
The Bombay High Court has affirmed that a contractor’s claim for loss of profits remains viable even after contract expiry, provided the parties continued to engage beyond the stated term and the arbitral tribunal meticulously substantiates the claim with empirical evidence. This judgment reinforces the limited scope of judicial intervention under Section 34 of the Arbitration and Conciliation Act, 1996, and sets a clear standard for evaluating profit loss claims in commercial arbitrations.
Background & Facts
The Dispute
The dispute arose from a construction contract between Shri Balaji Sugars and Chemicals Pvt. Ltd. (Balaji), the employer, and Tamhankar Patil & Associates (TPA), the contractor, for the construction of a sugar factory in Bijapur, Karnataka. A work order was issued on March 22, 2013, followed by a formal Agreement on July 8, 2013. The contract stipulated a completion date of December 31, 2013.
Disputes emerged over delays, alleged abandonment of work by TPA, and unilateral deductions by Balaji from Running Account Bills (RA Bills). TPA claimed Balaji had arbitrarily withheld payments, changed the Engineer-in-Charge mid-project, and ultimately terminated the work without justification. Balaji contended TPA had abandoned the site and failed to complete the work.
Key Facts
- Contract execution date: 08.07.2013
- Contract expiry date: 31.12.2013
- TPA continued work on site until 31.03.2014, beyond contract term
- Balaji engaged a third party to complete work in early 2014
- TPA raised nine claims in arbitration; withdrew Claims 2, 5, 7, and 9
- First Arbitral Award dated 06.08.2019 awarded TPA:
- Claim 1 (murrum filling): Rs. 8.40 lakh
- Claim 3 (RA Bill deductions): Rs. 93.12 lakh
- Claim 4 (miscellaneous): Rs. 1.81 lakh
- Claim 8 (loss of profits): Rs. 1.49 crore
- Balaji challenged the award under Section 34, particularly targeting Claim 8 for lack of evidence
- On 27.02.2020, the Bombay High Court permitted Balaji to seek clarification from the Arbitral Tribunal under Section 34(4)
- Second Arbitral Award dated 05.05.2022 reaffirmed the First Award, with detailed analysis of Claim 8
- TPA’s claim for loss of profits was based on five specific items of work: roofing and cladding of main factory and sugar godown, murrum filling, and related labor/material costs
- TPA submitted affidavits, measurement sheets, procurement bills, and CPWD schedule of rates to substantiate costs
- Balaji failed to cross-examine TPA’s witnesses on key calculations or produce rebuttal evidence on material/labor rates
- Balaji claimed TPA was gainfully employed at a Nashik sugar factory in 2014, but provided no evidence of capacity constraints
Procedural History
- 22.03.2013: Work order issued
- 08.07.2013: Agreement executed
- 31.12.2013: Contract expiry
- 31.03.2014: TPA vacated site after Balaji engaged third party
- 04.06.2018: TPA filed Statement of Claim in arbitration
- 06.08.2019: First Arbitral Award issued
- 27.02.2020: Bombay HC adjourned Section 34 petition under Section 34(4) to allow Tribunal to address evidentiary gaps
- 05.05.2022: Second Arbitral Award issued, reaffirming First Award with detailed reasoning
- 2019 - 2025: Multiple interim applications filed
- 16.03.2026: Judgment reserved
- 08.06.2026: Judgment pronounced
Relief Sought
Balaji sought to set aside the Impugned Award (First and Second Arbitral Awards) on grounds of: (1) lack of evidence for Claim 8 (loss of profits); (2) improper application of Hudson’s formula; (3) failure to permit evidence on all claims during Section 34(4) remand; and (4) perversity in findings. TPA sought enforcement of the award as a decree.
The Legal Issue
The central question was whether a claim for loss of profits is maintainable under the Arbitration and Conciliation Act, 1996, where the contract expired by efflux of time but the parties continued to engage beyond that date, and whether the arbitral tribunal’s detailed, evidence-based computation of such a claim can be set aside under Section 34 merely because the contractor did not seek a declaration of illegal termination.
Arguments Presented
For the Petitioner (Balaji)
Balaji contended that the claim for loss of profits was not arbitrable because: (1) the contract expired on December 31, 2013, extinguishing any right to future performance; (2) TPA had abandoned the site by January 2014 and engaged in other work (Nashik project); (3) TPA failed to produce audited books of accounts to prove actual loss; (4) no contemporaneous claim for loss of profits was made before arbitration; (5) Clause 15 and Clause 44 of the Agreement barred claims for de-scoped work; and (6) the award violated the principles in Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corp. Ltd. by awarding profits without proof of actual loss or market availability of alternative work.
For the Respondent (TPA)
TPA argued that: (1) the contract was not terminated by efflux of time but was effectively extended through conduct, as Balaji continued to issue instructions and delayed providing specifications; (2) TPA remained on site until March 2014 and incurred substantial costs; (3) the Second Arbitral Award meticulously computed the loss using verified measurements, procurement bills, CPWD rates, and expert affidavits; (4) Balaji failed to cross-examine witnesses or rebut evidence, warranting an adverse inference; (5) the claim was not for breach of contract but for loss arising from unilateral withdrawal of work after expenses were incurred; and (6) precedents in Brij Paul Singh, MSK Projects, and Mahanagar Gas Ltd. support awarding loss of profits based on reasonable expectation, not actual loss.
The Court's Analysis
The Court emphasized that Section 34 does not permit reappreciation of evidence or substitution of the arbitral tribunal’s view. The tribunal is the master of facts and evidence, and its findings are binding unless patently illegal or perverse.
The Court examined the Second Arbitral Award’s detailed analysis of Claim 8 and found it to be a model of evidentiary rigor. The tribunal did not rely on theoretical formulae like Hudson’s or Emden’s, but instead conducted a granular, item-wise calculation based on: (1) drawings provided by Balaji’s Engineer; (2) verified area measurements accepted by Balaji; (3) actual procurement bills for murrum from a Goa supplier; (4) CPWD labor rates; and (5) statutory royalty rates under Karnataka’s Minor Mineral Rules.
"The Learned Arbitral Tribunal has meticulously and methodically assessed evidence and made computations in respect of each sub-ingredient of the claim made towards loss of profits."
The Court rejected Balaji’s argument that TPA’s employment at Nashik negated its claim, noting that a contractor may undertake multiple projects simultaneously. The burden to prove capacity constraints lay with Balaji, which failed to discharge it.
The Court also clarified that Section 34(4) does not mandate a fresh arbitration. The remand was limited to eliminating the specific ground of lack of evidence on Claim 8, not to re-examine all claims. The tribunal acted within its mandate by restricting further evidence to Claim 8 alone.
The Court distinguished Batliboi, noting that case involved delay-induced loss where the contractor failed to prove alternative work availability. Here, the loss arose from unilateral withdrawal of work after expenses were incurred, and the tribunal found a reasonable expectation of profit based on contract terms and conduct.
The tribunal’s finding that cladding of the sugar godown was part of the contract, despite omission in the written terms, was upheld based on Balaji’s own drawings and instructions. The Court affirmed that arbitration tribunals may infer contractual obligations from conduct and correspondence.
The Verdict
The petition was dismissed. The Bombay High Court upheld the Impugned Award in its entirety, including the award of Rs. 1.49 crore for loss of profits, Rs. 93.12 lakh for arbitrary RA Bill deductions, Rs. 8.40 lakh for murrum filling, and Rs. 1.81 lakh for miscellaneous claims. TPA is entitled to execute the award as if it were a decree. The Court directed that all actions be taken upon receipt of the downloaded copy from the Court’s website.
What This Means For Similar Cases
Loss of Profits Requires Reasonable Expectation, Not Actual Loss
- Practitioners may now rely on Brij Paul Singh and MSK Projects to argue that loss of profits is compensable based on reasonable expectation, not proof of actual financial loss
- Contractors need not produce audited books of accounts if they provide credible, itemized evidence of costs and anticipated revenue
- The burden shifts to the employer to rebut such evidence through cross-examination or documentary contradiction
Conduct Beyond Contract Term Can Extend Obligations
- Merely stating a contract expired does not terminate obligations if parties continue to act as if it remains in force
- Issuing instructions, providing drawings, or delaying termination may constitute implied extension
- Arbitral tribunals may infer contractual obligations from conduct, even if unrecorded in writing
Section 34(4) Is Narrow and Targeted
- A remand under Section 34(4) is not a license to reopen the entire arbitration
- The tribunal may limit further evidence to the specific ground identified by the court
- Parties cannot insist on a full rehearing of all claims under the guise of eliminating grounds for setting aside
Evidence Must Be Rebutted, Not Ignored
- Failure to cross-examine on key calculations or submit rebuttal evidence invites adverse inference
- Arbitral awards based on unchallenged affidavits, measurements, and bills are highly resilient under Section 34
- Courts will not interfere where the tribunal has methodically analyzed evidence, even if the claim is substantial






