
The Calcutta High Court has delivered a significant ruling on the jurisdictional scope of Section 42 of the Arbitration and Conciliation Act, 1996, holding that once an application under Part I of the Act is filed before a court, all subsequent applications must be filed before the same court. This judgment clarifies the mandatory nature of Section 42 and its overriding effect on contractual jurisdiction clauses, reinforcing the principle of avoiding multiplicity of proceedings in arbitration matters.
Background & Facts
The Dispute
The case arises from a development agreement dated September 14, 2018, executed between late Biswanath Bhattacharjee (the landowner) and ATK Manor Developers LLP (the developer). The agreement included an arbitration clause for dispute resolution. Following the landowner’s death on June 22, 2020, disputes emerged between his legal heirs (the petitioners) and the respondents (the developer and the executor of the deceased’s will).
The petitioners alleged that the development agreement was executed under fraud and undue influence, as the deceased was visually impaired and in poor health. They contended that the agreement’s terms - allocating only 20,000 sq. ft. of the total 1,93,000 sq. ft. built-up area to the landowner - were grossly disproportionate and unreasonable.
Procedural History
The dispute traversed multiple forums:
- 2020: The respondent No. 2 (executor) filed a probate application (PLA 128 of 2020) and invoked arbitration under Section 21 of the Arbitration Act.
- 2021: The respondent No. 2 filed an application under Section 9 before the Commercial Court at Rajarhat (Misc. ARB Case No. 39 of 2021), seeking interim relief. The court granted an ex-parte injunction restraining the developer from alienating the property.
- 2021: The developer challenged the injunction in an appeal (FMAT 458 of 2021) before the High Court. The Division Bench disposed of the appeal, clarifying that the executor had ostensible authority to represent the estate until the will was invalidated.
- 2022: The petitioners filed an application under Section 9 before the same Commercial Court (Misc. ARB Case No. 78 of 2022), seeking to restrain further construction and alienation of the property.
- 2022: The Chief Justice appointed an arbitrator to adjudicate the dispute between the developer and the executor.
- 2023: The petitioners approached the Supreme Court via a Special Leave Petition, which was disposed of with liberty to intervene in the ongoing arbitration proceedings.
- 2024: The petitioners filed the present applications - AP(COM) 359 of 2024 (for appointment of a new arbitrator) and AP(COM) 607 of 2024 (for termination of the existing arbitrator’s mandate) - before the Calcutta High Court.
Relief Sought
The petitioners sought two primary reliefs:
- Appointment of a new arbitrator to adjudicate their disputes with the respondents, alleging collusion between the existing arbitrator and the respondents.
- Termination of the mandate of the existing arbitrator under Section 14(2) of the Arbitration Act, citing undue delay and failure to act without bias.
The Legal Issue
The central question before the court was whether the Calcutta High Court had jurisdiction to entertain the petitioners’ applications under Section 11(6) (appointment of arbitrator) and Section 14(2) (termination of mandate) of the Arbitration Act, given that the first application under Part I of the Act had already been filed before the Commercial Court at Rajarhat. Specifically, the court had to determine:
- Whether Section 42 of the Arbitration Act mandates exclusive jurisdiction for all subsequent applications once the first application is filed before a court.
- Whether the jurisdiction clause in the development agreement (granting jurisdiction to both the Calcutta High Court and the Commercial Court at Rajarhat) could override the statutory mandate of Section 42.
Arguments Presented
For the Petitioners
The petitioners contended:
- The disputes between the petitioners and the respondents were distinct from those between the developer and the executor, justifying a separate arbitration proceeding.
- The existing arbitrator had failed to act without undue delay, as evidenced by the prolonged pendency of their Section 16 application (challenging the arbitrator’s jurisdiction) and the developer’s failure to file the Statement of Claim (SOC) within the statutory timeline under Section 23(4).
- The arbitrator’s extension of time for filing the SOC, despite the expiry of the six-month period under Section 23(4), was illegal and contrary to the mandatory nature of the provision. They relied on the principle that Section 23(4) is mandatory, and its violation renders the arbitrator de jure unable to perform his functions under Section 14(1)(a).
- The jurisdiction clause in the development agreement allowed them to approach the Calcutta High Court, as it was one of the two courts with jurisdiction.
For the Respondents
The respondents argued:
- The petitioners’ applications were barred under Section 42 of the Arbitration Act, as the first application under Part I (Misc. ARB Case No. 39 of 2021) had been filed before the Commercial Court at Rajarhat. All subsequent applications must therefore be filed before the same court.
- The petitioners had submitted to the jurisdiction of the Commercial Court at Rajarhat by filing their Section 9 application (Misc. ARB Case No. 78 of 2022) and contesting the demurrer application filed by the developer.
- The arbitrator had not acted with undue delay, as the delay in filing the SOC was attributable to the pendency of the Section 16 application and the need to determine whether the petitioners would be impleaded as parties.
- The petitioners were forum shopping by approaching different courts for the same dispute, which was impermissible under Section 42.
The Court's Analysis
The court conducted a detailed analysis of the statutory framework and the factual matrix to resolve the jurisdictional dispute.
Jurisdiction Under Section 42
The court held that Section 42 of the Arbitration Act is mandatory and non-derogable, creating an exclusive jurisdiction for all subsequent applications under Part I once the first application is filed before a court. The provision aims to prevent multiplicity of proceedings and ensure judicial efficiency. The court relied on the Supreme Court’s decision in Ravi Ranjan Developers Pvt. Ltd. v. Aditya Kumar Chatterjee (2022 SCC Online SC 568), which emphasized that Section 42 overrides contractual jurisdiction clauses and binds parties to the court where the first application was filed.
"Section 42 of the Arbitration Act is mandatory. The Section has been enacted to prevent the parties from being dragged into proceedings in different Courts when more than one Court has jurisdiction. Where with respect to any arbitration agreement, any application under Part I of the Act has been made in a Court, that Court alone would have jurisdiction over the arbitral proceedings and all subsequent applications arising out of that agreement."
The court noted that the first application under Part I (Misc. ARB Case No. 39 of 2021) was filed before the Commercial Court at Rajarhat, and the petitioners themselves had submitted to its jurisdiction by filing their Section 9 application (Misc. ARB Case No. 78 of 2022) before the same court. Thus, the Calcutta High Court lacked jurisdiction to entertain the present applications.
Overriding Effect of Section 42
The court rejected the petitioners’ reliance on the jurisdiction clause in the development agreement, which granted jurisdiction to both the Calcutta High Court and the Commercial Court at Rajarhat. It held that Section 42 overrides contractual clauses, and once a party chooses a court for the first application, all subsequent applications must be filed before that court. The court cited Gammon Engineers and Contractors Pvt. Ltd. v. State of West Bengal (2023 SCC Online Cal 2326), which reiterated that Section 42 is binding irrespective of any other law or contractual provision.
Termination of Mandate Under Section 14
The court declined to adjudicate the petitioners’ prayer for termination of the arbitrator’s mandate under Section 14(2), as the Commercial Court at Rajarhat was the exclusive forum for such an application. It noted that the petitioners had an alternative remedy before the Commercial Court to challenge the arbitrator’s orders, including the extension of time for filing the SOC.
The court also observed that the petitioners’ Section 16 application (challenging the arbitrator’s jurisdiction) had been disposed of by the arbitrator, who impleaded them as parties to the proceedings. Thus, their grievance regarding the arbitrator’s delay had been rendered infructuous.
Interpretation of Section 23(4)
The court did not delve into the merits of whether Section 23(4) (timeline for filing the SOC) is mandatory or directory, as the issue was academic in light of its jurisdictional findings. However, it noted that the arbitrator had disposed of the application under Section 25(a) (termination of mandate for failure to file SOC), and the petitioners had not challenged the order before the appropriate forum.
The Verdict
The Calcutta High Court disposed of both applications (AP(COM) 359 of 2024 and AP(COM) 607 of 2024) with the following holdings:
- The court lacked jurisdiction to entertain the applications under Section 42 of the Arbitration Act, as the first application under Part I had been filed before the Commercial Court at Rajarhat.
- The petitioners’ Section 9 application before the Commercial Court and their submission to its jurisdiction precluded them from approaching the High Court for subsequent reliefs.
- The petitioners’ prayer for appointment of a new arbitrator was rejected, as the Supreme Court had already granted them liberty to intervene in the ongoing arbitration proceedings.
- The prayer for termination of the arbitrator’s mandate was held to be non-maintainable before the High Court, as the Commercial Court at Rajarhat was the exclusive forum for such relief.
What This Means For Similar Cases
Section 42 Creates Exclusive Jurisdiction
Practitioners must note that Section 42 of the Arbitration Act mandates exclusive jurisdiction for all subsequent applications under Part I once the first application is filed before a court. This principle applies irrespective of contractual jurisdiction clauses and overrides any agreement between the parties. Key takeaways:
- First Application is Determinative: The court where the first application under Part I is filed becomes the exclusive forum for all subsequent applications, including those under Sections 9, 11, 14, and 34.
- No Forum Shopping: Parties cannot approach different courts for reliefs arising from the same arbitration agreement, even if multiple courts have jurisdiction under the agreement.
- Strategic Filing: Parties must strategically choose the forum for the first application, as it binds all future proceedings.
Jurisdiction Clauses Are Subordinate to Section 42
The judgment reinforces that jurisdiction clauses in arbitration agreements are subordinate to the statutory mandate of Section 42. Even if an agreement grants jurisdiction to multiple courts, the first application filed determines the exclusive forum for all subsequent proceedings. Practitioners should:
- Avoid Contradictory Stands: Parties cannot submit to the jurisdiction of one court in one proceeding and challenge it in another. Such conduct may be viewed as forum shopping and may lead to dismissal of the application.
- Review Agreements Carefully: Draft arbitration clauses to minimize ambiguity about jurisdiction, as Section 42 will override any contractual choice once the first application is filed.
Termination of Mandate Must Be Sought Before the Same Court
Applications for termination of an arbitrator’s mandate under Section 14(2) must be filed before the same court where the first application under Part I was filed. Practitioners should:
- Exhaust Remedies Before the Arbitrator: Before approaching the court, parties must exhaust remedies before the arbitrator, including applications under Section 16 (challenging jurisdiction) or Section 25(a) (termination for failure to file SOC).
- Challenge Orders Promptly: If the arbitrator’s orders (e.g., extension of time for filing SOC) are challenged, such challenges must be filed before the exclusive forum under Section 42.
Multiplicity of Proceedings Is Impermissible
The judgment underscores that multiplicity of proceedings in arbitration matters is impermissible and contrary to the legislative intent of the Arbitration Act. Courts will dismiss applications filed in violation of Section 42, even if the relief sought is otherwise valid. Practitioners should:
- Consolidate Claims: Where multiple disputes arise from the same arbitration agreement, parties should consolidate their claims before the same court to avoid jurisdictional challenges.
- Avoid Parallel Proceedings: Filing parallel applications before different courts for the same dispute may lead to dismissal on jurisdictional grounds and may also attract costs or adverse inferences.






