
The Bombay High Court's judgment in Oil and Natural Gas Corporation Limited v. Swiber Offshore Construction PTE Limited clarifies the stringent threshold for obtaining post-award interim protection under Section 9 of the Arbitration and Conciliation Act, 1996. The Court dismissed ONGC's petition seeking continuation of a bank guarantee, holding that an unsuccessful party must demonstrate exceptional and compelling circumstances beyond a mere arguable challenge to the arbitral award. The judgment underscores the limited scope of judicial intervention in international commercial arbitrations and the importance of full disclosure in discretionary relief proceedings.
Background & Facts
The Dispute
The petitioner, Oil and Natural Gas Corporation Limited (ONGC), a Maharatna Public Sector Undertaking, entered into a contract (Contract No. MR/OW/MM/MHNRD-II/PL/08/2009) with the respondent, Swiber Offshore Construction PTE Limited (Swiber), a Singapore-incorporated company, on 3 July 2010. The contract, valued at USD 148,200,000, involved offshore construction works, including laying submarine pipelines and modifying offshore platforms in the Bombay High region. Under Clause 6.3.2 of the contract, Swiber was liable to pay liquidated damages for delays, capped at 10% of the contract value (USD 14,820,000), without requiring ONGC to prove actual loss. Clause 6.3.4 mandated Swiber to furnish a bank guarantee for the maximum liquidated damages amount.
Key Facts
- Project Timeline:
- Original completion deadline: 30 April 2011
- First extension granted: 30 June 2011 (ONGC reserved right to liquidated damages)
- Second extension granted: 28 February 2012
- Third extension granted: 30 April 2012
- Final extension granted: 31 May 2012
- Actual completion: 24 May 2012
- Completion Certificate issued: 18 February 2013
- Bank Guarantee:
- Initially issued by ANZ Banking Group on 3 October 2011 for USD 14,820,000
- Replaced by DBS Bank on 3 December 2015 (Reference No. 811-02-0041188)
- Extended validity: Currently up to 15 June 2026
- Arbitral Proceedings:
- Notice of Arbitration invoked by Swiber: 14 September 2015
- Final arguments concluded: August 2023
- Arbitral Award delivered: 30 September 2025 (received by ONGC on 9 October 2025)
- Key Findings:
- Rejected ONGC's claim for liquidated damages
- Directed return of the bank guarantee
- Awarded Swiber a net amount of USD 4,113,200 with 5% interest from the award date
- Each party to bear its own costs
- Key Findings:
Procedural History
- 5 January 2026: ONGC filed a Section 34 petition challenging the Award
- 16 January 2026: ONGC filed an application under Section 36(3) seeking stay of the Award and continuation of the bank guarantee
- 23 January 2026: Matter listed before the Court; parties agreed to hear the Section 34 petition finally
- 15 May 2026: ONGC filed the present Section 9 petition seeking continuation of the bank guarantee
- 1 June 2026: ONGC requested Swiber's liquidators to extend the bank guarantee
- 9 June 2026: Swiber filed its reply opposing the petition
- 11 June 2026: Hearing concluded; judgment reserved
- 15 June 2026: Judgment pronounced dismissing the petition
The Parties' Positions
For the Petitioner (ONGC)
- Contractual Rights: Relied on Clauses 6.3.2 and 6.3.4 of the contract, arguing that liquidated damages were a genuine pre-estimate of loss and did not require proof of actual damage.
- Tribunal's Error: Contended that the Arbitral Tribunal misapplied the law by insisting on proof of actual loss despite the contractual stipulation.
- Inconsistent Findings: Argued that the Tribunal's findings on delay were internally inconsistent, as it could not conclusively determine responsibility for critical delays but still rejected liquidated damages.
- Evidence Ignored: Claimed the Tribunal failed to consider evidence of losses beyond delayed production revenue, including overhead expenses, depreciation, and third-party costs.
- Financial Prejudice: Emphasized Swiber's liquidation (ordered by Singapore High Court on 11 November 2022) and admitted claims of USD 51,224,353.74 in liquidation proceedings, arguing that expiry of the bank guarantee would irreparably prejudice ONGC's recovery prospects.
- Balance of Convenience: Argued that continuation of the guarantee would merely preserve the status quo, while refusal would result in irrecoverable loss of security worth USD 14.82 million.
- Legal Precedent: Cited Home Care Retail Marts (P) Ltd. v. Haresh N. Sanghavi (2026 SCC OnLine SC 670) and ONGC v. Larsen & Toubro Ltd. (2026 SCC OnLine Bom 2861) to argue that post-award interim protection is available even to unsuccessful parties.
For the Respondent (Swiber)
- Non-Disclosure: Alleged that ONGC suppressed material facts, specifically Consent Terms dated 5 September 2016 (recorded by the Court on 8 September 2016), which limited the bank guarantee's validity to 120 days post-award (expiring on 28 January 2026).
- Lack of Urgency: Argued that ONGC delayed filing the Section 9 petition (filed on 15 May 2026, served on 1 June 2026) despite knowing the expiry date (15 June 2026), undermining its claim of urgency.
- No Prima Facie Case: Contended that the Tribunal categorically rejected ONGC's liquidated damages claim after detailed evidence analysis, and ONGC's challenge merely sought reappreciation of evidence, which is impermissible under Section 34.
- International Arbitration: Highlighted that the arbitration was international commercial, limiting the scope of challenge to public policy grounds under Section 34(2A).
- Parallel Proceedings: Argued that ONGC was abusing the judicial process by pursuing identical reliefs (continuation of the bank guarantee) in both the Section 36(3) application and the present Section 9 petition.
- Consent Terms Binding: Emphasized that the Consent Terms were a binding agreement between sophisticated commercial parties, and the Court cannot rewrite them by extending the guarantee beyond the agreed period.
Relief Sought
ONGC sought the following interim reliefs under Section 9:
- Direction to Swiber to continue, renew, or extend the existing bank guarantee (USD 14,820,000) until final disposal of the Section 34 proceedings.
- In the alternative, direction to Swiber to furnish a fresh bank guarantee of equivalent value.
- Any other relief deemed fit by the Court to preserve ONGC's security pending adjudication.
The Legal Issue
The central question was whether Section 9 of the Arbitration and Conciliation Act, 1996 permits an unsuccessful party in arbitration to obtain post-award interim protection (continuation of a bank guarantee) where:
- The arbitral award rejected the underlying claim (liquidated damages) and directed return of the security;
- The parties had agreed to a limited duration for the security post-award; and
- The respondent was under liquidation, raising concerns about irrecoverable prejudice.
The Court's Analysis
The Court conducted a multi-faceted analysis, balancing contractual rights, judicial precedent, and equitable considerations:
1. Threshold for Post-Award Interim Protection
The Court relied on Home Care Retail Marts, which held that an unsuccessful party seeking post-award relief under Section 9 must demonstrate exceptional and compelling circumstances. The Court emphasized:
"The real question is whether the circumstances are so extraordinary that refusal of interim protection would result in a situation which cannot later be corrected even if the challenge succeeds."
The Court found that ONGC failed to meet this threshold, as its challenge, while arguable, did not rise to the level of exceptional circumstances warranting interference with the Award.
2. Non-Disclosure of Consent Terms
The Court criticized ONGC's omission of the Consent Terms in its Section 9 petition, despite relying on them in its Section 36(3) application. It held:
"In matters involving discretionary jurisdiction, a party approaching the Court is expected to place before the Court all material facts, including facts which may not support its own case."
The Consent Terms limited the bank guarantee's validity to 120 days post-award, and their non-disclosure undermined ONGC's claim of urgency and affected the balance of equities.
3. Urgency and Delay
The Court scrutinized ONGC's conduct, noting:
- The Award was received on 9 October 2025;
- ONGC filed the Section 34 petition on 5 January 2026 and the Section 36(3) application on 16 January 2026 (both seeking continuation of the guarantee);
- Yet, ONGC waited until 15 May 2026 to file the Section 9 petition, barely a month before expiry.
The Court held that ONGC's delay in pursuing effective remedies diluted its claim of urgency, stating:
"Delay and urgency do not move together. If a litigant is aware of the facts and consequences, yet allows time to pass before approaching the Court, the Court is entitled to examine whether the urgency is genuine."
4. Scope of the Bank Guarantee
The Court distinguished the purpose of the bank guarantee from ONGC's broader financial exposure:
- The guarantee was specific to liquidated damages under Clauses 6.3.2 and 6.3.4;
- It was not a blanket security for all claims against Swiber;
- Swiber's liquidation, while increasing ONGC's apprehension of irrecoverable loss, did not enlarge the guarantee's scope.
5. Distinguishing ONGC v. Larsen & Toubro
The Court distinguished its earlier judgment in ONGC v. Larsen & Toubro, where continuation of a bank guarantee was directed:
- Partial Admission: In Larsen & Toubro, the Tribunal awarded 35% of liquidated damages to ONGC, creating a crystallized entitlement. Here, the Tribunal rejected the claim entirely.
- No Consent Terms: Larsen & Toubro lacked agreed outer limits for the guarantee's continuation, unlike the Consent Terms in the present case.
- Nature of Prejudice: In Larsen & Toubro, continuation was non-prejudicial and preserved ancillary rights. Here, it would override the Award and Consent Terms.
6. International Commercial Arbitration
The Court noted that the arbitration was international commercial, limiting the challenge to public policy grounds under Section 34(2A). It cautioned against broad interim protection that would effectively review the Award on merits, undermining the legislative policy of minimal judicial intervention.
The Verdict
The Court dismissed the petition, holding:
- ONGC failed to establish exceptional circumstances warranting post-award interim protection under Section 9;
- The bank guarantee's continuation was rejected, and Swiber was not directed to furnish a fresh guarantee;
- The Consent Terms and ONGC's non-disclosure were fatal to its claim;
- No costs were awarded;
- Observations were confined to the Section 9 petition and did not prejudice the pending Section 34 or Section 36(3) proceedings.
What This Means For Similar Cases
Exceptional Circumstances Are Non-Negotiable
The judgment raises the bar for post-award interim relief under Section 9:
- An arguable challenge to the Award is insufficient;
- The applicant must demonstrate circumstances so compelling that refusal of relief would render the challenge proceedings meaningless;
- Financial prejudice alone (e.g., liquidation) is not enough unless tied to specific security under dispute.
Full Disclosure Is Mandatory in Discretionary Relief
- Parties seeking interim protection must disclose all material facts, including adverse agreements (e.g., Consent Terms);
- Non-disclosure can defeat the petition, even if the challenge has merit;
- Courts will scrutinize conduct (e.g., delay) to assess genuine urgency.
Consent Terms Limit Judicial Intervention
- Contractual arrangements between parties bind the Court;
- Where parties agree to an outer limit for security post-award, Courts cannot extend it absent exceptional circumstances;
- Sophisticated commercial parties are expected to understand the implications of such agreements.
Practical Takeaways for Practitioners
-
For Applicants:
- Act promptly: File Section 9 petitions immediately upon receiving an adverse award;
- Disclose fully: Include all agreements affecting the relief sought;
- Focus on specificity: Tie irreparable prejudice to the specific security (not general financial exposure);
- Distinguish precedents: Highlight material differences from cases like Larsen & Toubro.
-
For Respondents:
- Exploit non-disclosure: Argue suppression of material facts as a fatal flaw;
- Emphasize delay: Undermine urgency by pointing to inaction;
- Leverage Consent Terms: Stress binding nature of agreed limits;
- Distinguish awards: Contrast partial admissions (e.g., Larsen & Toubro) with complete rejections (present case).






