Case Law Analysis

Foreign Arbitral Award | Liquidated & Unliquidated Damages Under Foreign Law Enforceable in India : Bombay HC

Bombay HC enforces an ICC award governed by Qatari law, holding that Indian public policy does not override parties' choice of foreign law for damages, including both liquidated and unliquidated claims. The ruling clarifies the scope of enforceability of foreign awards in commercial disputes with international elements.

Cassie News NetworkCassie News Network
Mar 19, 2026, 2:22 AM(Updated: Nov 3, 2026)
•9 min read
Be the first to share in your circle
Foreign Arbitral Award | Liquidated & Unliquidated Damages Under Foreign Law Enforceable in India : Bombay HC

The Bombay High Court has affirmed that a foreign arbitral award granting both liquidated and unliquidated damages is enforceable in India if the underlying contract is governed by foreign law and the award does not violate the fundamental policy of Indian law. This judgment reinforces the principle of minimal judicial interference in international commercial arbitration and upholds party autonomy in contract design.

Background & Facts

The Dispute

The dispute arose from a Memorandum of Understanding (MOU) dated 20.06.2016 between Trading and Agency Services Limited WLL (Petitioner), a Qatari entity, and Ion Exchange (India) Limited (Respondent), an Indian company. Pursuant to the MOU, four Sub-Contracts dated 27.10.2016 were executed for engineering, procurement, installation, and commissioning services related to industrial water recovery projects for Ras Laffan Olefins Company Ltd. and Qatar Chemical Company Limited (collectively, "Main Clients") in Qatar. The Main Clients had entered into lump-sum contracts with Trading and Agency on 20.10.2016 for QAR 106.41 million and QAR 122.97 million respectively.

Key Facts

  • The Sub-Contracts were structured on a back-to-back basis with the Main Client Contracts.
  • Article 3.7.1 of the Sub-Contracts provided for liquidated damages at 1% per week (capped at 5% of subcontract value) for delays in mobilization, work completion, or personnel removal.
  • Article 5.1 provided for indemnification against third-party claims arising from the Sub-Contractor’s breach.
  • Disputes emerged in 2018 when the Main Clients terminated their contracts with Trading and Agency due to delays and quality defects.
  • Trading and Agency terminated the Sub-Contracts with Ion Exchange on a back-to-back basis on 13.05.2018.
  • Ion Exchange initiated ICC arbitration in London as claimant, seeking declarations of breach, reimbursement for design costs, and damages.
  • Trading and Agency filed counterclaims for liquidated damages under Article 3.7.1 and indemnity for settlement payments made to the Main Clients.
  • Trading and Agency settled with the Main Clients for QAR 7 million (approx. USD 1.92 million) and waived a substantial invoice to secure the settlement.

Procedural History

  • 27.10.2016: Execution of four Sub-Contracts under the MOU.
  • 13.05.2018: Termination of Main Client Contracts and back-to-back termination of Sub-Contracts.
  • 2020: ICC arbitration proceedings initiated by Ion Exchange.
  • 27.10.2022: ICC Sole Arbitrator issued the Subject Award.
  • 28.10.2022: Subject Award served on parties.
  • 21.04.2024: Petition filed under Part II of the Arbitration and Conciliation Act, 1996, seeking recognition and enforcement of the Subject Award.
  • 19.01.2026: Judgment reserved.
  • 17.03.2026: Judgment pronounced.

Relief Sought

Trading and Agency sought recognition and enforcement of the Subject Award dated 27.10.2022, which directed Ion Exchange to pay:

  • USD 263,905.80 for unpaid work completed (46% of work, 11% unpaid)
  • USD 349,972.82 as unliquidated damages for settlement paid to Main Clients
  • USD 615,385.88 as liquidated damages under Article 3.7.1
  • USD 312,107.25 as legal costs of arbitration
  • USD 271,562.92 as costs and expenses
  • Total payable by Ion Exchange: USD 978,300.48, with simple interest at 5% per annum from 09.04.2020 until award date, and compounded annual interest at 5% from 26.11.2022 until actual payment.

The Parties' Positions

Ion Exchange contended that the award violated Indian public policy by granting both liquidated and unliquidated damages for the same breach, constituting unjust enrichment and contravening the Indian Contract Act, 1872. It further argued that the award was contrary to Qatari Civil Code, which requires proof of actual damage for indemnity. It also claimed denial of natural justice due to refusal of a hearing adjournment during the 2021 COVID-19 lockdown.

Trading and Agency countered that the damages were distinct: unliquidated damages compensated for settlement paid to Main Clients under Article 5.1, while liquidated damages compensated for contractual delays under Article 3.7.1. It emphasized that Qatari law governed the contract and placed the burden of proving no damage on Ion Exchange, which it failed to discharge.

Can a foreign arbitral award granting both liquidated damages and unliquidated damages be refused enforcement in India under Section 48(2)(b) of the Arbitration and Conciliation Act, 1996, on the ground that it violates the fundamental policy of Indian law, where the underlying contract is governed by foreign law and the damages relate to distinct contractual obligations?

Arguments Presented

For the Appellant/Petitioner

Trading and Agency argued that the Subject Award did not contravene Indian public policy because:

  • The unliquidated damages (USD 349,972.82) compensated for actual settlement payments made to the Main Clients under Article 5.1, an indemnity clause triggered by Ion Exchange’s breach.
  • The liquidated damages (USD 615,385.88) were contractually stipulated under Article 3.7.1 for delays and non-performance, a separate and independent claim.
  • The burden under Qatari Civil Code Article 266 lay on Ion Exchange to prove no damage was suffered, which it failed to discharge.
  • The ICC Arbitrator, as the master of evidence, had properly distinguished between the two heads of damages.
  • Indian courts cannot re-examine the merits of a foreign award under Section 48(2)(b), as clarified in Vijay Karia v. Prysmian Cavi and Shri Lal Mahal Ltd. v. Progetto Grano.
  • Enforcement of the award upholds the parties’ choice of law and forum, a cornerstone of international commercial arbitration.

For the Respondent/State

Ion Exchange contended that:

  • The award violated the fundamental policy of Indian law under Section 74 of the Indian Contract Act, which permits only reasonable compensation, not double recovery.
  • Chunilal Mehta, Fateh Chand, and Kailash Nath establish that liquidated damages are a ceiling, and unliquidated damages cannot be awarded over and above them.
  • The settlement payment to Main Clients was the only loss suffered; awarding liquidated damages on top constituted unjust enrichment.
  • Article 5.1 indemnity was inapplicable as no third-party proceedings were initiated against Trading and Agency.
  • The refusal to adjourn the July 2021 hearing during the pandemic violated natural justice under Section 48(1)(b), as Ion Exchange could not present witnesses or evidence effectively.
  • The award was irrational under Qatari law, which requires proof of damage for indemnity and permits reduction if damages are exaggerated.

The Court's Analysis

The Court undertook a rigorous analysis of Section 48 of the Arbitration and Conciliation Act, 1996, particularly the narrow scope of "public policy of India" under Explanation 2. It emphasized that the Act does not permit a review of the merits of a foreign award, and that the term "fundamental policy of Indian law" must be interpreted restrictively, as held in Vijay Karia, Shri Lal Mahal, and Renusagar.

"One cannot lose sight of the fact that the four Sub-Contracts containing the arbitration agreement were not governed by Indian law. One has to see if the outcome in the Subject Award is fundamentally in conflict with Indian public policy to bring it within the scope of a valid objection under Section 48(2)(b) of the Act."

The Court found that the Learned Arbitral Tribunal had correctly distinguished between two distinct heads of claim: (1) indemnity for settlement paid to third parties (unliquidated damages), and (2) contractual penalties for delay (liquidated damages). The Tribunal held that the breach by Ion Exchange directly caused the termination by the Main Clients, triggering both indemnity under Article 5.1 and liquidated damages under Article 3.7.1.

The Court noted that under Qatari Civil Code Article 266, the burden of proving absence of damage lay on Ion Exchange, which it failed to discharge. The Tribunal’s apportionment of damages - reducing Trading and Agency’s claim from QAR 7 million to QAR 4.5 million - demonstrated careful assessment, not overcompensation.

"The Learned Arbitral Tribunal is the best judge of the quality and quantity of evidence. Multiple grounds on appreciation of evidence have been drafted into the grounds in the Affidavit in Reply but the real ground that was solely pressed on merits is the legal test articulated above."

On the natural justice challenge, the Court held that the refusal to adjourn the July 2021 hearing did not amount to a denial of fair hearing. The Tribunal permitted virtual participation, which was consistent with ICC Rules. Ion Exchange actively participated, filed submissions, and cross-examined witnesses. The request for adjournment was made three months in advance, but the Tribunal reasonably considered that the pandemic’s trajectory was uncertain and virtual hearings were viable.

"A good working test for determining whether a party has been unable to present his case is to see whether factors outside the party's control have combined to deny the party a fair hearing."

The Court concluded that the award did not offend Indian public policy, as it did not involve fraud, corruption, or a violation of basic notions of justice. The award was commercially reasonable, factually grounded, and consistent with the parties’ contractual framework.

The Verdict

The Petition was allowed. The Bombay High Court recognized and enforced the ICC Arbitral Award dated 27.10.2022 as a foreign award enforceable under Section 49 of the Arbitration and Conciliation Act, 1996. Ion Exchange (India) Limited is directed to pay Trading and Agency Services Limited WLL:

  • USD 978,300.48 as the aggregate award amount
  • Simple interest at 5% per annum on USD 349,972.82, USD 615,385.88, USD 312,107.25, and USD 271,562.92 from 09.04.2020 until 26.11.2022
  • Compounded annual interest at 5% on the total sum of USD 978,300.48 from 26.11.2022 until actual payment
  • Compliance with the award is to be effected within 60 days of the judgment.

The Interim Application (L) No. 20707 of 2024 was disposed of.

What This Means For Similar Cases

Foreign Governing Law Overrides Indian Damages Doctrine

  • Practitioners must recognize that Indian courts will not apply Section 74 of the Indian Contract Act to override liquidated damages clauses in contracts governed by foreign law.
  • Where parties choose a foreign jurisdiction and law, Indian courts will enforce arbitral awards even if they award both liquidated and unliquidated damages, provided the award is factually grounded and the damages relate to distinct contractual obligations.
  • The burden shifts to the resisting party to prove that the award violates the "fundamental policy" of Indian law - a high threshold.

Natural Justice Requires More Than Disagreement with Procedural Rulings

  • A party’s dissatisfaction with an arbitrator’s refusal to adjourn a hearing, even during a pandemic, does not automatically constitute denial of natural justice.
  • Courts will assess whether the party had a reasonable opportunity to present its case - including through virtual means - and whether the outcome was prejudiced.
  • Procedural fairness under Section 48(1)(b) requires a clear showing of prejudice, not mere inconvenience.

Arbitral Tribunals Are Masters of Evidence - Courts Will Not Re-weigh

  • Section 48(2)(b) explicitly bars review of the merits. Courts must not substitute their view of evidence for that of the arbitrator.
  • Even if an award appears generous or complex, enforcement is mandatory unless it is tainted by fraud, corruption, or a clear violation of Indian public policy.
  • Parties should structure contracts with clear, distinct heads of damages to avoid ambiguity and strengthen enforceability in cross-border disputes.

Case Details

Trading and Agency Services Limited WLL v. Ion Exchange (India) Limited

2026:BHC-OS:6744
Judgment
Court
High Court of Judicature at Bombay
Date
17 March 2026
Case Number
Commercial Arbitration Petition No. 214 of 2024
Bench
Somasekhar Sundaresan
Counsel
Pet: Sharan Jagtiani, Sushmita Gandhi, Sanaya Patel, Vedant Chajed, Kritika Garg, Sankalpita Mallik
Res: S. U. Kamdar, Shaheda Madraswala, Devam Singh, Sharanya Sahadevan

Frequently Asked Questions

No, if the damages relate to distinct contractual obligations and the contract is governed by foreign law. Indian courts will not apply Section 74 of the Indian Contract Act to override such awards under Section 48(2)(b) of the Arbitration and Conciliation Act, 1996, unless the award violates the fundamental policy of Indian law, which requires a high threshold of proof.
No. The Indian Contract Act, including Section 74, does not automatically govern contracts where the parties have expressly chosen a foreign governing law. Indian courts must respect party autonomy and enforce foreign awards based on the governing law of the contract, provided they do not contravene the fundamental policy of Indian law.
A denial of natural justice occurs only if a party is deprived of a fair hearing due to factors beyond its control - such as being denied the opportunity to present evidence, cross-examine witnesses, or respond to a critical argument. Mere disagreement with procedural rulings, such as refusal of an adjournment during a pandemic, does not suffice unless it results in actual prejudice to the party’s case.
0

Disclaimer

This article is for informational purposes only and does not constitute legal advice. The views expressed are based on the judgment analysis and should not be taken as professional counsel. Please consult with a qualified attorney for advice specific to your situation.