" independent and expansive. The Court cited Manraj Enterprises to affirm that such language cannot be narrowed by interpretive rules.

"The expression 'amounts payable to the contractor under the contract' has to be read independently and disjunctively to earnest money deposit and security deposit as the word used is 'or' and not 'and'."

The Court emphasized that Section 31(7)(a) explicitly states that the arbitrator’s power to award pre-award interest is subordinate to the parties’ agreement. Where the contract expressly bars such interest, the tribunal has no jurisdiction to award it - even as "compensation." The tribunal’s award of interest on Claims 1, 3, and 6 was therefore held to be in direct violation of the contract and the Act.

Regarding post-award interest, the Court drew a sharp distinction. It held that Section 31(7)(b) operates independently of party autonomy. The phrase "unless the award otherwise directs" qualifies only the rate of interest, not the entitlement. The Court relied on RP Garg and Morgan Securities to affirm that post-award interest is a statutory default mechanism designed to ensure compliance with arbitral awards.

"Clause (b) does not give the parties the right to 'contract out' interest for the post-award period."

The Court further noted that Clause 64(5) only prohibits interest "till the date on which the award is made," leaving post-award interest unaffected. However, it found the 12% rate arbitrary and excessive. Citing Gayatri Balasamy v. ISG Novasoft, the Court held that courts may modify post-award interest rates under Section 31(7)(b) to ensure proportionality. The rate was reduced to 8% per annum to align with prevailing economic conditions and the statutory benchmark.

The Verdict

The Union of India succeeded in part. The Supreme Court set aside the award of pre-award interest on Claims 1, 3, and 6, holding it violative of the contractual bar under Clause 16(3) and Section 31(7)(a). However, it upheld the entitlement to post-award interest under Section 31(7)(b), modifying the rate from 12% to 8% per annum. The appeal was partly allowed.

What This Means For Similar Cases

Contractual Bars on Pre-Award Interest Are Enforceable

  • Practitioners must now rigorously examine arbitration clauses for express prohibitions on interest from the date of cause of action to the date of award.
  • Claims for "compensation" or "damages" that function as disguised interest will be struck down if the contract bars interest.
  • Arbitrators must explicitly state if they are awarding interest under Section 31(7)(a) and must justify why the contractual bar does not apply.

Post-Award Interest Is Statutorily Mandated

  • Parties cannot exclude post-award interest by contract; any such clause is void to the extent it conflicts with Section 31(7)(b).
  • Arbitrators must either specify a rate or default to the statutory rate (currently 2% above the prevailing rate under the Interest Act, 1978).
  • Courts retain the power to adjust post-award interest rates for fairness, even if the award is otherwise valid.

Arbitral Awards Must Clearly Distinguish Interest Types

  • Arbitral awards must separately identify pre-award and post-award interest components.
  • Failure to do so invites judicial scrutiny under Section 34 and Section 37.
  • Legal teams should draft pleadings to distinguish between admitted amounts (eligible for post-award interest) and disputed amounts (subject to contractual interest bars).

Case Details

Union of India v. Larsen & Toubro Limited

2026 INSC 203
Judgment
Court
Supreme Court of India
Date
27 February 2026
Case Number
Civil Appeal No. _______ of 2026 (@ SLP (C) No. 14989 of 2023)
Bench
Sanjay Karol, Vipul M. Pancholi
Counsel
Pet: Aishwarya Bhati
Res: Meenakshi Arora

Frequently Asked Questions

Yes. Section 31(7)(a) explicitly states that the arbitrator’s power to award interest from the date of cause of action to the date of award is subordinate to the parties’ agreement. If the contract expressly bars such interest, the arbitrator cannot award it, even as compensation.
Yes. Section 31(7)(b) mandates that the awarded sum shall carry interest from the date of award unless the award itself directs otherwise. This is a statutory default, and parties cannot contract out of this entitlement, regardless of any contractual prohibition on pre-award interest.
Yes. Under Section 31(7)(b), courts may modify the rate of post-award interest if it is arbitrary, excessive, or unjustified. The Supreme Court has affirmed that such modification is necessary to ensure proportionality and avoid setting aside the entire award on minor grounds.
No. Where the contract uses the disjunctive 'or' between specific items (like earnest money) and a general phrase (like 'amounts payable to the contractor'), the general phrase must be read independently. The Supreme Court has held that ejusdem generis cannot be used to narrow such broad contractual language.
0

Disclaimer

This article is for informational purposes only and does not constitute legal advice. The views expressed are based on the judgment analysis and should not be taken as professional counsel. Please consult with a qualified attorney for advice specific to your situation.