
The High Court of Tripura's judgment in NER-II Transmission Ltd. v. Smt Sumitra Debbarma establishes critical boundaries for District Courts adjudicating compensation claims under Section 16(3) of the Indian Telegraph Act, 1885. By distinguishing between quantifiable damage to property and speculative commercial losses, the Court reinforces the principle that statutory compensation mechanisms must remain tethered to their legislative purpose: redressing actual, not hypothetical, harm. This ruling carries significant implications for infrastructure projects where land acquisition and compensation disputes frequently arise.
Background & Facts
The Dispute
The case originated from a transmission line project under the North Eastern Region System Strengthening Scheme-II. The petitioner, NER-II Transmission Ltd., a government company, was granted a transmission license by the Central Electricity Regulatory Commission in 2017 to construct a 400 KV line from Surjyamaninagar to Purba Kanchanbari. This required clearing a rubber plantation owned by the respondent landowners (Smt Sumitra Debbarma and others), whose trees were approximately 10 years old at the time of felling.
Procedural History
The dispute progressed through the following key stages:
- 29.03.2019: Petitioner served notice to respondents regarding tree clearance for transmission line
- 06.04.2022: Respondents filed compensation claim under Section 16(3) of the Telegraph Act, 1885 before the District Judge, West Tripura, seeking Rs. 1.10 crores
- 14.12.2022: District Court proceeded ex-parte against petitioner after repeated non-appearance
- 13.03.2023: Three issues framed, including maintainability and entitlement to compensation
- 14.02.2025: District Court awarded Rs. 64 lakhs (Rs. 46 lakhs for 460 rubber trees + Rs. 18 lakhs for commercial loss)
The Parties' Positions
The respondents claimed:
- 460 rubber trees valued at Rs. 10,000 each (as per Rubber Board assessment)
- Loss of commercial potential due to transmission line restrictions, estimating Rs. 3 lakhs/month in lost lease income
- Procedural violations by petitioner in failing to obtain proper damage assessments
The petitioner, despite being served, deliberately abstained from participating in the District Court proceedings, raising objections only in the revision petition.
The Legal Issue
The High Court confronted two critical questions:
- Whether Section 16(3) of the Telegraph Act, 1885 empowers District Courts to award compensation for speculative commercial losses, or is it limited to actual damage to property?
- Under what circumstances can the High Court interfere with factual findings under Article 227 of the Constitution when a party has willfully abstained from lower court proceedings?
Arguments Presented
For the Petitioner
The petitioner contended that:
- The District Court exceeded its jurisdiction by awarding compensation for speculative commercial losses
- The compensation for rubber trees was arbitrarily calculated without expert assessment
- The petitioner had already paid partial compensation (Rs. 1.41 lakhs and Rs. 2.58 lakhs) through cheques
- The District Court usurped the role of the Telegraph Authority by directly assessing damages
For the Respondents
The respondents argued:
- The ex-parte proceedings were justified due to petitioner's repeated non-appearance
- Uncontroverted evidence (affidavits and Rubber Board rates) established the quantum of damage
- The commercial potential of the land was a direct consequence of the transmission line's restrictions
- The petitioner's delayed objections should not be entertained under Order 9 Rule 7 CPC
The Court's Analysis
The High Court conducted a meticulous examination of the jurisdictional boundaries of District Courts under Section 16(3) of the Telegraph Act, 1885, which provides for compensation when telegraph lines are laid through private property. The Court's reasoning proceeded along three key axes:
- Statutory Interpretation The Court emphasized that Section 16(3) is designed to compensate for actual damage to property, not hypothetical commercial losses. Relying on the principle of ejusdem generis, it held that the provision's scope is limited to:
"The destruction or damage to the property itself, such as trees, crops, or structures, and not to the loss of potential income that might have been generated from the property's commercial exploitation."
The Court distinguished between:
- Quantifiable damage (460 rubber trees at Rs. 10,000 each)
- Speculative loss (alleged Rs. 3 lakhs/month commercial income)
- Procedural Fairness and Waiver The Court expressed strong disapproval of the petitioner's conduct, noting:
- Deliberate abstention from District Court proceedings despite proper service
- Failure to cross-examine respondent witnesses or adduce contrary evidence
- No explanation for non-participation, despite being a government entity
The Court invoked the principle that waiver of procedural rights (such as the right to contest evidence) cannot later be used to challenge factual findings:
"The petitioners, being a government company, cannot now be permitted to raise objections that they could have, but deliberately chose not to, raise before the District Court."
- Scope of Article 227 Review The Court reiterated the limited scope of Article 227, citing Estralla Rubber v. Dass Estate (P) Ltd. and Garment Craft v. Prakash Chand Goel:
- No appellate jurisdiction: The High Court cannot reappreciate evidence or substitute its judgment
- Interference only for grave injustice: Where findings are perverse or based on no evidence
- Factual findings binding if supported by evidence, even in ex-parte proceedings
Applying this standard, the Court found:
- The Rs. 46 lakh award for rubber trees was supported by uncontroverted evidence and Rubber Board rates
- The Rs. 18 lakh award for commercial loss was speculative and beyond the District Court's jurisdiction
The Verdict
The High Court partly allowed the revision petition:
- Upheld the District Court's award of Rs. 46,00,000 for the destruction of 460 rubber trees, along with 7.5% interest from 06.04.2022
- Set aside the Rs. 18,00,000 awarded for loss of commercial potential, holding that such claims fall outside the jurisdictional ambit of Section 16(3) of the Telegraph Act, 1885
- Criticized the petitioner's conduct, noting that their deliberate non-participation in the lower court proceedings precluded them from challenging factual findings under Article 227
What This Means For Similar Cases
Compensation Must Be Grounded In Actual Damage
Practitioners handling infrastructure compensation claims must now:
- Distinguish between actual damage and speculative losses when framing claims under Section 16(3) of the Telegraph Act, 1885
- Adduce documentary evidence (e.g., government notifications, expert assessments) to support damage claims
- Avoid claiming commercial losses unless the statute expressly provides for such compensation
Procedural Participation Is Non-Negotiable
The judgment reinforces that:
- Ex-parte proceedings create binding factual findings if the non-participating party was duly served
- Failure to cross-examine witnesses waives the right to later challenge their testimony
- Article 227 cannot rescue procedural defaults - parties must exhaust remedies (e.g., Order 9 Rule 7 CPC) at the trial stage
The Limits Of District Court Jurisdiction
- District Courts cannot award compensation for losses not directly tied to physical damage under Section 16(3)
- Speculative claims (e.g., lost business income) require separate legal proceedings, such as suits for tortious interference or breach of contract
- Government entities are held to higher standards of procedural compliance and cannot claim ignorance of legal consequences
The judgment serves as a cautionary tale for infrastructure companies and a roadmap for landowners seeking compensation, emphasizing the importance of evidence-based claims and procedural diligence.






