Arbitral Awards Cannot Be Set Aside For Mere Error Of Fact | Termination For Delay Must Be Justified : Bombay High Court

The Bombay High Court has upheld an arbitral award setting aside termination and penalties, ruling that courts cannot interfere with factual findings unless they are perverse. Loss of profit upon wrongful termination is compensable without proof of actual loss.

Cassie News NetworkCassie News Network
Feb 8, 2026, 1:39 AM(Updated: Nov 3, 2026)
•6 min read
Be the first to share in your circle
Arbitral Awards Cannot Be Set Aside For Mere Error Of Fact | Termination For Delay Must Be Justified : Bombay High Court

The Bombay High Court has reaffirmed the limited scope of judicial interference in arbitral awards, holding that mere disagreement with factual findings or alleged errors in evidence appreciation cannot justify setting aside an award under Section 34 of the Arbitration and Conciliation Act, 1996. The judgment underscores the primacy of party autonomy and the finality of arbitral decisions, particularly in complex infrastructure disputes.

Background & Facts

The Dispute

The dispute arose from the termination of a Rs.212.52 crore sewerage treatment plant contract by the Solapur Municipal Corporation (SMC) against the joint venture contractor M/s. S.M.C.-G.E.C.P. Ltd. (JV). SMC alleged delay in project execution and imposed escalating penalties, ultimately terminating the contract on 9 December 2013 and blacklisting the JV on 11 April 2014. The JV challenged these actions before a sole arbitrator, claiming Rs.25.5 crore in unpaid bills, Rs.6.37 crore in security deposit, Rs.8.7 crore in damages for wrongful termination, and other reliefs.

Procedural History

  • 2012: Contract awarded to JV for 75 MLD STP and sewerage network construction.
  • 2012 - 2013: SMC issued four penalty orders totaling Rs.11.44 lakh per day, citing delay.
  • 9 December 2013: SMC terminated contract without completing contractual period.
  • 11 April 2014: JV blacklisted for alleged sub-contracting and delay.
  • 2014: JV filed Statement of Claim before Arbitral Tribunal.
  • 18 June 2020: Arbitral Tribunal awarded Rs.32.16 crore to JV, setting aside penalties, termination, and blacklisting.
  • 2024: SMC filed CARBP No. 444/2024 to set aside the award; JV filed CARBP No. 252/2024 challenging partial award but later withdrew it.

Relief Sought

SMC sought to set aside the entire arbitral award on grounds of perversity, ignoring vital evidence, and misinterpretation of contract. The JV sought confirmation of the award and recovery of the awarded amount with interest.

The central question was whether the Bombay High Court could interfere with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 merely because it disagreed with the arbitrator’s factual findings on delay, termination, and damages, or whether such interference is permissible only where the award is perverse, based on no evidence, or ignores vital evidence.

Arguments Presented

For the Petitioner (SMC)

SMC contended that the Arbitral Tribunal ignored critical documentary evidence of JV’s delay, including delay in submission of bar charts, non-completion of work, and failure to secure permissions. It argued that the Tribunal wrongly relied on oral admissions of its own witnesses, misapplied Clause 10 (penalty) and Clause 2(a) (compensation), and awarded speculative damages without proof of actual loss. SMC relied on Associate Builders v. DDA, Ssangyong v. NHAI, and OPG Power v. Enexio to argue that the award was patently illegal and perverse.

For the Respondent (JV)

The JV countered that the Tribunal’s findings were based on a comprehensive review of evidence, including admissions by SMC’s own witnesses. It emphasized that the Tribunal did not reappreciate evidence but merely concluded that delay was attributable to SMC’s inaction. The JV relied on A.T. Brij Paul Singh v. State of Gujarat and Dwaraka Das v. State of M.P. to defend the 10% damages award as a reasonable estimate of loss of profit upon wrongful termination, not loss of profitability requiring proof of actual loss.

The Court's Analysis

The Court conducted a meticulous review of the Arbitral Tribunal’s findings across 15 sub-heads of delay, concluding that each was supported by evidence, including admissions by SMC’s witnesses. The Court emphasized that under Section 34, courts cannot act as appellate forums. As held in OPG Power Generation Pvt. Ltd. v. Enexio, interference is permissible only if the award is perverse - i.e., based on no evidence, considers irrelevant factors, or ignores vital evidence.

"An admission in cross-examination, by itself, constitutes best evidence... and though not conclusive is decisive of the matter, unless successfully withdrawn or proved erroneous."

The Court held that SMC’s reliance on letters alleging delay was insufficient to override the Tribunal’s factual findings, especially where its own witnesses admitted to delays in approvals, land acquisition, and infrastructure coordination. The Tribunal’s conclusion that delay was attributable to SMC’s inaction was therefore not perverse.

Regarding penalties, the Court held that since the underlying ground of delay was rejected, the penalty orders lacked legal foundation. The Tribunal’s setting aside of termination and blacklisting followed logically.

On damages, the Court drew a critical distinction between loss of profit and loss of profitability. Citing State Industries Promotion Corporation v. RPP Infra and A.T. Brij Paul Singh, it held that where termination is wrongful, the contractor is entitled to a reasonable percentage of the unexecuted contract value as damages for lost profit - without needing to prove actual loss. The 10% award, based on the tender value (not the higher contract value), was deemed conservative and legally sound.

The Court also upheld the award of Rs.16.45 crore on the RA bill, noting that SMC’s own PMC and officials had certified the amount, and the JV’s challenge to the certified figure did not negate its validity.

The Verdict

The JV won. The Bombay High Court held that an arbitral award cannot be set aside under Section 34 merely for error of fact or disagreement with evidence appreciation, and that wrongful termination entitles a contractor to damages for loss of profit based on a reasonable percentage of unexecuted work, without requiring proof of actual loss. The petition was dismissed, and the award was upheld in full.

What This Means For Similar Cases

Arbitral Findings on Delay Are Final Unless Perverse

  • Practitioners must now argue that factual findings on delay are binding unless they meet the high threshold of perversity under Associate Builders and Ssangyong.
  • Mere absence of documentary proof of delay by the contractor does not invalidate an arbitrator’s finding if oral admissions or circumstantial evidence support it.
  • Letters from the employer alleging delay are not conclusive; they must be tested against evidence led at arbitration.

Damages for Wrongful Termination Are Presumptive

  • In cases of unlawful termination, claimants need not prove actual loss of manpower, machinery, or opportunity - only that termination was unjustified.
  • Courts may award 5 - 15% of unexecuted contract value as damages for loss of profit, as a reasonable proxy for expected earnings.
  • The distinction between ‘loss of profit’ (due to termination) and ‘loss of profitability’ (due to delay) is now firmly established; the former requires no proof of actual loss.

Contractual Interpretation Must Be Plausible, Not Perfect

  • Arbitrators are entitled to interpret contract clauses based on conduct, correspondence, and context - even if the interpretation is not the only possible one.
  • A plausible interpretation of Clause 10 (penalty) versus Clause 2(a) (compensation) cannot be overturned unless it is wholly irrational or contrary to the contract’s plain terms.
  • Pre-bid clarifications that alter tax or cost obligations bind the parties even if not incorporated in the final contract document.

Case Details

Solapur Municipal Corporation v. M/s. S.M.C.-G.E.C.P. Ltd. (J.V.)

PDF
Court
High Court of Judicature at Bombay
Date
06 February 2026
Case Number
CARBP No. 444 of 2024
Bench
Sanjeev V. Marne
Counsel
Pet: M.P. Rao, Vishwanath Patil, Nidhi Chauhan, Akshay Naidu
Res: Shardul Singh, Prerna Gandhi, Anisa Shahapurkar, Ninad Thikekar

Frequently Asked Questions

An arbitral award may be set aside under Section 34 only if it is perverse - that is, based on no evidence, considers irrelevant factors, or ignores vital evidence. Mere error of fact, misappreciation of evidence, or disagreement with the arbitrator’s view is insufficient.
Yes. Once termination is found to be unjustified, the contractor is entitled to damages for loss of profit based on a reasonable percentage of the unexecuted contract value. Actual proof of loss is not required; the entitlement arises from the reasonable expectation of profit inherent in the contract.
Loss of profit arises from wrongful termination, entitling the contractor to compensation for unexecuted work based on a reasonable estimate. Loss of profitability arises from delay, requiring proof of actual loss due to prolonged site presence, blocked resources, or missed opportunities. Only the latter requires evidence of actual financial harm.
Yes. Admissions in cross-examination constitute best evidence and are decisive unless withdrawn or proven erroneous. Arbitrators may rely on such admissions to establish facts, even if the party later disputes them.