
The Madhya Pradesh High Court has reaffirmed that a party cannot raise a jurisdictional challenge to an arbitrator’s authority for the first time at the appellate stage under Section 37 of the Arbitration and Conciliation Act, 1996, if no such objection was raised before the arbitrator or in the Section 34 application. This judgment underscores the importance of procedural finality in arbitration proceedings and the consequences of strategic silence.
Background & Facts
The Dispute
The dispute arose from a works contract dated 1995 for temporary black carpeting at the Sports Complex, T.T. Nagar, Jabalpur, for the Rashtriya Yuva Utsav, 1995. The respondent-contractor, M/s Rock Bed Renovators Ltd., performed the work but was not paid the full amount due. Despite repeated demands, the State of Madhya Pradesh delayed finalizing the bill.
Key Facts
- Work completed under contract issued in 1995
- Final bill remained pending due to administrative delays
- Executive Engineer’s letter dated 18.12.2008 confirmed final bill was pending approval by Superintending Engineer
- Superintending Engineer approved additional payment of Rs. 2,54,389/- on 10.06.2010
- Contractor filed Writ Petition No. 1912/2009 seeking direction for payment
- Contempt Petition No. 275/2010 filed; disposed of on 18.08.2010 with liberty to approach arbitration forum
- Arbitration petition (AC No. 96/2010) filed before High Court on 2010
- High Court appointed sole arbitrator on 05.08.2011; order modified on 09.09.2011
- Arbitrator passed award on 15.09.2012 awarding Rs. 37,88,062/-
- State filed application under Section 34 of the Act on 2015 seeking to set aside the award; dismissed by District Court on 16.12.2015
- State filed Arbitration Appeal No. 9 of 2016 before High Court on 2016
Procedural History
- 1995: Contract executed for temporary black carpeting
- 18.12.2008: Executive Engineer confirms bill pending Superintending Engineer approval
- 27.05.1996: Documents forwarded to Superintending Engineer
- 10.06.2010: Superintending Engineer approves additional payment
- 02.07.2010: Executive Engineer informs contractor of approved amount
- 2009: Contractor files WP No. 1912/2009
- 18.08.2010: Contempt Petition disposed of with liberty to approach arbitration
- 2010: AC No. 96/2010 filed for appointment of arbitrator
- 05.08.2011: High Court appoints arbitrator
- 09.09.2011: Appointment order modified
- 15.09.2012: Sole arbitrator awards Rs. 37,88,062/-
- 2015: State files Section 34 application before District Court
- 16.12.2015: District Court dismisses Section 34 application
- 2016: State files Arbitration Appeal No. 9 of 2016 before High Court
The Parties' Positions
For the Appellant (State of Madhya Pradesh)
- Argued that the arbitration was barred by limitation as the contract was from 1995 and arbitration initiated in 2010
- Contended that the M.P. Madhyastham Adhikaran Adhiniyam, 1983 overrides the Arbitration and Conciliation Act, 1996 per M.P. Rural Road Development Authority v. L.G. Chaudhary Engineers (2018) 10 SCC 826
- Asserted that the contractor failed to approach the Superintending Engineer as required under the contract before initiating arbitration
- Claimed the arbitrator lacked jurisdiction and the award must be set aside under Section 34
For the Respondent (M/s Rock Bed Renovators Ltd.)
- Argued that limitation did not bar the claim as the final approval by Superintending Engineer occurred on 10.06.2010, making the 2010 arbitration timely
- Pointed out that the High Court, in AC No. 96/2010, had already determined the applicability of the 1996 Act
- Highlighted that the State had admitted before the referral court that the Superintending Engineer had taken a decision
- Stated that no jurisdictional objection was raised before the arbitrator or in the Section 34 application
- Relied on Gayatri Project Limited v. MP Road Development Corporation (2025) 10 SCC 750 and Modern Builders v. State of M.P. (2024) 10 SCC 637 to argue that belated objections are not permissible
Relief Sought
The State sought to set aside the arbitrator’s award dated 15.09.2012 and the District Court’s order dated 16.12.2015, arguing that the award was void ab initio due to lack of jurisdiction. The respondent sought dismissal of the appeal and confirmation of the award.
The Legal Issue
Can a party raise a jurisdictional challenge under Section 37 of the Arbitration and Conciliation Act, 1996, based on the applicability of the M.P. Madhyastham Adhikaran Adhiniyam, 1983, when no such objection was raised before the arbitrator or in the Section 34 application?
Arguments Presented
For the Appellant
The State relied on M.P. Rural Road Development Authority v. L.G. Chaudhary Engineers (2018) 10 SCC 826, which held that the M.P. Adhiniyam, 1983 has overriding effect over the 1996 Act for works contracts executed by state engineering departments. It argued that the arbitrator appointed under the 1996 Act lacked jurisdiction, rendering the award void. The State further contended that the contractor’s delay in initiating arbitration (15 years after contract) barred the claim under the Limitation Act, 1963, and that the failure to approach the Superintending Engineer rendered the arbitration premature.
For the Respondent
The contractor countered that the limitation period commenced only on 10.06.2010, when the Superintending Engineer finally approved the bill, making the 2010 arbitration timely. It emphasized that the High Court had already determined the applicability of the 1996 Act in AC No. 96/2010, and that the State had admitted before the referral court that the Superintending Engineer had acted. Crucially, no jurisdictional objection was raised before the arbitrator or in the Section 34 application. The contractor relied on Gayatri Project Limited and Modern Builders, which hold that a party cannot raise jurisdictional objections belatedly at the appellate stage.
The Court's Analysis
The Court examined the timeline of events and the procedural posture of the case. It noted that the State had not objected to the arbitrator’s jurisdiction at any stage prior to the Section 37 appeal. The arbitrator was appointed in 2011, when the prevailing view was that the 1996 Act applied, as per VA Tech Escher Wyass Flovel Ltd. v. M.P. SEB (2011) 13 SCC 261. The Supreme Court’s contrary view in L.G. Chaudhary-II (2018) came years later.
"It is only at this stage that this objection is being raised with vehemence after the judgment in the case of MPRRDA Vs. L.G. Chaudhary Engineers, (2012) 3 SCC 495 was delivered and subsequently in the case of L.G. Choudhary-2 (supra) was delivered in the year 2018."
The Court held that the State’s failure to raise jurisdictional objections before the arbitrator or in the Section 34 application amounted to waiver. The principle of estoppel and the doctrine of finality in arbitration proceedings preclude parties from raising objections at the appellate stage that could and should have been raised earlier.
The Court further noted that the State itself had acknowledged before the referral court that the Superintending Engineer had taken a decision, thereby negating its claim that the contractor had not exhausted contractual remedies. The approval on 10.06.2010 was held to be the date of cause of action, making the 2010 arbitration well within limitation.
The Court also relied on Gayatri Project Limited (2025) 10 SCC 750, which explicitly held that a party cannot raise a jurisdictional challenge under Section 37 if it had remained silent during the arbitration and Section 34 proceedings. The Court emphasized that allowing such belated challenges would undermine the very purpose of arbitration - speed, finality, and party autonomy.
The Verdict
The appeal was dismissed. The High Court upheld the District Court’s order dated 16.12.2015 rejecting the Section 34 application and confirmed the arbitrator’s award dated 15.09.2012 for Rs. 37,88,062/-. The Court held that the State’s jurisdictional objections were barred by delay and procedural waiver. No costs were awarded.
What This Means For Similar Cases
Jurisdictional Objections Must Be Raised Early
- Practitioners must raise jurisdictional challenges under the M.P. Adhiniyam, 1983 or other statutory exclusions at the earliest opportunity - before the arbitrator and in the Section 34 application
- Failure to do so constitutes waiver and bars relief under Section 37
- Strategic silence will not be rewarded; courts will not entertain belated jurisdictional pleas
Finality of Arbitration Awards Is Paramount
- Awards cannot be reopened on grounds that were available but not raised during arbitration
- The doctrine of res judicata by conduct applies even in arbitration
- Parties must assess jurisdictional risks before initiating arbitration and raise objections immediately
Limitation Period Starts at Final Approval, Not Contract Execution
- In delayed payment disputes, limitation begins from the date of final administrative approval, not the date of contract
- Letters confirming pending approvals or partial payments may extend the limitation period
- Practitioners must document all administrative correspondence to establish the true date of cause of action






