
The Madras High Court has clarified that while delays in filing Section 34 petitions under the Arbitration and Conciliation Act are not excused lightly, substantial delays in commercial litigation may be condoned if reasonable grounds are shown and appropriate costs are imposed. This ruling reinforces the balance between procedural rigor and substantive justice in arbitration enforcement.
Background & Facts
The Dispute
The applicant, Akshaya Private Limited, sought to challenge an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. The award was dated 28.07.2024, making the last date for filing the petition 28.10.2024 under the 90-day limitation period prescribed by Section 34(3). The applicant filed papers on 28.01.2025, but the Registry returned them for defects. The corrected petition was re-filed on 24.10.2025 - 231 days after the original filing and 27 days beyond the statutory deadline.
Procedural History
- 28.07.2024: Arbitral award pronounced
- 28.01.2025: Petition under Section 34 filed with award, vakalath, and court fees
- 07.02.2025: Registry returned papers citing defects
- 24.10.2025: Corrected petition re-filed
- 21.01.2026: Application for condonation of delay heard
- 29.01.2026: Court allowed application on terms
Relief Sought
The applicant sought condonation of the 231-day delay in representing the Section 34 petition, arguing that the initial filing on 28.01.2025 constituted a valid commencement of proceedings and that the delay was due to operational exigencies, including ongoing proceedings before the NCLT to prevent corporate liquidation.
The Legal Issue
The central question was whether a delay of 231 days in representing a Section 34 petition - after an initial filing was returned for defects - can be condoned under Section 5 of the Limitation Act, 1963, and whether commercial litigation warrants a stricter standard than ordinary civil suits.
Arguments Presented
For the Petitioner
The petitioner argued that the filing on 28.01.2025 was complete with the petition, vakalath, and court fees, and that the Registry’s return order explicitly referenced the petition’s maintainability, indicating its receipt. The delay in re-filing was attributed to the company’s urgent focus on NCLT proceedings to avoid liquidation, a legitimate commercial exigency. Reliance was placed on S.B.P. & Co. v. Patel Engineering Ltd. for the principle that arbitration law should be interpreted to favor finality and minimal judicial interference.
For the Respondent
The respondent contended that the initial filing on 28.01.2025 was incomplete and non-est under procedural rules, as the petition document itself was allegedly missing. The re-filing on 24.10.2025 was therefore the first valid filing, making the petition time-barred. The respondent emphasized that Section 34(3) is a mandatory limitation period and that condonation under Section 5 is not available for arbitration petitions, citing Bharat Aluminium Co. v. Kaiser Aluminium Technical Services Inc.
The Court's Analysis
The Court examined the Registry’s records and found that the petition, vakalath, and court fees were indeed submitted on 28.01.2025. The return order of 07.02.2025 explicitly commented on the petition’s maintainability, which would be illogical if the petition had not been received. This established that the initial filing was effective, and the delay arose only from the need to correct procedural defects.
"If the Registry could not have returned the papers by commenting on the maintainability of the petition, then the petition must have been presented on 28.01.2025."
The Court acknowledged that Section 34(3) prescribes a strict limitation period, but clarified that Section 5 of the Limitation Act applies to applications for condonation of delay in filing Section 34 petitions, as held in Union of India v. Popular Construction Company. However, the Court emphasized that in commercial litigation, courts must balance procedural fairness with the need for expedition. The 231-day delay was substantial, but the reasons - focused on preventing corporate collapse through NCLT proceedings - were deemed reasonable and not mala fide.
The Court distinguished this from routine civil delays, noting that while leniency is not expected, rigid denial of relief without considering the context would defeat the spirit of arbitration as a speedy dispute resolution mechanism.
The Verdict
The applicant prevailed. The Court held that condonation of delay under Section 5 of the Limitation Act is permissible in Section 34 petitions, provided the reasons are reasonable and the delay is not attributable to negligence. The petition was allowed on the condition that the applicant pays ₹1,50,000 as costs to the respondent.
What This Means For Similar Cases
Initial Filing with Core Documents Constitutes Effective Presentation
- Practitioners must retain proof of submission of petition, vakalath, and court fees - even if returned for defects
- Registry’s return order referencing petition maintainability is strong evidence of effective filing
- Delay arising from correction of procedural defects, not substantive omission, supports condonation
Commercial Litigation Demands Contextual, Not Mechanical, Application of Limitation
- Courts will not automatically reject delays in arbitration petitions due to commercial exigencies
- Corporate survival concerns, such as pending NCLT proceedings, qualify as sufficient cause
- Costs imposed are a calibrated tool to deter frivolous delay without denying substantive rights
Section 5 Applies to Section 34 Petitions - Clarifying a Persistent Ambiguity
- The judgment reaffirms that Section 5 of the Limitation Act governs condonation in arbitration petitions
- Contrary to some lower court rulings, the Madras High Court rejects the notion that arbitration is exempt from Section 5
- Practitioners may now confidently invoke Section 5 in applications for condonation, provided the delay is explained with credible evidence






