
The Bombay High Court’s dismissal of a writ petition against the Council of Architecture reaffirms the limited scope of judicial review in disciplinary matters involving statutory regulatory bodies. This judgment reinforces that courts must defer to expert bodies on technical and professional conduct issues, absent procedural illegality or arbitrariness.
Background & Facts
The Dispute
The petitioner, Shabbir A. Tambawala, purchased four flats in the Tivoli residential complex at Powai, Mumbai, in 2004 based on a layout plan that included a common clubhouse and recreation area. Upon possession in September 2004, he discovered that the actual building did not include these amenities. An email sent by the developer in May 2006 contained a revised layout plan dated 11.05.2004, which omitted the clubhouse and added two additional buildings. The petitioner obtained the original sanctioned plan via RTI and found material discrepancies: the forged plan lacked MCGM officer signatures, showed 12 buildings instead of 10, and bore the signature of Respondent No. 4, Architect Suhas Joshi, on behalf of Respondent No. 3, Hafiz Contractor.
Procedural History
The petitioner filed two complaints against the architects under Chapter VII of the Council of Architecture Rules, 1973:
- 2009: First complaint dismissed by the Council on 22.03.2010
- 2010: Second complaint dismissed on 16.11.2011
- 2013: Writ Petition No. 130 of 2013 filed in Bombay HC, which quashed both dismissals and directed the Council to decide on merits
- 2018: Disciplinary Committee found prima facie violation of Regulation 2(1)(iv), (x), and (xii) of the Architects (Professional Conduct) Regulations, 1989
- 2019: Full Council of the Council of Architecture dismissed the complaint, holding the signature error was inadvertent and directed Respondent No. 4 to apologize
Relief Sought
The petitioner sought quashing of the Council’s 2019 order and demanded removal of Respondents No. 3 and 4 from the Register of Architects, termination of their licenses, and imposition of stricter penalties for professional misconduct.
The Legal Issue
The central question was whether the Bombay High Court could interfere with the Council of Architecture’s finding of no professional misconduct on grounds of alleged forgery and misrepresentation, or whether judicial review permits only scrutiny of procedural legality and not reappreciation of evidence.
Arguments Presented
For the Petitioner
The petitioner’s counsel argued that the revised plan was forged, materially different from the sanctioned plan, and signed by Respondent No. 4 without authority. They relied on Regulation 2(1)(iv), (x), and (xii) of the Architects (Professional Conduct) Regulations, 1989, which prohibit misrepresentation, lack of written agreement, and conduct unbecoming of an architect. They cited the Disciplinary Committee’s report, which found violations, and contended that the Full Council’s dismissal without imposing penalties was irrational and contrary to the evidence.
For the Respondent
The Council and architects contended that the signature on the plan was an inadvertent clerical error - stamped as a "true copy of full occupation certificate" instead of "approved layout plan." Respondent No. 3 claimed he had no involvement after 2009 due to termination of his Special Power of Attorney. Respondent No. 4 admitted the mistake and apologized. They argued that the Council followed due process under the Architects Act, 1972, and that the petitioner’s grievance was contractual, not professional. They relied on Union of India v. P. Gunasekaran to assert that courts cannot act as appellate forums in disciplinary matters.
The Court's Analysis
The Court emphasized that the Council of Architecture is a statutory expert body constituted under the Architects Act, 1972, with specialized knowledge to assess professional conduct. It held that judicial review under Articles 226 and 227 of the Constitution does not permit reappreciation of evidence or substitution of the authority’s opinion with that of the court.
"The High Court is not and cannot act as a second court of first appeal. The High Court can only see whether: (a) the enquiry is held by a competent authority; (b) the enquiry is held according to the procedure prescribed... (f) the conclusion, on the very face of it, is so wholly arbitrary and capricious that no reasonable person could ever have arrived at such conclusion."
The Court noted that the Council had followed all procedural safeguards: the Disciplinary Committee submitted a detailed report, both parties were heard twice, and the Full Council deliberated before concluding that the error was inadvertent and not fraudulent. The absence of malafide intent, the apology tendered, and the lack of any complaint from the housing society further supported the Council’s conclusion.
The Court rejected the petitioner’s argument that the penalty of an apology was inadequate, holding that the quantum of punishment is a matter of discretion for the expert body. The Court found no illegality, arbitrariness, or violation of natural justice. The Council’s decision was neither irrational nor shockingly disproportionate.
The Verdict
The petitioner’s challenge failed. The Bombay High Court dismissed the writ petition, upholding the Council of Architecture’s 2019 order. The Court held that judicial review does not permit reappreciation of evidence in disciplinary proceedings and that the Council’s expert assessment of professional misconduct is entitled to deference absent procedural illegality or arbitrariness.
What This Means For Similar Cases
Judicial Review Is Not an Appeal
- Practitioners must understand that writ petitions against disciplinary bodies like the Council of Architecture, Bar Council, or Medical Council cannot succeed merely by arguing that the penalty was too lenient
- Courts will not substitute their view of the evidence for that of the expert body
- Challenges must focus on procedural flaws, bias, or manifest irrationality - not factual disagreements
Expert Bodies Hold Discretionary Power on Penalties
- Apologies, warnings, or censures may be deemed sufficient penalties even in cases of significant misrepresentation
- The absence of a formal suspension or removal does not automatically render an order invalid
- Petitioners must prove the penalty is so disproportionate that it shocks the conscience, a very high threshold
Documentation and Intent Matter More Than Outcome
- Mere discrepancy between plans does not equate to professional misconduct without proof of intent to deceive
- Inadvertent errors, even if serious, may be remedied by apology and assurance if no malafide is established
- Practitioners should document all communications and approvals to preempt allegations of forgery or misrepresentation






