Case Law Analysis
|Supreme Court of India
Section 61(d) Electricity Act | Depreciation Recovery Cannot Exceed Approved Operational Period : SC Upholds Consumer Protection Over Utility Claims
The Supreme Court ruled that depreciation recovery under electricity tariff regulations is capped by the approved operational period of the asset, even if its technical life extends beyond it. The judgment reinforces consumer protection under Section 61(d) of the Electricity Act, 2003, prioritizing regulatory limits over utility cost recovery demands, impacting tariff determinations for power distribution companies.