
The Patna High Court has clarified that renewal of Khas Mahal leases under the Bihar Government Estates (Khas Mahal) Manual requires strict compliance with lease terms, including timely application and continuous possession. The judgment underscores that writ jurisdiction cannot adjudicate disputed questions of fact, particularly when possession and lease compliance are contested.
Background & Facts
The Dispute
The case involves a Khas Mahal lease granted to Bhola Singh in 1939 for 30 years, covering land in Dumra, Sitamarhi. The lease deed provided for renewal, subject to compliance with its terms. The petitioners, descendants of Bhola Singh, claimed entitlement to renewal, while the respondents, heirs of Rama Prasad Verma, asserted possession and sought settlement in their favour.
Procedural History
The dispute progressed through multiple stages:
- 1939: Lease executed in favour of Bhola Singh for 30 years.
- 1955: Rama Prasad Verma (respondent’s predecessor) began paying rent and occupying the land.
- 1962: Verma applied for settlement; revenue authorities recommended cancellation of the original lease.
- 1976: Petitioners applied for renewal, six years after lease expiry.
- 1980-1992: Revenue authorities consistently recommended settlement in favour of Verma’s heirs.
- 1992: Additional Collector recommended renewal for petitioners.
- 1993: Collector, Sitamarhi, rejected renewal and upheld Verma’s claim.
- 1994: Patna High Court set aside the 1993 order in CWJC No. 1554 of 1994 for non-compliance with natural justice.
- 1997: Collector passed a fresh order on remand, rejecting petitioners’ claim.
Relief Sought
The petitioners sought:
- Quashing of the orders dated 21.01.1997 (Collector) and 11.12.1980 (Circle Officer).
- Renewal of the lease for 30 years.
- Restraint on respondents from taking possession of the disputed property.
The Legal Issue
The central question was whether the Collector’s order rejecting lease renewal was valid, given:
- Whether the petitioners’ delayed application for renewal (filed six years after lease expiry) complied with lease terms.
- Whether the disputed possession of the land could be adjudicated in writ jurisdiction.
- Whether the principle of natural justice was violated in the remand proceedings.
Arguments Presented
For the Petitioners
- Relied on clause 14 of the lease deed, which allowed renewal if all terms were complied with.
- Cited The Gait Public Library and Institute v. State of Bihar (1995 (1) PLJR 585) and Hindustan Petroleum Corporation Ltd. v. State of Bihar (1996 (2) PLJR 621) to argue that forcible possession by the state was illegal.
- Contended that the Collector lacked power to review the Additional Collector’s order.
For the Respondents
- Argued that the petitioners abandoned the land and failed to apply for renewal within the lease period.
- Submitted that Rama Prasad Verma was in continuous possession since 1955, as evidenced by revenue records and electricity bills.
- Distinguished the cited precedents, noting that those cases involved undisputed possession, unlike the present dispute.
The Court's Analysis
The Court examined the Bihar Government Estates (Khas Mahal) Manual and the lease deed’s terms, emphasizing the following principles:
-
Timely Application for Renewal: The lease deed required renewal applications to be filed three months prior to expiry. The petitioners’ application in 1976 (six years after expiry) was held to be non-compliant with the lease terms. The Court observed:
"The condition for renewal was clear: an application had to be made three months prior to the expiry of the lease. The petitioners’ application in 1976, long after the lease had expired, cannot be entertained."
-
Possession as a Determinative Factor: The Court relied on revenue records, which consistently showed Rama Prasad Verma’s possession since 1955. The petitioners’ claim of possession was contradicted by:
- Electricity bills paid by Verma.
- Rent receipts issued in Verma’s name.
- Revenue inspections recording Verma’s occupation. The Court held that disputed possession could not be resolved in writ jurisdiction, stating:
"The complicated questions of fact, including possession and compliance with lease terms, cannot be adjudicated in writ proceedings. Such matters must be resolved before a competent civil court."
-
Natural Justice in Remand Proceedings: The Court rejected the petitioners’ argument that the Collector’s order was a review. It held that the 1994 High Court order (remanding the matter for fresh hearing) merged all prior orders, making the 1997 order an original decision after due compliance with natural justice.
-
Precedents Distinguished: The Court distinguished Gait Public Library and Hindustan Petroleum, noting that those cases involved undisputed possession and violation of lease terms by the state. Here, the petitioners’ possession was disputed, and the state had acted in accordance with revenue records.
The Verdict
The Patna High Court dismissed the writ petition, upholding the Collector’s order dated 21.01.1997. The Court held that:
- The petitioners’ delayed application for renewal was non-compliant with lease terms.
- Disputed questions of possession could not be adjudicated in writ jurisdiction.
- The Collector’s order was valid, as it complied with natural justice and was not a review of prior orders.
What This Means For Similar Cases
Lease Renewal Requires Strict Compliance
- Timely applications are mandatory. Renewal requests filed after lease expiry may be rejected unless the lease deed or government resolutions provide otherwise.
- Possession must be continuous and undisputed. Revenue records, utility bills, and official inspections will be critical in establishing possession.
Writ Jurisdiction Has Limits
- Courts will not adjudicate disputed questions of fact in writ proceedings, particularly in property disputes involving possession and title.
- Practitioners must exhaust civil remedies before approaching writ courts for such matters.
Natural Justice in Administrative Proceedings
- Remand orders by higher courts merge prior orders, requiring fresh adjudication. Administrative authorities must ensure full compliance with natural justice in such cases.
- Procedural irregularities (e.g., non-hearing of parties) can vitiate orders, but subsequent compliance cures such defects.






